Concrete structure repair (vertical & overhead), TxDOT 429-7007
Low bidders on TxDOT contracts carried a median of $185.00 per SF for this item, over the 24 months to 19 NOV 2026, across 265 low bids. Half of all 1,781 bids fell between $150.00 and $290.00.
- Owner
- Texas DOT
- Item
- 429-7007
- Unit
- SF
- Data through
- 19 NOV 2026
TxDOT prints this item as “CONC STR REPAIR (VERTICAL & OVERHEAD)”.
TxDOT has bid this work under more than one code: 4296007 on lettings from 09 JAN 2020 to 09 AUG 2024 (1,192 bids); 4296007001 on lettings from 09 JAN 2020 to 09 JAN 2020 (7 bids); 429-7007 on lettings from 06 NOV 2024 to 19 NOV 2026 (1,819 bids); 429-6007 on lettings from 04 DEC 2024 to 07 JAN 2025 (9 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 36 | 36 | $240.00 | 182 | $272.59 |
| 2021 | 56 | 56 | $180.00 | 279 | $200.00 |
| 2022 | 55 | 55 | $200.00 | 244 | $230.50 |
| 2023 | 57 | 57 | $205.00 | 230 | $260.00 |
| 2024 | 68 | 68 | $200.00 | 325 | $275.00 |
| 2025 | 134 | 132 | $200.00 | 843 | $220.00 |
| 2026 | 126 | 126 | $172.69 | 900 | $200.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 32 | $181.50 | 187 | $200.00 |
| Austin District | 20 | $326.00 | 185 | $250.00 |
| Dallas District | 31 | $160.00 | 171 | $200.00 |
| San Antonio District | 17 | $275.00 | 95 | $210.00 |
| Odessa District | 14 | $182.50 | 94 | $175.00 |
| Paris District | 13 | $200.00 | 93 | $232.00 |
| Amarillo District | 13 | $200.00 | 80 | $209.43 |
| Waco District | 12 | $182.00 | 80 | $200.00 |
| Lufkin District | 15 | $175.00 | 78 | $200.00 |
| Childress District | 6 | $104.00 | 74 | $131.00 |
| Abilene District | 6 | $135.00 | 67 | $152.00 |
| Corpus Christi District | 8 | $283.25 | 63 | $275.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 2 to 50 | 66 | $275.00 |
| 51 to 204 | 66 | $200.00 |
| 204.50 to 760 | 66 | $182.50 |
| 765 to 8,708 | 67 | $125.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Ragle Construction, Inc. | 112 | 59 (53%) |
| BK Field Operations LLC | 56 | 25 (45%) |
| Garret Shields Infrastructure | 114 | 20 (18%) |
| Road Doctors LLC | 35 | 17 (49%) |
| Isi Contracting, Inc. | 38 | 16 (42%) |
| MPB, Inc. | 33 | 15 (45%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 NOV 2026 | A00224304 | Odessa District | 1,500 | $185.00 | $175.50 | $200.00 | 4 | Relmco, Inc. | TxDOT |
| 12 NOV 2026 | A00222854 | Amarillo District | 317 | $170.38 | $215.00 | $225.00 | 7 | Ti-Zack Concrete, LLC | TxDOT |
| 12 NOV 2026 | A00222903 | Dallas District | 82 | $200.00 | $195.00 | $220.00 | 6 | Garret Shields Infrastructure | TxDOT |
| 12 NOV 2026 | A00223438 | Dallas District | 1,700 | $115.00 | $182.50 | $140.00 | 6 | Fireman Excavating, Inc. | TxDOT |
| 04 NOV 2026 | A00223826 | Childress District | 5,431 | $99.00 | $119.00 | $140.00 | 15 | Blacksmith Ventures LLC | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 43.70 | $364.31 | $380.21 | $550.00 | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 03 NOV 2026 | A00211095 | Odessa District | 139 | $180.00 | $300.00 | $231.20 | 7 | The Truesdell Corporation | TxDOT |
| 03 NOV 2026 | A00219553 | Austin District | 945 | $80.00 | $210.00 | $150.00 | 13 | Road Doctors LLC | TxDOT |
| 03 NOV 2026 | A00223831 | Childress District | 3,216 | $94.50 | $150.00 | $140.00 | 15 | Icos Management, LLC | TxDOT |
| 03 NOV 2026 | A00211505 | Amarillo District | 2,433 | $125.00 | $125.00 | $177.00 | 8 | Coppell Construction Co., Inc. | TxDOT |
| 28 OCT 2026 | A00223651 | Lufkin District | 47 | $250.00 | $250.00 | $250.00 | 8 | Blacksmith Ventures LLC | TxDOT |
| 15 OCT 2026 | A00223685 | Paris District | 238 | $240.00 | $240.00 | $250.00 | 11 | 12Twelve Road and Bridge LLC | TxDOT |
| 14 OCT 2026 | A00215965 | Dallas District | 11 | $200.00 | $210.00 | $125.00 | 6 | Garret Shields Infrastructure | TxDOT |
| 14 OCT 2026 | A00222907 | Dallas District | 1,000 | $120.00 | $171.00 | $150.00 | 4 | Jackson Excavation, LLC | TxDOT |
| 14 OCT 2026 | A00218976 | Dallas District | 24 | $280.00 | $300.00 | $120.00 | 3 | Gibson & Associates, Inc. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.