TxDOT contract A00217521 bid tabulation
Landscape Development, IH 45 (IH 10 to SL 8(S)). Let by Texas DOT on December 3, 2025, Harris, Houston District. 4 bids received; low bid $2,257,594 by Yellowstone Landscape - Central, Inc., -27% against the engineer's estimate of $3,094,755.
- Owner
- Texas DOT
- Letting
- 03 DEC 2025
- Pay items
- 39
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Yellowstone Landscape - Central, Inc. | $2,257,594 | Low | -27% |
| 2 | Central North Construction, LLC | $2,370,175 | +5.0% | -23% |
| 3 | Texas Wall & Landscape | $3,196,353 | +42% | +3.0% |
| 4 | Jfo Services, LLC | $3,586,118 | +59% | +16% |
Engineer's estimate: $3,094,755.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Yellowstone Landscape - Central, Inc. | 2. Central North Construction, LLC | 3. Texas Wall & Landscape | 4. Jfo Services, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 78 | $750.00 | $341.88 | $200.00 | $350.00 | $515.57 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 78 | $1,050.00 | $982.91 | $300.00 | $500.00 | $832.94 |
| 3 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 78 | $1,550.00 | $1.03 | $400.00 | $800.00 | $1,106.16 |
| 4 | Furn & place topsoil (vehicle) (160-7007) | CY | 390 | $45.00 | $68.38 | $40.00 | $80.00 | $77.57 |
| 5 | Erosion control compost (vehicle) (161-7008) | CY | 926.50 | $30.00 | $44.07 | $40.00 | $45.00 | $77.57 |
| 6 | General use compost (vehicle) (161-7010) | CY | 444.25 | $30.00 | $45.02 | $40.00 | $60.00 | $77.57 |
| 7 | Block sodding (162-7002) | SY | 720 | $6.00 | $5.79 | $6.00 | $10.00 | $7.76 |
| 8 | Fertilizer (166-7001) | ACRE | 0.15 | $1,258.00 | $1,454.14 | $1,500.00 | $2,400.00 | $5,206.65 |
| 9 | Vegetative watering (168-7001) | TGL | 17.88 | $42.00 | $60.59 | $25.00 | $200.00 | $258.60 |
| 10 | Soil amend (type I) (192-7008) | SY | 7,200 | $0.15 | $0.25 | $0.50 | $0.50 | $8.79 |
| 11 | Plant bed preparation (type III) (192-7012) | SY | 7,200 | $0.50 | $0.46 | $1.50 | $8.00 | $5.18 |
| 12 | Plant material (3 gal) (192-7028) | EACH | 364 | $21.00 | $31.14 | $25.00 | $40.00 | $56.89 |
| 13 | Plant material (30 gal) (tree) (192-7039) | EACH | 762 | $300.00 | $170.60 | $225.00 | $300.00 | $429.27 |
| 14 | Plant material (45 gal) (tree) (192-7040) | EACH | 107 | $500.00 | $514.02 | $500.00 | $520.00 | $646.49 |
| 15 | Plant material (65 gal) (tree) (192-7041) | EACH | 788 | $650.00 | $592.22 | $550.00 | $700.00 | $739.59 |
| 16 | Plant material (min 10' TRNK HT)(palm) (192-7066) | EACH | 20 | $1,150.00 | $1,041.67 | $1,200.00 | $1,650.00 | $1,499.87 |
| 17 | Plant material (min 12' TRNK HT)(palm) (192-7067) | EACH | 20 | $1,450.00 | $1,166.67 | $1,800.00 | $1,880.00 | $1,706.75 |
| 18 | Plant material (min 14' TRNK HT)(palm) (192-7068) | EACH | 21 | $1,700.00 | $1,269.84 | $2,100.00 | $2,300.00 | $1,913.63 |
| 19 | Soil amend (type II) (192-7084) | SY | 7,200 | $0.13 | $0.15 | $0.50 | $0.50 | $3.16 |
| 20 | Landscape establish (193-7001) | MO | 18 | $3,850.00 | $6,666.67 | $10,000 | $22,000 | $22,239 |
| 21 | Landscape establish (193-7002) | CYC | 4 | $47,500 | $66,667 | $20,000 | $27,000 | $8,792.32 |
| 22 | Landscape treat (type I) (193-7023) | EACH | 1,657 | $1.00 | $1.08 | $4.00 | $11.00 | $15.52 |
| 23 | Landscape treat (type II) (193-7024) | EACH | 8,285 | $0.35 | $0.34 | $4.00 | $11.00 | $15.52 |
| 24 | Landscape treat (type II) (193-7026) | CYC | 2 | $8,800.00 | $13,033 | $25,000 | $23,000 | $12,930 |
| 25 | Landscape treat (type III) (193-7028) | EACH | 2,021 | $2.00 | $3.17 | $1.00 | $0.25 | $20.69 |
| 26 | Landscape treat (type IV) (193-7029) | EACH | 788 | $75.00 | $48.93 | $180.00 | $120.00 | $87.92 |
| 27 | Landscape treat (type V) (193-7030) | EACH | 869 | $55.00 | $36.70 | $150.00 | $115.00 | $67.24 |
| 28 | Landscape treat (type VI) (193-7031) | EACH | 1,657 | $45.00 | $2.41 | $15.00 | $70.00 | $36.20 |
| 29 | Landscape treat (type VII) (193-7032) | EACH | 1,657 | $1.25 | $23.93 | $5.00 | $75.00 | $20.69 |
| 30 | Landscape treat (type IX) (193-7034) | EACH | 117 | $125.00 | $123.00 | $250.00 | $480.00 | $77.57 |
| 31 | Landscape treat (type X) (193-7035) | EACH | 117 | $250.00 | $239.66 | $300.00 | $680.00 | $181.02 |
| 32 | Landscape treat (type III) (193-7036) | CYC | 4 | $90,500 | $45,833 | $18,000 | $16,000 | $22,757 |
| 33 | Landscape treat (type VII) (193-7040) | CYC | 252 | $2,250.00 | $628.31 | $685.00 | $1,100.00 | $2,120.50 |
| 34 | Mobilization (500-7001) | LS | 1 | $279,385 | $217,564 | $165,006 | $130,000 | $349,962 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $6,500.00 | $2,393.33 | $67,250 | $14,000 | $19,181 |
| 36 | TMA (stationary) (505-7001) | DAY | 110 | $900.00 | $1,230.00 | $200.00 | $1,200.00 | $181.02 |
| 37 | TMA (mobile operation) (505-7003) | DAY | 25 | $750.00 | $1,230.00 | $500.00 | $800.00 | $501.16 |
| 38 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 2,050 | $3.50 | $2.67 | $0.10 | $4.50 | $8.28 |
| 39 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,050 | $1.00 | $0.33 | $0.10 | $2.00 | $4.13 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way