Aad Contracting Inc.: TxDOT bid record

Aad Contracting Inc. submitted 75 bids on Texas DOT contracts in the data, from 01 OCT 2020 to 19 MAR 2026, and was the low bidder on 7 of them (9%). When it was not low, its total sat a median +31% above the low bid.

Owner
Texas DOT
Low bid volume
$5,013,824
Latest bid
19 MAR 2026
Data through
19 NOV 2026
75Bids
7Low bids
9Win rate, percent
+31%Median gap to the low bid when not low, 66 bids

By year

YearBidsLow bidsWin rate
2020200%
2021100%
2023400%
202417318%
202533412%
20261800%
Aad Contracting Inc., TxDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Paris District16213%
Lufkin District14214%
San Antonio District900%
Dallas District8225%
Bryan District700%
Austin District5120%
Houston District300%
Waco District300%
Beaumont District200%
Wichita Falls District200%
Tyler District200%
Pharr District200%
Aad Contracting Inc., TxDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Flowable backfill401-7001CY2413 (54%)$250.00$350.00
Biodegradable erosion control logs (remove)506-7046LF1713 (76%)$1.00$1.40
TMA (stationary)505-7001DAY6112 (20%)$350.00$230.00
Temporary sediment control fence (remove)506-7041LF1611 (69%)$1.00$1.00
Remove metal beam guard fence542-7001LF169 (56%)$1.50$3.00
Metal beam guard fence trans (thrie-beam)540-7005EACH108 (80%)$1,350.00$2,140.00
Concrete structure repair (vertical & overhead)429-7007SF237 (30%)$250.00$220.00
Temporary sediment control fence (install)506-7039LF167 (44%)$4.00$4.00
Replace single gdrail terminal post770-7017EACH97 (78%)$65.00$96.00
Replace rail element (W-beam)770-7001LF86 (75%)$18.00$25.00
Realign posts770-7010EACH76 (86%)$20.00$25.00
Tree removal (4" - 12" diameter)752-7005EACH105 (50%)$100.00$150.00
Aad Contracting Inc., TxDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Aad Contracting Inc., TxDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
19 MAR 2026A00219346Paris DistrictDITCH CLEANING AND RESHAPING, US0075 (Various Roadways in to Grayson and Fannin County)3 of 3$297,000+32%
18 MAR 2026A00214342San Antonio DistrictEROSION REPAIR, FM3175 (AT W PRONG ATASCOSA RIVER to AT W PRONG ATASCOSA RIVER)5 of 7$175,656+143%
18 MAR 2026A00218939Atlanta DistrictMETAL BEAM GUARD FENCE REPAIR, US0271 (VARIOUS ROADWAYS to VARIOUS ROADWAYS)2 of 2$197,590+14%
18 MAR 2026A00218464San Antonio DistrictEROSION REPAIR, FM2438 (AT MILL CREEK to AT MILL CREEK)2 of 7$63,916+32%
10 MAR 2026A00218250Houston DistrictBRIDGE DECK REPAIR, US0059 (Various Highways in Fort Bend County to Various Highways in Fort Bend County)2 of 5$421,575+28%
19 FEB 2026A00218062Paris DistrictMETAL BEAM GUARD FENCE REPAIR, IH0030 (Various locations in to Hunt, Rain, Hopkins, Franklin Co.)4 of 4$1,204,275+98%
18 FEB 2026A00217008Lufkin DistrictCABLE BARRIER REPAIR, SH0019 (Trinity County Maintenance to Various Locations)3 of 5$279,315+53%
11 FEB 2026A00216038Wichita Falls DistrictCULVERT REPLACEMENT, FM0368 (FM 0368 to in Archer County)5 of 7$322,919+12%
11 FEB 2026A00217726Lufkin DistrictMETAL BEAM GUARD FENCE REPAIR, US0059 (NACOGDOCHES COUNTY MAINTENANCE SECTION to VARIOUS ROADWAYS)5 of 5$199,034+32%
10 FEB 2026A00219214Bryan DistrictDRAINAGE IMPROVEMENT AND/OR REPAIRS, US0190 (Various to Various)3 of 4$654,825+24%
10 FEB 2026A00218646Bryan DistrictBRIDGE BEAM REPAIR, SH0019 (@ SH 75 to @ SH 75)5 of 7$100,000+74%
04 FEB 2026A00198028Paris DistrictConstruct Pedestrian Infrastructure, BU 271B (E Price St to MLK Dr)5 of 13$818,260+13%
14 JAN 2026A00216266Dallas DistrictBRIDGE JOINT REPLACEMENT, US0380 (0.15 MI WEST OF CR0559 to 1.17 MI WEST OF CR0560)5 of 9$95,590+77%
14 JAN 2026A00214341San Antonio DistrictEROSION REPAIR, FM0466 (AT CORDELL CREEK to AT CORDELL CREEK)7 of 8$107,942+84%
14 JAN 2026A00217987Lufkin DistrictDITCH CLEANING AND RESHAPING, FM2022 (VARIOUS LOCATIONS IN HOUSTON COUNTY to MAINTENANCE SECTION)3 of 5$314,251+23%
14 JAN 2026A00216489Lufkin DistrictTREE TRIMMING AND BRUSH REMOVAL, US0287 (Houston County to VARIOUS LOCATIONS)4 of 4$437,500+62%
05 JAN 2026A00217700Lufkin DistrictMETAL BEAM GUARD FENCE REPAIR, US0059 (SAN JACINTO COUNTY MAINTENANCE SECTION to VARIOUS ROADWAYS)2 of 4$191,550+3.0%
05 JAN 2026A00217725Lufkin DistrictMETAL BEAM GUARD FENCE REPAIR, US0096 (SAN AUGUSTINE COUNTY MAINTENANCE SECTION to VARIOUS ROADWAYS)3 of 4$173,235+43%
17 DEC 2025A00217857San Antonio DistrictBRIDGE SCOUR REPAIR, FM0775 (UNNAMED DRAW to UNNAMED DRAW)6 of 8$92,312+72%
10 DEC 2025A00217375Dallas DistrictREPAIR/REPLACE CONCRETE BARRIER, US0075 (VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION)6 of 7$228,900+155%
24 NOV 2025A00218325Bryan DistrictBRIDGE BEAM REPAIR, IH0045 (Various to Various)8 of 8$244,050+113%
20 NOV 2025A00217804Paris DistrictCONCRETE STRUCTURE REPAIR, SH0019 (Various locations in to Hopkins County)5 of 6$233,333+22%
20 NOV 2025A00217651Paris DistrictDITCH CLEANING AND RESHAPING, US0082 (Various locations in to Lamar, Delta, and Red River Counties)2 of 3$216,500+29%
19 NOV 2025A00217264Fort Worth DistrictTREE TRIMMING AND BRUSH REMOVAL, US0377 (VARIOUS LOCATIONS IN to Hood, Erath and Somervell)11 of 11$370,350+82%
12 NOV 2025A00216530Tyler DistrictBRIDGE RAIL REPAIR, US0080 (VARIOUS BRIDGES to IN THE TYLER DISTRICT)4 of 7$180,827+26%
Aad Contracting Inc.: latest TxDOT bids in the data

How this record was read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way