TxDOT contract A00191741 bid tabulation
Construct Pedestrian Infrastructure, FM 3005 (SS 342 (61st Street) to Cove View Blvd). Let by Texas DOT on September 3, 2026, Galveston, Houston District. 7 bids received; low bid $2,086,922 by Castillo Aranda LLC, -4.2% against the engineer's estimate of $2,179,546.
- Owner
- Texas DOT
- Letting
- 03 SEP 2026
- Pay items
- 85
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Castillo Aranda LLC | $2,086,922 | Low | -4.0% |
| 2 | Jfo Services, LLC | $2,259,895 | +8.0% | +4.0% |
| 3 | MBN Enterprises LLC | $2,293,251 | +10% | +5.0% |
| 4 | Ti-Zack Concrete, LLC | $2,396,674 | +15% | +10% |
| 5 | Roman Emperors Road, LLC | $2,520,515 | +21% | +16% |
| 6 | Ser Construction Partners, LLC | $2,933,723 | +41% | +35% |
| 7 | Ragle Construction, Inc. | $3,517,679 | +69% | +61% |
Engineer's estimate: $2,179,546.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Castillo Aranda LLC | 2. Jfo Services, LLC | 3. MBN Enterprises LLC | 4. Ti-Zack Concrete, LLC | 5. Roman Emperors Road, LLC | 6. Ser Construction Partners, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 0.50 | $15,000 | $35,750 | $193,537 | $20,000 | $11,000 | $20,000 | $160,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 151 | $25.00 | $30.00 | $80.63 | $15.00 | $26.42 | $30.00 | $50.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 1,331 | $15.06 | $20.00 | $39.13 | $20.00 | $29.98 | $20.00 | $20.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 128 | $20.00 | $20.00 | $135.34 | $25.00 | $31.17 | $20.00 | $50.00 |
| 5 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 1,460 | $16.00 | $5.00 | $19.43 | $12.00 | $27.33 | $5.00 | $20.00 |
| 6 | Removing stab base and asphalt pavement(0"-16") (105-7129) | SY | 247 | $25.00 | $20.00 | $85.86 | $20.00 | $32.31 | $25.00 | $26.00 |
| 7 | Embankment (final)(OC)(type C) (132-7005) | CY | 200 | $30.00 | $25.00 | $160.22 | $30.00 | $39.90 | $50.00 | $50.00 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 1,777 | $5.00 | $4.00 | $6.58 | $7.00 | $4.49 | $2.00 | $2.40 |
| 9 | Block sodding (162-7002) | SY | 1,777 | $2.97 | $8.00 | $4.21 | $10.00 | $3.69 | $5.00 | $5.80 |
| 10 | Vegetative watering (168-7001) | TGL | 34 | $100.00 | $90.00 | $48.70 | $85.00 | $30.80 | $200.00 | $35.00 |
| 11 | Full - depth repair CRCP (9") (361-7004) | CY | 38 | $965.83 | $150.00 | $764.21 | $950.00 | $773.84 | $1,500.00 | $870.00 |
| 12 | Cut & restore asphalt paving (400-7008) | SY | 1,263 | $150.00 | $130.00 | $65.41 | $110.00 | $108.46 | $160.00 | $140.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 11 | $100.00 | $11.00 | $71.33 | $120.00 | $261.55 | $110.00 | $89.00 |
| 14 | Class A concrete (collar) (420-7008) | EACH | 1 | $1,700.00 | $2,000.00 | $1,791.14 | $2,500.00 | $1,060.50 | $1,500.00 | $1,000.00 |
| 15 | Riprap (concrete)(6 in) (432-7003) | CY | 23 | $750.00 | $450.00 | $708.06 | $800.00 | $773.84 | $560.00 | $497.00 |
| 16 | Riprap (mow strip)(4 in) (432-7013) | CY | 57 | $800.00 | $450.00 | $738.79 | $850.00 | $773.84 | $650.00 | $738.00 |
| 17 | Rail (handrail)(type B) (450-7059) | LF | 1,043 | $164.24 | $120.00 | $104.46 | $145.00 | $104.76 | $180.00 | $89.00 |
| 18 | RC pipe (CL IV)(24 in) (464-7021) | LF | 20 | $135.00 | $150.00 | $206.50 | $150.00 | $220.00 | $220.00 | $107.00 |
| 19 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $2,500.00 | $3,500.00 | $3,852.19 | $3,000.00 | $2,035.00 | $8,000.00 | $1,616.00 |
| 20 | Adjusting manholes (water valve box) (479-7007) | EACH | 2 | $600.00 | $550.00 | $3,113.29 | $2,000.00 | $399.00 | $1,000.00 | $475.00 |
| 21 | Removing structure (set) (496-7004) | EACH | 1 | $500.00 | $400.00 | $632.90 | $1,000.00 | $825.00 | $1,000.00 | $250.00 |
| 22 | Removing structure (pipe) (496-7007) | LF | 7 | $50.00 | $20.00 | $90.42 | $50.00 | $825.00 | $50.00 | $35.00 |
| 23 | Mobilization (500-7001) | LS | 1 | $230,000 | $205,000 | $219,553 | $200,000 | $207,288 | $170,000 | $290,000 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $5,000.00 | $10,150 | $10,637 | $5,000.00 | $4,950.00 | $8,000.00 | $13,000 |
| 25 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $15,000 | $15,276 | $20,000 | $1.10 | $200.00 | $21,600 |
| 26 | TMA (stationary) (505-7001) | DAY | 116 | $200.00 | $250.00 | $219.51 | $200.00 | $1.10 | $250.00 | $543.00 |
| 27 | TMA (mobile operation) (505-7003) | DAY | 10 | $500.00 | $550.00 | $1,142.72 | $260.00 | $1.10 | $250.00 | $887.00 |
| 28 | Sandbags for erosion control (506-7035) | EACH | 500 | $15.00 | $20.00 | $3.14 | $15.00 | $2.75 | $10.00 | $12.00 |
| 29 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,000 | $6.00 | $10.00 | $3.14 | $10.00 | $2.75 | $8.00 | $7.20 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,000 | $2.00 | $1.00 | $1.25 | $2.00 | $2.75 | $2.00 | $1.70 |
| 31 | Colored textured concrete (4") (527-7001) | SY | 746 | $120.00 | $115.00 | $89.85 | $125.00 | $118.88 | $120.00 | $300.00 |
| 32 | Concrete curb (type I) (529-7001) | LF | 887 | $20.64 | $15.00 | $19.25 | $12.00 | $57.96 | $40.00 | $5.90 |
| 33 | Concrete curb (type II) (529-7002) | LF | 3,057 | $20.00 | $8.00 | $20.95 | $10.00 | $57.96 | $30.00 | $36.70 |
| 34 | Concrete curb & gutter (type II) (529-7009) | LF | 95 | $30.00 | $10.00 | $29.54 | $40.00 | $57.96 | $100.00 | $50.00 |
| 35 | Concrete curb (slotted) (529-7013) | LF | 9,098 | $10.00 | $12.00 | $17.16 | $17.50 | $29.15 | $28.00 | $9.40 |
| 36 | Driveways (concrete) (hes) (530-7007) | SY | 1,665 | $120.00 | $130.00 | $98.80 | $120.00 | $117.04 | $150.00 | $160.00 |
| 37 | Concrete sidewalks (4") (531-7001) | SY | 2,036 | $70.00 | $80.00 | $68.46 | $95.00 | $88.95 | $80.00 | $140.00 |
| 38 | Curb ramps (type 1) (531-7015) | SY | 289 | $160.00 | $225.00 | $240.21 | $280.00 | $133.88 | $130.00 | $300.00 |
| 39 | Curb ramps (type 5) (531-7018) | SY | 259 | $250.00 | $225.00 | $236.55 | $280.00 | $133.88 | $150.00 | $300.00 |
| 40 | Curb ramps (type 7) (531-7020) | SY | 10 | $250.00 | $225.00 | $296.64 | $280.00 | $133.88 | $155.00 | $330.00 |
| 41 | Curb ramps (type 21) (531-7023) | SY | 92 | $164.66 | $205.00 | $291.87 | $260.00 | $133.88 | $220.00 | $300.00 |
| 42 | Concrete sidewalks (special) (type B) (531-7030) | SY | 919 | $180.00 | $75.00 | $159.91 | $130.00 | $239.10 | $200.00 | $271.00 |
| 43 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,255 | $35.00 | $40.00 | $34.81 | $45.00 | $30.53 | $50.00 | $36.00 |
| 44 | Remove metal beam guard fence (542-7001) | LF | 1,019 | $5.00 | $10.00 | $7.53 | $8.00 | $6.60 | $8.00 | $5.50 |
| 45 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $300.00 | $250.00 | $295.54 | $500.00 | $256.97 | $240.00 | $294.00 |
| 46 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $7,000.00 | $3,500.00 | $4,766.05 | $3,500.00 | $4,179.52 | $4,000.00 | $4,080.00 |
| 47 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $5,000.00 | $500.00 | $648.41 | $350.00 | $568.61 | $520.00 | $351.00 |
| 48 | Ground box type D (162922) (624-7007) | EACH | 11 | $1,500.00 | $950.00 | $1,066.21 | $1,000.00 | $962.50 | $1,800.00 | $1,050.00 |
| 49 | Aluminum signs (type A) (636-7001) | SF | 516 | $76.89 | $50.00 | $33.86 | $38.00 | $33.00 | $35.00 | $36.00 |
| 50 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $800.00 | $800.00 | $1,017.29 | $1,000.00 | $848.10 | $850.00 | $926.00 |
| 51 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 12 | $800.00 | $800.00 | $1,058.68 | $850.00 | $767.80 | $860.00 | $838.00 |
| 52 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 13 | $850.00 | $1,000.00 | $1,211.71 | $850.00 | $955.90 | $940.00 | $1,043.00 |
| 53 | Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040) | EACH | 12 | $850.00 | $1,250.00 | $1,254.37 | $850.00 | $1,030.70 | $860.00 | $1,125.00 |
| 54 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 4 | $750.00 | $500.00 | $564.47 | $3,000.00 | $463.10 | $200.00 | $506.00 |
| 55 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $100.00 | $300.00 | $106.62 | $500.00 | $82.50 | $30.00 | $90.00 |
| 56 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 17 | $40.00 | $25.00 | $26.31 | $500.00 | $23.07 | $35.00 | $24.00 |
| 57 | Install delineator assembly (D-SY)SZ 1(yflx)SRF (658-7025) | EACH | 55 | $110.00 | $150.00 | $137.77 | $100.00 | $120.81 | $120.00 | $114.00 |
| 58 | Remove delin & object marker assms (658-7078) | EACH | 16 | $10.00 | $20.00 | $25.08 | $85.00 | $29.89 | $30.00 | $18.00 |
| 59 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,750 | $2.00 | $2.00 | $2.51 | $2.00 | $1.10 | $1.50 | $1.20 |
| 60 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,339 | $12.00 | $8.00 | $6.27 | $10.50 | $8.26 | $8.00 | $9.00 |
| 61 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 18 | $1.00 | $1.00 | $1.06 | $10.00 | $0.55 | $2.50 | $0.60 |
| 62 | Reflectorized pavement marking type II (W) (curb) (666-7202) | LF | 1,512 | $1.00 | $3.00 | $3.14 | $2.75 | $2.20 | $2.00 | $2.40 |
| 63 | Reflectorized pavement marking type II (Y)(curb) (666-7221) | LF | 1,447 | $1.00 | $3.00 | $3.14 | $2.75 | $2.20 | $1.20 | $2.40 |
| 64 | Reflectorized pavement marking type II (R&W) 6" (fire lane) (666-7230) | LF | 10 | $25.00 | $30.00 | $3.14 | $100.00 | $27.50 | $10.00 | $30.00 |
| 65 | Pavement sler 4" (666-7346) | LF | 18 | $1.00 | $2.00 | $0.19 | $6.00 | $1.10 | $8.00 | $1.20 |
| 66 | Pavement sler 6" (666-7347) | LF | 717 | $0.90 | $2.00 | $0.24 | $1.00 | $1.10 | $0.25 | $1.20 |
| 67 | Pavement sler 8" (666-7348) | LF | 1,750 | $1.00 | $2.00 | $0.31 | $1.00 | $1.10 | $1.40 | $1.20 |
| 68 | Pavement sler 24" (666-7352) | LF | 2,367 | $5.00 | $3.00 | $0.63 | $2.00 | $2.87 | $3.00 | $3.10 |
| 69 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 265 | $1.80 | $2.00 | $2.20 | $6.00 | $1.10 | $4.00 | $1.20 |
| 70 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 14 | $8.00 | $8.00 | $7.46 | $60.00 | $7.57 | $4.00 | $8.30 |
| 71 | Eliminating existing PM & markers (4") (677-7001) | LF | 109 | $1.00 | $2.00 | $0.37 | $1.50 | $1.10 | $3.00 | $1.20 |
| 72 | Eliminating existing PM & markers (8") (677-7004) | LF | 287 | $2.00 | $2.00 | $0.51 | $2.00 | $1.10 | $4.00 | $1.20 |
| 73 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,703 | $2.00 | $3.00 | $0.63 | $1.40 | $2.20 | $4.00 | $2.40 |
| 74 | Eliminating existing PM & markers (24") (677-7008) | LF | 414 | $5.00 | $5.00 | $1.88 | $3.00 | $4.40 | $4.00 | $4.80 |
| 75 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $60.00 | $150.00 | $25.10 | $150.00 | $122.10 | $100.00 | $134.00 |
| 76 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $60.00 | $150.00 | $31.36 | $150.00 | $122.10 | $100.00 | $134.00 |
| 77 | Pavement surface preparation for marking (4") (678-7001) | LF | 18 | $1.00 | $2.00 | $0.13 | $1.20 | $1.10 | $0.25 | $1.20 |
| 78 | Pavement surface preparation for marking (6") (678-7002) | LF | 717 | $0.90 | $2.00 | $0.19 | $0.60 | $1.10 | $0.75 | $1.20 |
| 79 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,750 | $1.00 | $2.00 | $0.24 | $0.60 | $1.10 | $1.00 | $1.20 |
| 80 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,367 | $0.67 | $2.00 | $0.63 | $1.00 | $1.10 | $1.00 | $1.20 |
| 81 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 1 | $35.00 | $30.00 | $6.27 | $50.00 | $27.50 | $5.00 | $30.00 |
| 82 | Pedestrian detect push button (APS) (688-7001) | EACH | 20 | $922.55 | $1,250.00 | $1,166.56 | $1,200.00 | $1,375.00 | $1,500.00 | $1,500.00 |
| 83 | Removal of ground boxes (690-7006) | EACH | 10 | $300.00 | $500.00 | $188.15 | $160.00 | $115.50 | $1,000.00 | $126.00 |
| 84 | Removal of pedestrian push buttons (690-7030) | EACH | 20 | $150.00 | $200.00 | $94.08 | $100.00 | $55.00 | $500.00 | $60.00 |
| 85 | Solar-powered RRFB (two-way wireless) (6073-7005) | EACH | 18 | $6,622.57 | $10,000 | $8,799.39 | $11,000 | $9,625.00 | $10,000 | $10,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.