TxDOT contract A00211436 bid tabulation
Bridge Maintenance, IH 27 (IH 27 NB/SH 217 BRG to .). Let by Texas DOT on October 7, 2026, Randall, Amarillo District. 5 bids received; low bid $3,904,923 by Gibson & Associates, Inc., +2.9% against the engineer's estimate of $3,795,189.
- Owner
- Texas DOT
- Letting
- 07 OCT 2026
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gibson & Associates, Inc. | $3,904,923 | Low | +3.0% |
| 2 | The Truesdell Corporation | $3,975,975 | +2.0% | +5.0% |
| 3 | Ti-Zack Concrete, LLC | $4,113,614 | +5.0% | +8.0% |
| 4 | Ragle Construction, Inc. | $4,465,749 | +14% | +18% |
| 5 | Freyssinet, Inc. | $5,104,969 | +31% | +35% |
Engineer's estimate: $3,795,189.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gibson & Associates, Inc. | 2. The Truesdell Corporation | 3. Ti-Zack Concrete, LLC | 4. Ragle Construction, Inc. | 5. Freyssinet, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (traffic barrier) (104-7035) | LF | 120 | $105.00 | $325.00 | $64.63 | $50.00 | $440.38 | |
| 2 | Embankment (final)(OC)(type B) (132-7003) | CY | 150 | $60.00 | $128.70 | $125.00 | $41.13 | $150.00 | $53.20 |
| 3 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 2,560 | $1.00 | $1.29 | $1.00 | $5.88 | $1.00 | $1.36 |
| 4 | Drill seed (temporary_warm) (164-7013) | SY | 1,280 | $0.50 | $3.47 | $1.00 | $4.70 | $2.00 | $2.71 |
| 5 | Drill seed (temporary_cool) (164-7014) | SY | 1,280 | $0.50 | $3.47 | $1.00 | $7.05 | $2.00 | $2.71 |
| 6 | Soil retention blankets (CL 1) (type B) (169-7043) | SY | 2,560 | $3.00 | $1.10 | $7.00 | $25.85 | $4.50 | $6.10 |
| 7 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 2,112 | $8.00 | $34.10 | $22.00 | $14.10 | $26.00 | $52.21 |
| 8 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 2,838 | $37.40 | $22.00 | $16.45 | $18.00 | $52.21 | |
| 9 | Full - depth repair CRCP (9") (361-7050) | SY | 100 | $350.00 | $750.00 | $1,200.00 | $411.25 | $650.00 | $271.98 |
| 10 | Flowable backfill (401-7001) | CY | 7.60 | $600.00 | $750.00 | $750.00 | $646.25 | $600.00 | $702.02 |
| 11 | Epoxy waterproof finish (type X) (427-7005) | SF | 2,830 | $11.35 | $8.80 | $10.00 | $29.38 | $8.58 | $10.84 |
| 12 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 5 | $200.00 | $500.00 | $250.00 | $2,937.50 | $400.00 | $223.58 |
| 13 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 2,230 | $175.00 | $10.00 | $50.00 | $99.88 | $150.00 | $135.50 |
| 14 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 248 | $200.00 | $240.00 | $160.00 | $135.13 | $150.00 | $257.45 |
| 15 | Pneumatically placed concrete (repair) (431-7002) | CF | 125 | $150.00 | $620.00 | $110.00 | $145.70 | $200.00 | $1,387.60 |
| 16 | Riprap (concrete)(4 in) (432-7001) | CY | 226 | $770.00 | $657.80 | $450.00 | $464.13 | $716.00 | $385.53 |
| 17 | Polyester polymer concrete overlay (2") (439-7017) | SY | 2,112 | $175.00 | $205.00 | $235.00 | $334.88 | $165.00 | $314.36 |
| 18 | Polyester polymer concrete overlay (2-1/2") (439-7018) | SY | 1,160 | $250.00 | $275.00 | $387.75 | $196.00 | $389.20 | |
| 19 | CL CO concrete ovrly(steel fiber rein)(3.5 in) (439-7024) | SY | 1,678 | $160.00 | $125.00 | $169.20 | $125.00 | $165.61 | |
| 20 | Clean and paint existing STR (ref no. 1) (446-7020) | EACH | 1 | $24,620 | $30,000 | $49,350 | $100,000 | $30,328 | |
| 21 | Clean and paint existing STR (ref no. 2) (446-7021) | EACH | 1 | $64,706 | $70,000 | $88,125 | $100,000 | $79,707 | |
| 22 | Pipe (PVC) (schedule 40) (6 in) (481-7013) | LF | 20 | $90.00 | $100.00 | $100.00 | $176.25 | $160.00 | $108.09 |
| 23 | Hydro-demolition (1 in) (483-7008) | SY | 1,678 | $108.00 | $90.00 | $99.88 | $88.00 | $163.43 | |
| 24 | Shot blasting (483-7016) | SY | 3,272 | $10.00 | $9.90 | $8.00 | $12.93 | $2.50 | $4.74 |
| 25 | Mobilization (500-7001) | LS | 1 | $305,000 | $330,000 | $540,004 | $64,625 | $490,000 | $140,823 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $20,000 | $8,700.00 | $5,700.00 | $7,637.50 | $62,000 | $3,627.12 |
| 27 | Portable changeable message sign (503-7002) | EACH | 2 | $18,000 | $7,500.00 | $14,100 | $25,000 | $22,629 | |
| 28 | TMA (stationary) (505-7001) | DAY | 185 | $265.00 | $360.00 | $1.00 | $170.38 | $300.00 | $369.15 |
| 29 | TMA (mobile operation) (505-7002) | HR | 140 | $150.00 | $40.00 | $155.00 | $64.63 | $63.00 | $43.55 |
| 30 | Temporary sediment control fence (install) (506-7039) | LF | 3,271 | $6.90 | $6.05 | $1.00 | $5.88 | $5.00 | $6.78 |
| 31 | Temporary sediment control fence (remove) (506-7041) | LF | 3,271 | $2.00 | $2.20 | $1.00 | $3.53 | $1.50 | $2.03 |
| 32 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 120 | $5.00 | $13.20 | $1.00 | $8.23 | $8.00 | $10.84 |
| 33 | Biodegradable erosion control logs (remove) (506-7046) | LF | 120 | $2.00 | $5.00 | $1.00 | $3.53 | $2.00 | $2.71 |
| 34 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 900 | $53.61 | $27.00 | $76.38 | $60.00 | $33.88 | |
| 35 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 900 | $36.50 | $16.00 | $52.88 | $20.00 | $20.33 | |
| 36 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 900 | $53.61 | $27.00 | $76.38 | $20.00 | $33.88 | |
| 37 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 720 | $110.00 | $161.70 | $175.00 | $217.38 | $110.00 | $121.95 |
| 38 | Permanent CTB (F-shape) (type 1) (514-7013) | LF | 120 | $146.66 | $195.00 | $264.38 | $152.00 | $121.95 | |
| 39 | Remove metal beam guard fence (542-7001) | LF | 450 | $5.00 | $11.00 | $11.00 | $12.93 | $10.00 | $13.55 |
| 40 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $405.00 | $605.00 | $600.00 | $3,818.75 | $400.00 | $745.26 |
| 41 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $495.00 | $605.00 | $600.00 | $587.50 | $400.00 | $745.26 |
| 42 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 3 | $2,750.00 | $2,750.00 | $14,100 | $1,300.00 | $3,387.53 | |
| 43 | Crash cushion attenuator (remove) (545-7004) | EACH | 3 | $2,200.00 | $2,500.00 | $5,287.50 | $1,100.00 | $2,710.03 | |
| 44 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $29,400 | $38,500 | $36,000 | $41,125 | $33,000 | $47,425 |
| 45 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 3 | $11,000 | $11,000 | $12,925 | $15,000 | $9,078.59 | |
| 46 | Remove electrical services (628-7002) | EACH | 1 | $6,250.00 | $3,000.00 | $881.25 | $2,500.00 | $3,387.53 | |
| 47 | Replace existing aluminum signs(type A) (636-7004) | SF | 56 | $40.00 | $75.00 | $125.00 | $135.13 | $60.00 | $27.10 |
| 48 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 17,636 | $1.05 | $1.76 | $1.70 | $1.88 | $1.60 | $8.13 |
| 49 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 19,597 | $1.05 | $1.76 | $1.70 | $1.88 | $1.60 | $8.13 |
| 50 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 5,789 | $1.20 | $3.30 | $3.20 | $3.53 | $3.00 | $4.07 |
| 51 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 96 | $3.30 | $3.20 | $3.53 | $3.00 | $6.78 | |
| 52 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 6,172 | $1.20 | $3.30 | $3.20 | $3.53 | $3.00 | $4.07 |
| 53 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 679 | $2.48 | $2.40 | $2.64 | $2.25 | $6.78 | |
| 54 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 2,715 | $2.48 | $2.40 | $2.64 | $2.25 | $4.07 | |
| 55 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 5,102 | $2.48 | $2.40 | $2.64 | $2.25 | $5.42 | |
| 56 | Pavement sler 6" (666-7347) | LF | 21,904 | $1.00 | $1.38 | $1.40 | $1.47 | $1.25 | $2.71 |
| 57 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 6 | $50.00 | $22.00 | $22.00 | $23.50 | $20.00 | $271.00 |
| 58 | Eliminating existing PM & markers (6") (677-7002) | LF | 24,900 | $0.65 | $1.38 | $1.30 | $1.47 | $1.25 | $2.71 |
| 59 | Pavement surface preparation for marking (6") (678-7002) | LF | 21,904 | $0.80 | $1.38 | $1.30 | $1.47 | $1.25 | $1.36 |
| 60 | Crack cleaning and sealing (JCP) (713-7004) | LF | 3,420 | $25.00 | $27.00 | $28.00 | $16.45 | $42.00 | $3.31 |
| 61 | Drain inlet cleaning (764-7001) | EACH | 8 | $500.00 | $250.00 | $750.00 | $2,937.50 | $1,000.00 | $389.01 |
| 62 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 752 | $31.75 | $22.00 | $32.00 | $17.63 | $60.00 | $151.76 |
| 63 | Rep steel bridge member (diaphragm) (784-7003) | EACH | 1 | $2,500.00 | $11,000 | $16,450 | $12,000 | $23,169 | |
| 64 | Bridge joint replacement (SEJ) (785-7011) | LF | 652 | $475.00 | $755.00 | $825.00 | $299.63 | $467.00 | $1,114.99 |
| 65 | Carbon fiber reinforced polymer protection (786-7001) | SF | 344 | $100.00 | $65.00 | $52.00 | $52.88 | $46.00 | $86.07 |
| 66 | Concrete beam repair (CFRP) (788-7002) | EACH | 8 | $7,000.00 | $4,700.00 | $5,000.00 | $9,400.00 | $6,500.00 | $5,891.99 |
| 67 | Tied-concrete block erosion control mat (2005-7001) | SF | 1,050 | $19.80 | $25.00 | $14.10 | $20.50 | $5.42 | |
| 68 | Steel bridge zone painting (4010-7021) | SF | 2,886 | $20.90 | $21.00 | $29.38 | $17.00 | $25.75 | |
| 69 | Prefb PV MK W/wnty type B (W)(6")(broken) (6064-7001) | LF | 1,352 | $13.50 | $19.25 | $19.00 | $20.56 | $17.50 | $9.49 |
| 70 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 2 | $600.00 | $600.00 | $5,287.50 | $1,500.00 | $677.51 | |
| 71 | Bridge beam end cleaning (7001-7003) | EACH | 5 | $600.00 | $600.00 | $2,937.50 | $1,500.00 | $677.51 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 7, 2026. Compiled by Mirage Metrics.