TxDOT contract A00219214 bid tabulation
DRAINAGE IMPROVEMENT AND/OR REPAIRS, US0190 (Various to Various). Let by Texas DOT on February 10, 2026, Brazos, Bryan District. 4 bids received; low bid $529,711 by BK Field Operations LLC, +24% against the engineer's estimate of $425,932.
- Owner
- Texas DOT
- Letting
- 10 FEB 2026
- Pay items
- 37
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $529,711 | Low | +24% |
| 2 | Blacksmith Ventures LLC | $555,480 | +5.0% | +30% |
| 3 | Aad Contracting Inc. | $654,825 | +24% | +54% |
| 4 | Brazos Paving, Inc. | $745,755 | +41% | +75% |
Engineer's estimate: $425,932.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Blacksmith Ventures LLC | 3. Aad Contracting Inc. | 4. Brazos Paving, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (roadway & channel) (110-7004) | CY | 600 | $30.80 | $24.00 | $10.00 | $20.00 | $80.00 |
| 2 | Embankment (final)(OC)(type D) (132-7011) | CY | 250 | $32.00 | $24.00 | $42.00 | $55.00 | $110.00 |
| 3 | FL BS (CMP in place)(tya GR1-2)(in vehicle) (247-7136) | CY | 400 | $44.00 | $50.00 | $70.00 | $115.00 | $150.00 |
| 4 | Cut & restoring pavement (400-7006) | SY | 300 | $172.00 | $130.00 | $150.00 | $175.00 | $85.00 |
| 5 | Cem stabil BKFL (400-7010) | CY | 400 | $193.60 | $240.00 | $200.00 | $250.00 | $130.00 |
| 6 | Flowable backfill (401-7001) | CY | 50 | $393.60 | $288.00 | $275.00 | $250.00 | $600.00 |
| 7 | Trench excavation protection (402-7001) | LF | 25 | $20.00 | $5.00 | $100.00 | $33.00 | $70.00 |
| 8 | Temporary special shoring (403-7001) | SF | 100 | $40.00 | $5.00 | $50.00 | $33.00 | $500.00 |
| 9 | RC pipe (CL III)(18 in) (464-7003) | LF | 50 | $75.20 | $207.00 | $140.00 | $128.00 | $120.00 |
| 10 | RC pipe (CL III)(24 in) (464-7005) | LF | 100 | $100.00 | $230.00 | $181.00 | $144.00 | $140.00 |
| 11 | RC pipe (CL III)(30 in) (464-7007) | LF | 250 | $160.00 | $267.00 | $217.00 | $180.00 | $170.00 |
| 12 | RC pipe (CL III)(36 in) (464-7009) | LF | 50 | $160.00 | $401.00 | $269.00 | $200.00 | $207.00 |
| 13 | RC pipe (CL III)(42 in) (464-7010) | LF | 100 | $195.20 | $487.00 | $317.00 | $275.00 | $248.00 |
| 14 | RC pipe (CL III)(48 in) (464-7011) | LF | 40 | $288.00 | $600.00 | $376.00 | $320.00 | $300.00 |
| 15 | RC pipe (CL III)(60 in) (464-7013) | LF | 40 | $368.00 | $1,140.00 | $513.00 | $490.00 | $397.00 |
| 16 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 5 | $1,024.00 | $1,140.00 | $1,500.00 | $1,700.00 | $2,000.00 |
| 17 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 5 | $1,172.80 | $1,410.00 | $2,000.00 | $1,900.00 | $2,250.00 |
| 18 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 5 | $1,440.00 | $1,680.00 | $2,500.00 | $2,200.00 | $2,400.00 |
| 19 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 5 | $1,792.00 | $2,280.00 | $2,500.00 | $2,500.00 | $2,650.00 |
| 20 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 5 | $2,080.00 | $2,700.00 | $3,200.00 | $3,000.00 | $2,800.00 |
| 21 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 5 | $2,520.00 | $3,600.00 | $3,200.00 | $3,200.00 | $4,105.00 |
| 22 | Removing & RE - lay pipe (18 in) (472-7004) | LF | 10 | $45.60 | $60.00 | $70.00 | $100.00 | $65.00 |
| 23 | Removing & RE - lay pipe (24 in) (472-7006) | LF | 10 | $72.00 | $65.00 | $90.00 | $100.00 | $70.00 |
| 24 | Removing & RE - lay pipe (30 in) (472-7008) | LF | 10 | $80.80 | $72.00 | $108.00 | $200.00 | $85.00 |
| 25 | Removing & RE - lay pipe (36 in) (472-7011) | LF | 10 | $104.80 | $80.00 | $134.00 | $300.00 | $95.00 |
| 26 | Removing & RE - lay pipe (42 in) (472-7012) | LF | 10 | $104.80 | $90.00 | $156.00 | $300.00 | $105.00 |
| 27 | Removing & RE - lay pipe (48 in) (472-7013) | LF | 10 | $120.00 | $110.00 | $175.00 | $300.00 | $125.00 |
| 28 | Clean existing culverts (480-7002) | CY | 20 | $70.40 | $100.00 | $117.00 | $2,500.00 | $350.00 |
| 29 | Removing structure (set) (496-7004) | EACH | 10 | $288.00 | $100.00 | $250.00 | $1,500.00 | $2,000.00 |
| 30 | Removing structure (wingwall) (496-7005) | EACH | 4 | $2,560.00 | $1,440.00 | $500.00 | $3,000.00 | $3,500.00 |
| 31 | Removing structure (pipe) (496-7007) | LF | 400 | $22.40 | $27.00 | $1.00 | $100.00 | $50.00 |
| 32 | Mobilization (callout) (500-7002) | EACH | 6 | $800.00 | $1.00 | $10,000 | $3,500.00 | $10,000 |
| 33 | TMA (stationary) (505-7001) | DAY | 50 | $240.00 | $1.00 | $400.00 | $450.00 | $1,500.00 |
| 34 | Temporary sediment control fence (install) (506-7039) | LF | 500 | $3.60 | $5.00 | $6.00 | $4.00 | $8.00 |
| 35 | Temporary sediment control fence (remove) (506-7041) | LF | 500 | $1.20 | $3.00 | $1.00 | $1.00 | $4.00 |
| 36 | Driveways (concrete) (530-7006) | SY | 50 | $108.00 | $72.00 | $90.00 | $75.00 | $180.00 |
| 37 | Driveways (base) (530-7015) | SY | 400 | $44.00 | $12.00 | $69.00 | $65.00 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.