TxDOT contract A00214360 bid tabulation

Landscape Development, IH 69 (Chimney Rock Road to Newcastle Drive). Let by Texas DOT on November 6, 2025, Harris, Houston District. 5 bids received; low bid $2,411,103 by Green Sage Services LLC, -3.6% against the engineer's estimate of $2,502,398.

Owner
Texas DOT
Letting
06 NOV 2025
Pay items
49
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Green Sage Services LLC$2,411,103Low-4.0%
2Apex Landscape & Irrigation, LLC$2,428,607+1.0%-3.0%
3Central North Construction, LLC$2,781,657+15%+11%
4Texas Wall & Landscape$3,423,091+42%+37%
5Yellowstone Landscape - Central, Inc.$3,709,533+54%+48%
TxDOT contract A00214360: bids by rank

Engineer's estimate: $2,502,398.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Green Sage Services LLC2. Apex Landscape & Irrigation, LLC3. Central North Construction, LLC4. Texas Wall & Landscape5. Yellowstone Landscape - Central, Inc.
1Preparation row (tree remove) (0"-12" diameter) (100-7003)EACH25$550.00$410.00$375.00$750.00$700.00$286.67
2Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH100$620.00$500.00$950.00$1,100.00$500.00
3Preparation row (tree remove) (24"-36" diameter) (100-7005)EACH100$820.00$500.00$1,100.00$1,900.00$1.00
4Erosion control compost (vehicle) (161-7008)CY421.80$30.00$38.00$40.00$28.00$76.00$49.39
5General use compost (vehicle) (161-7010)CY205.40$35.00$45.00$36.00$28.00$83.00$48.69
6Block sodding (162-7002)SY73,775$5.00$4.60$4.75$3.10$8.00$5.31
7Fertilizer (166-7001)ACRE15.30$2,000.00$700.00$2,225.00$800.00$1,064.00$1,285.40
8Vegetative watering (168-7001)TGL1,834$35.00$32.00$31.00$15.00$212.00$49.98
9Irrigation system (type I) (170-7002)EACH1$120,000$395,000$125,000$400,000$300,000$245,521
10Irrigation system (type II) (170-7003)EACH1$25,000$50,000$215,000$37,000$296,667
11Irrigation system (type III) (170-7004)EACH1$15,500$50,000$46,838$16,500$4,583.33
12Irrigation system (miscellaneous) (170-7013)LS1$4,500.00$25,000$42,500$128.00$2,416.67
13Mulch (192-7001)CY10.30$90.00$50.00$28.00$118.00$56.63
14Soil amend (type I) (192-7008)SY3,856$1.00$0.70$0.45$2.00$0.35$0.24
15Plant bed preparation (type II) (192-7011)SY3,856$0.50$4.50$4.00$5.00$4.00$0.20
16Plant bed preparation (type III) (192-7012)SY80$10.00$8.85$15.00$9.00$0.40
17Loose aggregate GRND cover (type I) (192-7024)CY262$230.00$290.00$275.00$278.00$194.02
18Loose aggregate GRND cover (type II) (192-7025)CY97$195.00$150.00$125.00$254.00$185.57
19Plant material (1 gal) (192-7026)EACH509$10.50$10.00$10.00$6.00$6.22
20Plant material (5 gal) (192-7029)EACH18$40.00$33.50$200.00$36.00$19.91
21Plant material (45 gal) (192-7032)EACH20$750.00$520.00$620.00$550.00$470.00$500.00
22Plant material (65 gal) (192-7033)EACH146$1,000.00$590.00$550.00$600.00$530.00$673.52
23Plant material (30 gal) (tree) (192-7039)EACH762$300.00$340.00$280.00$230.00$238.00$218.72
24Plant material (1 gal) (shrub) (192-7044)EACH487$13.00$12.00$10.00$10.00$8.00$8.56
25Soil amend (type II) (192-7084)SY3,856$0.75$3.00$0.40$2.00$0.25$0.14
26Landscape establish (193-7001)MO18$2,000.00$9,700.00$4,800.00$10,000$25,000$14,815
27Landscape establish (193-7002)CYC4$30,000$19,000$15,000$20,000$27,000$67,917
28Landscape treat (193-7022)CYC32$3,000.00$4,000.00$10,000$7,000.00$7,000.00$10,156
29Landscape treat (type I) (193-7023)EACH1,415$1.25$6.00$4.00$1.25$5.00$1.08
30Landscape treat (type II) (193-7024)EACH4,245$0.30$2.50$4.00$0.85$5.00$0.33
31Landscape treat (type I) (193-7025)CYC1$17,000$25,000$12,500$100,000$43,000$133,333
32Landscape treat (type III) (193-7028)EACH1,415$2.25$7.50$1.00$1.00$0.25$3.06
33Landscape treat (type IV) (193-7029)EACH146$125.00$54.00$180.00$40.00$100.00$47.95
34Landscape treat (type V) (193-7030)EACH1$200,000$35,000$47,500$65,000$5,550.00$117,500
35Landscape treat (type VII) (193-7032)EACH795$125.00$38.00$125.00$25.00$70.00$35.64
36Landscape treat (type III) (193-7036)CYC1$5,200.00$28,000$10,000$40,000$19,000$137,500
37Landscape treat (type IV) (193-7037)CYC2$25,000$11,000$10,000$25,000$21,100$29,583
38Landscape treat (type VI) (193-7039)CYC2$90,000$18,500$20,000$28,500$14,700$48,750
39Landscape treat (type VII) (193-7040)CYC2$20,000$19,500$10,000$18,500$3,218.00$47,917
40Class B concrete (miscellaneous) (420-7011)CY32.80$750.00$1,100.00$1,250.00$3,000.00$1,000.00$2,210.37
41Mobilization (500-7001)LS1$221,948$149,000$235,000$130,000$100,000$260,784
42Barricades, signs and traffic handling (502-7001)MO4$9,375.00$6,500.00$11,000$6,200.00$15,900$52,083
43TMA (mobile operation) (505-7003)DAY25$120.00$790.00$1.00$500.00$787.00$2,520.00
44Construction exits (install) (type 1) (506-7020)SY560$30.00$20.00$80.00$10.00$38.00$72.92
45Construction exits (remove) (506-7024)SY560$10.00$8.00$40.00$1.00$32.00$11.31
46Biodegradable erosion control logs (install) (8") (506-7043)LF750$5.50$6.00$9.50$1.00$6.00$3.33
47Biodegradable erosion control logs (remove) (506-7046)LF750$1.50$2.00$3.00$1.00$2.50$0.67
48Landscape pavers (528-7001)SY67$150.00$50.00$200.00$300.00$107.59
49Conduit (PVC) (schedule 40) (4") (bore) (618-7041)LF150$52.00$70.00$50.00$43.00$40.56
TxDOT contract A00214360: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of November 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy