Bicycle And Pedestrian Improvements, SL 8 (Briar Forest Drive to Briar Hill Drive). Let by Texas DOT on March 4, 2026, Harris, Houston District. 9 bids received; low bid $2,049,391 by Forde Construction Company, Inc., -46% against the engineer's estimate of $3,780,772.
- Owner
- Texas DOT
- Letting
- 04 MAR 2026
- Pay items
- 36
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Forde Construction Company, Inc. | $2,049,391 | Low | -46% |
| 2 | MBN Enterprises LLC | $2,051,247 | 0.0% | -46% |
| 3 | Icos Management, LLC | $2,288,369 | +12% | -39% |
| 4 | Isi Contracting, Inc. | $2,473,863 | +21% | -35% |
| 5 | MC2 Civil, LLC | $2,736,035 | +34% | -28% |
| 6 | Garret Shields Infrastructure | $2,766,737 | +35% | -27% |
| 7 | Jfo Services, LLC | $2,996,672 | +46% | -21% |
| 8 | Castillo Aranda LLC | $3,212,769 | +57% | -15% |
| 9 | Roman Emperors Road, LLC | $3,371,155 | +64% | -11% |
Engineer's estimate: $3,780,772.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Forde Construction Company, Inc. | 2. MBN Enterprises LLC | 3. Icos Management, LLC | 4. Isi Contracting, Inc. | 5. MC2 Civil, LLC | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 51 | $500.00 | $7,700.00 | $1,000.00 | $1,070.00 | $2,500.00 | $6,000.00 | $500.00 |
| 2 | Preparation row (tree prune and trim) (100-7010) | STA | 6 | $1,000.00 | $6,500.00 | $3,000.00 | $2,675.00 | $3,836.00 | $2,000.00 | $8,000.00 |
| 3 | Removing concrete (riprap) (104-7007) | CY | 120 | $50.00 | $400.00 | $150.00 | $129.00 | $605.00 | $320.00 | $600.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 2,422 | $318.79 | $21.00 | $15.00 | $38.00 | $40.60 | $15.00 | $20.00 |
| 5 | Removing concrete (sawcut) (104-7020) | LF | 333 | $20.00 | $11.00 | $15.00 | $64.00 | $22.80 | $10.00 | $20.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 462 | $6.89 | $145.00 | $20.00 | $64.00 | $16.60 | $75.00 | $40.00 |
| 7 | Embankment (final)(OC)(type B) (132-7003) | CY | 557 | $200.00 | $124.00 | $30.00 | $75.00 | $65.30 | $80.00 | $80.00 |
| 8 | Block sodding (162-7002) | SY | 3,695 | $4.67 | $7.00 | $11.00 | $6.50 | $5.00 | $5.00 | $10.00 |
| 9 | Vegetative watering (168-7001) | TGL | 92.10 | $33.31 | $90.00 | $95.00 | $38.00 | $38.00 | $40.00 | $50.00 |
| 10 | Rdside amenity (removing & reset) (194-7020) | EACH | 195 | $6,000.00 | $975.00 | $100.00 | $4,280.00 | $1,500.00 | $20.00 | $2,000.00 |
| 11 | Struct excavation (pipe) (400-7003) | CY | 541 | $100.00 | $89.00 | $10.00 | $43.00 | $299.00 | $325.00 | $40.00 |
| 12 | Cem stabil BKFL (400-7010) | CY | 97 | $84.11 | $350.00 | $140.00 | $321.00 | $130.00 | $600.00 | $300.00 |
| 13 | Riprap (concrete)(4 in) (432-7001) | CY | 125 | $974.74 | $765.00 | $820.00 | $856.00 | $1,150.00 | $3,000.00 | $1,000.00 |
| 14 | Gabion mattresses (galvanized)(6 in) (459-7005) | SY | 153 | $150.00 | $260.00 | $150.00 | $129.00 | $300.00 | $255.00 | $300.00 |
| 15 | Gabion mattresses (galvanized)(12 in) (459-7007) | SY | 279 | $150.00 | $275.00 | $200.00 | $129.00 | $300.00 | $750.00 | $300.00 |
| 16 | Adjusting manholes & inlets (479-7003) | EACH | 7 | $2,700.00 | $750.00 | $2,000.00 | $4,280.00 | $670.00 | $800.00 | $2,000.00 |
| 17 | Clean existing culverts (480-7001) | EACH | 7 | $5,000.00 | $400.00 | $1,000.00 | $12,840 | $2,000.00 | $800.00 | $2,000.00 |
| 18 | Pipe (PVC) (schedule 80) (8 in) (481-7028) | LF | 3,685 | $130.00 | $38.00 | $200.00 | $22.00 | $75.00 | $70.00 | $150.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $390,000 | $200,000 | $200,000 | $280,000 | $200,000 | $270,000 | $300,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $5,533.15 | $3,500.00 | $3,500.00 | $1.00 | $3,000.00 | $17,500 | $5,000.00 |
| 21 | Portable changeable message sign (503-7001) | DAY | 7 | $79.85 | $500.00 | $300.00 | $642.00 | $201.00 | $150.00 | $100.00 |
| 22 | TMA (stationary) (505-7001) | DAY | 220 | $184.70 | $205.00 | $200.00 | $1.00 | $1,000.00 | $300.00 | $300.00 |
| 23 | Construction perimeter fence (506-7034) | LF | 5,100 | $8.00 | $2.00 | $7.00 | $2.00 | $5.00 | $9.00 | $5.00 |
| 24 | Temporary sediment control fence (install) (506-7039) | LF | 11,040 | $2.48 | $4.50 | $5.00 | $2.00 | $4.04 | $4.00 | $5.00 |
| 25 | Temporary sediment control fence (remove) (506-7041) | LF | 11,040 | $0.68 | $2.00 | $1.00 | $1.00 | $1.62 | $0.50 | $1.00 |
| 26 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 252 | $5.17 | $4.00 | $14.00 | $8.00 | $7.55 | $9.00 | $5.00 |
| 27 | Biodegradable erosion control logs (remove) (506-7046) | LF | 252 | $2.57 | $1.00 | $2.00 | $5.00 | $2.16 | $1.00 | $1.00 |
| 28 | Concrete sidewalks (4") (531-7001) | SY | 2,992 | $63.00 | $75.00 | $95.00 | $86.00 | $62.00 | $100.00 | $150.00 |
| 29 | Curb ramps (type 6) (531-7009) | EACH | 1 | $5,050.00 | $4,500.00 | $3,000.00 | $7,490.00 | $4,200.00 | $2,500.00 | $3,000.00 |
| 30 | Curb ramps (type 7) (531-7010) | EACH | 3 | $4,250.00 | $4,500.00 | $3,000.00 | $8,560.00 | $3,500.00 | $3,500.00 | $3,000.00 |
| 31 | Chain link fence (install) (6') (550-7001) | LF | 200 | $25.00 | $70.00 | $70.00 | $43.00 | $450.00 | $35.00 | $20.00 |
| 32 | Chain link fence (remove) (550-7007) | LF | 200 | $13.00 | $20.00 | $20.00 | $22.00 | $450.00 | $2.00 | $1.00 |
| 33 | Pipe underdrains (type 8) (6") (556-7008) | LF | 1,950 | $45.00 | $35.00 | $80.00 | $43.00 | $55.00 | $80.00 | $100.00 |
| 34 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 75 | $8.70 | $85.00 | $25.00 | $11.00 | $81.00 | $13.00 | $50.00 |
| 35 | Pavement surface preparation for marking (24") (678-7008) | LF | 75 | $0.42 | $29.00 | $2.00 | $11.00 | $27.00 | $0.55 | $50.00 |
| 36 | Relocate pedestrian pole assembly (687-7003) | EACH | 1 | $5,720.00 | $5,000.00 | $7,000.00 | $17,120 | $3,127.00 | $4,000.00 | $3,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.