Texas Wall & Landscape: TxDOT bid record
Texas Wall & Landscape submitted 26 bids on Texas DOT contracts in the data, from 04 JUN 2020 to 07 MAY 2026, and was the low bidder on 5 of them (19%). When it was not low, its total sat a median +34% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $11,083,709
- Latest bid
- 07 MAY 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 5 | 2 | 40% |
| 2021 | 5 | 2 | 40% |
| 2022 | 3 | 0 | 0% |
| 2023 | 5 | 1 | 20% |
| 2024 | 1 | 0 | 0% |
| 2025 | 5 | 0 | 0% |
| 2026 | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Plant maintenance | 193-6002 | CYC | 11 | 6 (55%) | $9,500.00 | $11,000 |
| Landscape treatment (type 5) | 1022-6005 | EACH | 9 | 6 (67%) | $0.40 | $1.15 |
| TMA (stationary) | 505-7001 | DAY | 20 | 5 (25%) | $675.00 | $230.00 |
| Plant maintenance | 193-6001 | MO | 9 | 5 (56%) | $8,000.00 | $1,800.00 |
| Landscape treat (type III) | 193-7028 | EACH | 7 | 5 (71%) | $0.25 | $2.31 |
| Preparation row (tree) (2" to 12" diameter) | 100-6013 | EACH | 7 | 4 (57%) | $240.00 | $500.00 |
| Plant material (1 gal) (shrub) | 192-7044 | EACH | 6 | 4 (67%) | $8.50 | $11.00 |
| Block sodding | 162-7002 | SY | 21 | 3 (14%) | $6.00 | $6.20 |
| TMA (mobile operation) | 505-7003 | DAY | 16 | 3 (19%) | $800.00 | $291.17 |
| Landscape soil amendment (type II) | 1006-6002 | SY | 13 | 3 (23%) | $0.30 | $0.35 |
| Erosion control compost | 161-6009 | CY | 10 | 3 (30%) | $19.25 | $31.92 |
| Landscape treatment(type 4) | 1022-6004 | EACH | 7 | 3 (43%) | $30,000 | $31,952 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Yellowstone Landscape - Central, Inc. | 20 | 12 of 20 |
| Central North Construction, LLC | 14 | 10 of 14 |
| Apex Landscape & Irrigation, LLC | 14 | 11 of 14 |
| Green Sage Services LLC | 6 | 6 of 6 |
| Main Lane Industries LTD. | 4 | 2 of 4 |
| Isi Contracting, Inc. | 3 | 1 of 3 |
| Boyer, Inc. | 2 | 2 of 2 |
| James Construction Group, LLC | 2 | 1 of 2 |
| FNH Construction, LLC | 2 | 0 of 2 |
| B & MS Construction, Inc. | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 MAY 2026 | A00198364 | Houston District | Landscape Development, SH 242 (FM 1488 to East of IH 45) | 7 of 7 | $2,052,617 | +30% |
| 07 APR 2026 | A00217861 | Houston District | Landscape Development, SH 242 (IH 45 to IH 69) | 7 of 7 | $3,293,287 | +117% |
| 03 DEC 2025 | A00217521 | Houston District | Landscape Development, IH 45 (IH 10 to SL 8(S)) | 3 of 4 | $3,196,353 | +42% |
| 06 NOV 2025 | A00216803 | Houston District | LANDSCAPE MAINTENANCE, SH0288 (SH 288 to SH 288) | 4 of 4 | $2,995,982 | +34% |
| 06 NOV 2025 | A00214360 | Houston District | Landscape Development, IH 69 (Chimney Rock Road to Newcastle Drive) | 4 of 5 | $3,423,091 | +42% |
| 08 AUG 2025 | A00214152 | Houston District | Landscape Development, IH 69 (Langley Rd to FM 1960) | 5 of 5 | $2,560,857 | +56% |
| 08 AUG 2025 | A00211270 | Houston District | Landscape Development, IH 69 (Jefferson Street to Buffalo Bayou) | 4 of 5 | $2,375,770 | +31% |
| 05 MAR 2024 | 03243029 | Houston District | SH 146 Landscape development from RED BLUFF RD to HARRIS/GALVESTON COUNTY LINE | 3 of 4 | $2,057,329 | +41% |
| 01 NOV 2023 | 11233014 | Houston District | VA Hike and/or bike from ON SH 96, SH 146, FM 270 & FM 2094 | 4 of 4 | $8,113,862 | +13% |
| 28 JUN 2023 | 06233628 | Houston District | FM 518 Landscape development from RIVERSIDE DRIVE to EAGLE LAKES DRIVE | 2 of 2 | $4,935,163 | +49% |
| 27 JUN 2023 | 06233444 | Houston District | SH 6 Landscape development from VOSS ROAD to SH 6 | 3 of 3 | $2,625,575 | +80% |
| 05 MAY 2023 | 05233214 | Houston District | FM 1960 Hazard elimination & safety from 0.369 MI E OF IH 45 to 0.179 MI W OF LEE RD | 3 of 4 | $6,760,891 | +32% |
| 05 MAY 2023 | 05233216 | Houston District | IH 45 Landscape development from IH 10 to GALVESTON COUNTY LINE | 1 of 2 | $5,862,272 | Low, 33% under the second |
| 07 SEP 2022 | 09223018 | Houston District | IH 69 Landscape development from 0.094 WEST OF READING RD to GREATWOOD PARKWAY | 2 of 2 | $1,146,747 | +43% |
| 04 AUG 2022 | 08223255 | Houston District | VA Construct new 5 ft sidewalks along city owned rds from VARIOUS LOCATIONS IN SOUTH HOUSTON | 2 of 9 | $1,134,513 | +2.0% |
| 07 APR 2022 | 04223205 | Houston District | FM 1488 Hazard elimination & safety from IH 45 to MOSTYN DRIVE | 3 of 7 | $11,646,664 | +14% |
| 04 NOV 2021 | 11213222 | Houston District | US 290 Landscape development from BLASINGAME/OLD HOWTH RD (W OF SH 6) to WALLER/HARRIS COUNTY LINE | 3 of 4 | $4,491,283 | +43% |
| 02 JUL 2021 | 07213230 | Houston District | IH 610 Landscape development from IH 69 WEST to IH 10 WEST | 1 of 4 | $1,794,234 | Low, 26% under the second |
| 05 MAY 2021 | 05213031 | Houston District | IH 10 Landscape development from IH 610 LOOP NORTH to CROSSTIMBERS STREET | 1 of 2 | $655,025 | Low, 70% under the second |
| 08 APR 2021 | 04213214 | Houston District | SL 8 Landscape development from NORTH GARDEN STREET to HOLLISTER ROAD | 2 of 5 | $3,937,732 | +5.0% |
| 07 APR 2021 | 04213004 | Houston District | SH 99 Landscape development from BOUDREAUX to SPRING CREEK (HARRIS/MONTGOMERY C/L | 3 of 6 | $2,735,539 | +15% |
| 03 SEP 2020 | 09203030 | Houston District | FM 2759 Construct noise barrier from MIDDLE BAYOU TO SANSBURY BLVD | 1 of 13 | $1,285,464 | Low, 3.0% under the second |
| 06 AUG 2020 | 08203242 | Houston District | IH 45 Landscape and scenic enhancement from IH 10 to NYACK DRIVE | 2 of 2 | $1,933,639 | +24% |
| 09 JUL 2020 | 07203215 | Houston District | SH 99 Landscape development from EAST OF US 290 to EAST OF SH 249 | 5 of 5 | $4,940,121 | +55% |
| 09 JUL 2020 | 07203245 | Houston District | US 90 Landscape & scenic enhancements from FORT BEND/WALLER COUNTY LINE to FORT BEND/HARRIS COUNTY LINE | 3 of 4 | $711,313 | +32% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.