The Truesdell Corporation: TxDOT bid record
The Truesdell Corporation submitted 41 bids on Texas DOT contracts in the data, from 08 APR 2020 to 12 NOV 2026, and was the low bidder on 10 of them (24%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $19,495,491
- Latest bid
- 12 NOV 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 3 | 100% |
| 2022 | 1 | 0 | 0% |
| 2023 | 2 | 2 | 100% |
| 2024 | 1 | 0 | 0% |
| 2025 | 6 | 0 | 0% |
| 2026 | 28 | 5 | 18% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Amarillo District | 7 | 0 | 0% |
| Austin District | 4 | 0 | 0% |
| Beaumont District | 3 | 2 | 67% |
| El Paso District | 3 | 1 | 33% |
| San Angelo District | 3 | 1 | 33% |
| Brownwood District | 3 | 0 | 0% |
| Paris District | 3 | 1 | 33% |
| Fort Worth District | 2 | 0 | 0% |
| Abilene District | 2 | 1 | 50% |
| Odessa District | 2 | 1 | 50% |
| Tyler District | 2 | 0 | 0% |
| Waco District | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Barricades, signs and traffic handling | 502-7001 | MO | 36 | 14 (39%) | $3,850.00 | $5,000.00 |
| Multi-layer polymer overlay | 439-7014 | SY | 14 | 8 (57%) | $34.00 | $53.31 |
| TMA (stationary) | 505-7001 | DAY | 24 | 6 (25%) | $302.50 | $230.00 |
| Temporary sediment control fence (install) | 506-7039 | LF | 16 | 6 (38%) | $5.00 | $4.00 |
| Shot blasting | 483-7016 | SY | 19 | 5 (26%) | $4.00 | $7.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 16 | 5 (31%) | $2.00 | $1.00 |
| Concrete structure repair (vertical & overhead) | 429-7007 | SF | 30 | 4 (13%) | $175.00 | $220.00 |
| Concrete structure repair(deck rep(part depth)) | 429-7003 | SF | 14 | 4 (29%) | $150.00 | $200.00 |
| TMA (mobile operation) | 505-7003 | DAY | 12 | 3 (25%) | $525.00 | $291.17 |
| Riprap (stone protection)(18 in) | 432-7043 | CY | 11 | 3 (27%) | $200.00 | $200.00 |
| Concrete structure repair(clean & coat WTH epoxy) | 429-7001 | SF | 9 | 3 (33%) | $60.00 | $195.00 |
| Riprap (stone protection)(12 in) | 432-7041 | CY | 8 | 3 (38%) | $200.00 | $200.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Gibson & Associates, Inc. | 22 | 15 of 22 |
| Structural Integrity Group LLC | 22 | 12 of 22 |
| Built Right Construction of Oklahoma, LLC | 20 | 5 of 20 |
| Ragle Construction, Inc. | 17 | 7 of 17 |
| Garret Shields Infrastructure | 15 | 4 of 15 |
| Blacksmith Ventures LLC | 15 | 2 of 15 |
| Icos Management, LLC | 15 | 3 of 15 |
| Ti-Zack Concrete, LLC | 12 | 3 of 12 |
| Premier Contractors LLC | 10 | 5 of 10 |
| Pathfield Investments LLC | 10 | 4 of 10 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00223898 | Amarillo District | BRIDGE JOINT CLEANING AND SEALING, IH0040 (Various Locations- See Plan Sheets to Various Locations-See Plan Sheets) | 14 of 14 | $844,844 | +175% |
| 03 NOV 2026 | A00211095 | Odessa District | Bridge Maintenance, US 90 (AT 19.6 MI E OF SH 349 to .) | 1 of 7 | $2,888,888 | Low, 3.0% under the second |
| 03 NOV 2026 | A00219553 | Austin District | BRIDGE PREVENTATIVE MAINTENANCE, RM2222 (VARIOUS LOCATIONS IN to THE AUSTIN DISTRICT) | 3 of 13 | $1,352,352 | +25% |
| 03 NOV 2026 | A00211505 | Amarillo District | Bridge Maintenance, IH 27 (IH 27 NB/WESTERN AVE BRG to .) | 4 of 8 | $6,099,099 | +5.0% |
| 15 OCT 2026 | A00223685 | Paris District | BRIDGE PREVENTATIVE MAINTENANCE, IH0030 (Various locations in to Hopkins County) | 6 of 11 | $292,292 | +16% |
| 07 OCT 2026 | A00211436 | Amarillo District | Bridge Maintenance, IH 27 (IH 27 NB/SH 217 BRG to .) | 2 of 5 | $3,975,975 | +2.0% |
| 07 OCT 2026 | A00222466 | Brownwood District | BRIDGE PREVENTATIVE MAINTENANCE, FM0581 (VARIOUS to VARIOUS) | 2 of 9 | $889,889 | +24% |
| 06 OCT 2026 | A00211479 | Austin District | Bridge Maintenance, US 79 (US 79 at Drain to #14-246-0-0204-01-008.) | 6 of 14 | $535,535 | +56% |
| 06 OCT 2026 | A00220460 | Brownwood District | BRIDGE PREVENTATIVE MAINTENANCE, SH0016 (DISTRICT-WIDE to DISTRICT-WIDE) | 4 of 11 | $1,041,041 | +43% |
| 29 SEP 2026 | A00223850 | San Angelo District | CULVERT REPAIR, FM 2169 (FM 2169 AT SOUTH LLANO RIVER CROSSING to FM 2169 AT SOUTH LLANO RIVER CROSSING) | 3 of 5 | $311,311 | +35% |
| 22 SEP 2026 | A00218207 | Abilene District | BRIDGE PREVENTATIVE MAINTENANCE, BI0020R (VARIOUS LOCATIONS to IN THE ABILENE DISTRICT) | 12 of 12 | $1,394,394 | +103% |
| 16 SEP 2026 | A00222875 | Tyler District | CONCRETE SPALL REPAIR, US0080 (Various Locations in to the Tyler District) | 3 of 8 | $879,879 | +32% |
| 03 SEP 2026 | A00221262 | San Angelo District | BRIDGE PREVENTATIVE MAINTENANCE, SH0208 (VARIOUS LOCATIONS IN SAN ANGELO DISTRICT to VARIOUS LOCATIONS IN SAN ANGELO DISTRICT) | 1 of 11 | $1,383,383 | Low, 0.0% under the second |
| 20 AUG 2026 | A00218396 | Paris District | BRIDGE PREVENTATIVE MAINTENANCE, FM0897 (Various locations to Fannin and Hopkins County) | 2 of 8 | $575,575 | +7.0% |
| 21 JUL 2026 | A00220736 | Tyler District | BRIDGE PREVENTATIVE MAINTENANCE, US0287 (Various Bridges in Anderson and to Henderson Co in the Tyler District) | 3 of 4 | $495,495 | +20% |
| 01 JUL 2026 | A00221442 | Waco District | BRIDGE PREVENTATIVE MAINTENANCE, SH0006 (VARIOUS BRIDGE LOCATIONS to in the Waco District) | 2 of 11 | $929,929 | +1.0% |
| 01 JUL 2026 | A00211476 | Austin District | Bridge Maintenance, SH 71 (At Oatman Creek to #14-150-0-0700-04-016.) | 4 of 11 | $789,789 | +50% |
| 03 JUN 2026 | A00210143 | Amarillo District | BRIDGE PREVENTATIVE MAINTENANCE, US0060 (Various Locations- See Plan Sheets to Various Locations-See Plan Sheets) | 5 of 10 | $1,523,523 | +21% |
| 03 JUN 2026 | A00208955 | Corpus Christi District | Bridge Maintenance, Various (@Various Locations to In Corpus Christi District) | 5 of 9 | $563,563 | +18% |
| 03 JUN 2026 | A00216795 | Waco District | Bridge Maintenance, Various (Various to Various) | 1 of 9 | $3,058,058 | Low, 10% under the second |
| 02 JUN 2026 | A00188372 | El Paso District | Bridge Maintenance, Various (DISTRICTWIDE (BRIDGE MAINTENANCE) to .) | 6 of 6 | $1,268,268 | +56% |
| 02 JUN 2026 | A00211709 | Austin District | Bridge Maintenance, RM 620 (At Colorado River to #14-227-0-0683-02-019.) | 6 of 8 | $4,292,292 | +29% |
| 07 MAY 2026 | A00207724 | Abilene District | Bridge Maintenance, US 83 (US 83 SB to @ BU 84 UPRR) | 1 of 14 | $4,004,004 | Low, 4.0% under the second |
| 06 MAY 2026 | A00211596 | Childress District | Bridge Maintenance, US 83 (US 83 SB @ Salt Fork of Red River to .) | 3 of 13 | $2,867,867 | +20% |
| 21 APR 2026 | A00220409 | Odessa District | BRIDGE PREVENTATIVE MAINTENANCE, SL0338 (VARIOUS to VARIOUS) | 4 of 7 | $751,610 | +44% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.