TxDOT contract A00185000 bid tabulation
Drainage Improvements, Various (Harmon Road to Alum Creek Road). Let by Texas DOT on October 9, 2025, Bastrop, Austin District. 8 bids received; low bid $846,903 by STX Civil, -3.9% against the engineer's estimate of $880,992.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 30
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $846,903 | Low | -4.0% |
| 2 | Beck-Reit & Sons, LTD. | $853,696 | +1.0% | -3.0% |
| 3 | Relmco, Inc. | $855,910 | +1.0% | -3.0% |
| 4 | C. E. Barker, LTD. | $862,933 | +2.0% | -2.0% |
| 5 | Dan Williams Company | $915,623 | +8.0% | +4.0% |
| 6 | Aad Contracting Inc. | $1,012,867 | +20% | +15% |
| 7 | Aaron Concrete Contractors, LLC | $1,086,471 | +28% | +23% |
| 8 | Garret Shields Infrastructure | $1,148,056 | +36% | +30% |
Engineer's estimate: $880,992.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Beck-Reit & Sons, LTD. | 3. Relmco, Inc. | 4. C. E. Barker, LTD. | 5. Dan Williams Company | 6. Aad Contracting Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 8.70 | $20,000 | $19,200 | $4,200.00 | $10,000 | $9,750.00 | $6,000.00 | $10,000 |
| 2 | Removing concrete (wingwall) (104-7028) | CY | 7 | $550.00 | $750.00 | $400.00 | $800.00 | $504.00 | $450.00 | $2,000.00 |
| 3 | Removing concrete (inter art concrete blocks) (104-7044) | SY | 1,081 | $7.30 | $5.00 | $11.00 | $15.00 | $19.60 | $35.00 | $28.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 355.70 | $40.00 | $30.00 | $35.00 | $80.00 | $35.00 | $90.00 | $20.00 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 330.70 | $60.00 | $40.00 | $45.00 | $80.00 | $35.00 | $175.00 | $60.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 1,455 | $5.00 | $4.00 | $7.77 | $8.00 | $3.92 | $3.50 | $10.00 |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,455 | $1.00 | $3.00 | $1.77 | $2.20 | $2.24 | $2.00 | $2.00 |
| 8 | Soil ret BLKT(SL_mod_sand_wldlfe) (169-7026) | SY | 1,455 | $2.00 | $6.00 | $5.00 | $5.75 | $5.60 | $5.30 | $5.00 |
| 9 | Flowable backfill (401-7001) | CY | 9 | $550.00 | $375.00 | $600.00 | $300.00 | $198.80 | $550.00 | $300.00 |
| 10 | Trench excavation protection (402-7001) | LF | 80 | $25.00 | $25.00 | $1.00 | $30.00 | $61.60 | $2.00 | $30.00 |
| 11 | Riprap (stone common)(dry)(8 in) (432-7030) | CY | 659.10 | $170.00 | $180.00 | $155.00 | $165.00 | $194.60 | $235.00 | $180.00 |
| 12 | Gabions (galvanized) (459-7001) | CY | 20.60 | $600.00 | $560.00 | $210.00 | $350.00 | $591.92 | $700.00 | $300.00 |
| 13 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 72 | $450.00 | $500.00 | $488.00 | $796.60 | $543.48 | $600.00 | $500.00 |
| 14 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 62 | $475.00 | $520.00 | $710.00 | $784.00 | $537.99 | $600.00 | $600.00 |
| 15 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 50 | $800.00 | $850.00 | $1,077.00 | $882.00 | $838.26 | $1,180.00 | $1,000.00 |
| 16 | RC pipe (CL III)(18 in) (464-7003) | LF | 123 | $120.00 | $125.00 | $118.00 | $140.00 | $164.08 | $175.00 | $90.00 |
| 17 | RC pipe (CL III)(24 in) (464-7005) | LF | 42 | $185.00 | $140.00 | $124.00 | $172.20 | $177.30 | $215.00 | $110.00 |
| 18 | Wingwall (FW - 0) (HW=7 FT) (466-7149) | EACH | 2 | $22,500 | $17,000 | $13,000 | $12,500 | $32,816 | $17,500 | $25,000 |
| 19 | Wingwall (SW - 0) (HW=6 FT) (466-7205) | EACH | 2 | $17,300 | $15,000 | $12,000 | $12,500 | $32,480 | $17,500 | $20,000 |
| 20 | Clean existing culverts (480-7001) | EACH | 12 | $3,000.00 | $3,500.00 | $300.00 | $3,500.00 | $1,176.00 | $1,300.00 | $2,000.00 |
| 21 | Removing structure (pipe) (496-7007) | LF | 165 | $28.00 | $18.00 | $30.00 | $30.00 | $44.80 | $35.00 | $90.00 |
| 22 | Removing structure (box culvert) (496-7008) | LF | 184 | $165.00 | $100.00 | $50.00 | $50.00 | $64.40 | $45.00 | $75.00 |
| 23 | Remove STR (gabion) (496-7018) | LF | 100 | $125.00 | $30.00 | $35.00 | $40.00 | $35.00 | $12.00 | $60.00 |
| 24 | Mobilization (500-7001) | LS | 1 | $86,000 | $65,000 | $67,000 | $75,000 | $76,500 | $90,000 | $50,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $2,000.00 | $4,000.00 | $1,100.00 | $4,000.00 | $8,120.00 | $7,500.00 | $10,000 |
| 26 | Rock filter dams (install) (type 4) (506-7004) | LF | 600 | $52.00 | $50.00 | $22.00 | $60.50 | $56.00 | $55.00 | $24.00 |
| 27 | Rock filter dams (remove) (506-7011) | LF | 600 | $12.00 | $10.00 | $5.00 | $13.20 | $22.40 | $12.00 | $1.00 |
| 28 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,020 | $6.60 | $8.00 | $4.00 | $6.05 | $22.40 | $5.50 | $4.50 |
| 29 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,020 | $2.00 | $2.00 | $1.00 | $1.10 | $11.20 | $1.00 | $1.00 |
| 30 | Intrlck art concrete BLKS (4001-7001) | SF | 9,728 | $9.00 | $10.00 | $33.33 | $12.00 | $5.88 | $10.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.