TxDOT contract A00210143 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, US0060 (Various Locations- See Plan Sheets to Various Locations-See Plan Sheets). Let by Texas DOT on June 3, 2026, Potter, Amarillo District. 10 bids received; low bid $1,256,310 by Gibson & Associates, Inc., -27% against the engineer's estimate of $1,720,012.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 29
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gibson & Associates, Inc. | $1,256,310 | Low | -27% |
| 2 | Ragle Construction, Inc. | $1,384,913 | +10% | -19% |
| 3 | Pathfield Investments LLC | $1,388,818 | +11% | -19% |
| 4 | Built Right Construction of Oklahoma, LLC | $1,475,106 | +17% | -14% |
| 5 | The Truesdell Corporation | $1,523,523 | +21% | -11% |
| 6 | Cross Plus Construction, LLC | $1,630,595 | +30% | -5.0% |
| 7 | Rear Contractors LLC | $1,636,039 | +30% | -5.0% |
| 8 | Blacksmith Ventures LLC | $1,707,132 | +36% | -1.0% |
| 9 | Ti-Zack Concrete, LLC | $1,717,717 | +37% | 0.0% |
| 10 | PBX Bridge Company | $1,746,122 | +39% | +2.0% |
Engineer's estimate: $1,720,012.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gibson & Associates, Inc. | 2. Ragle Construction, Inc. | 3. Pathfield Investments LLC | 4. Built Right Construction of Oklahoma, LLC | 5. The Truesdell Corporation | 6. Cross Plus Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Embankment (final)(OC)(type A) (132-7001) | CY | 46 | $40.00 | $170.00 | $90.00 | $195.00 | $30.00 | $150.00 | $44.00 |
| 2 | Flowable backfill (401-7001) | CY | 5 | $350.00 | $1,200.00 | $650.00 | $1,000.00 | $400.00 | $1,500.00 | $1,100.00 |
| 3 | Epoxy waterproof finish (type X) (427-7005) | SF | 6,454 | $12.00 | $8.80 | $7.40 | $15.00 | $10.00 | $12.00 | $5.50 |
| 4 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 256 | $300.00 | $97.00 | $125.00 | $160.00 | $275.00 | $200.00 | $132.00 |
| 5 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 107 | $150.00 | $102.00 | $75.00 | $220.00 | $275.00 | $165.00 | $220.00 |
| 6 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 662 | $170.00 | $217.00 | $125.00 | $180.00 | $300.00 | $220.00 | $165.00 |
| 7 | Riprap (concrete)(4 in) (432-7001) | CY | 1 | $500.00 | $1,750.00 | $1,150.00 | $2,200.00 | $1,000.00 | $5,000.00 | $5,500.00 |
| 8 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 446 | $75.00 | $67.00 | $30.00 | $80.00 | $75.00 | $65.00 | $55.00 |
| 9 | Cleaning existing joints (438-7008) | LF | 760 | $25.00 | $5.00 | $30.00 | $40.00 | $75.00 | $26.00 | $22.00 |
| 10 | Clean and seal existing JTS (strip seal) (438-7014) | LF | 68 | $100.00 | $100.00 | $75.00 | $80.00 | $100.00 | $150.00 | $165.00 |
| 11 | Multi-layer polymer overlay (439-7014) | SY | 14,605 | $64.00 | $37.00 | $30.00 | $40.00 | $45.00 | $32.00 | $55.00 |
| 12 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 80 | $18.00 | $55.00 | $55.00 | $45.00 | $100.00 | $25.00 | $110.00 |
| 13 | Shot blasting (483-7016) | SY | 14,605 | $11.00 | $6.50 | $2.50 | $10.00 | $5.00 | $5.00 | $5.50 |
| 14 | Mobilization (500-7001) | LS | 1 | $156,365 | $114,500 | $138,000 | $130,000 | $75,000 | $402,298 | $220,000 |
| 15 | Barricades, signs and traffic handling (502-7004) | EACH | 11 | $4,000.00 | $6,700.00 | $35,000 | $1,500.00 | $4,500.00 | $5,500.00 | $13,200 |
| 16 | Downstream anchor terminal section (540-7015) | EACH | 4 | $3,200.00 | $1,650.00 | $2,500.00 | $1,300.00 | $2,000.00 | $3,000.00 | $1,650.00 |
| 17 | Remove terminal anchor section (542-7002) | EACH | 4 | $400.00 | $220.00 | $500.00 | $600.00 | $350.00 | $600.00 | $550.00 |
| 18 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,899 | $2.00 | $2.00 | $1.00 | $2.00 | $1.00 | $1.50 | $1.65 |
| 19 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,201 | $0.50 | $2.00 | $1.00 | $2.00 | $1.00 | $1.50 | $1.65 |
| 20 | Pavement sler 6" (666-7347) | LF | 12,329 | $1.00 | $2.20 | $2.00 | $1.50 | $2.50 | $2.20 | $1.10 |
| 21 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 350 | $1.20 | $3.30 | $3.00 | $1.50 | $3.75 | $3.50 | $3.30 |
| 22 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 6,694 | $1.00 | $3.30 | $3.00 | $1.00 | $3.50 | $3.20 | $2.20 |
| 23 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 270 | $1.20 | $3.30 | $3.00 | $1.60 | $3.50 | $3.20 | $3.30 |
| 24 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 5,016 | $1.00 | $3.30 | $3.00 | $1.20 | $3.50 | $3.20 | $2.20 |
| 25 | Eliminating existing PM & markers (6") (677-7002) | LF | 7,516 | $1.75 | $3.30 | $3.00 | $0.90 | $3.50 | $3.20 | $0.33 |
| 26 | Crack cleaning and sealing (JCP) (713-7004) | LF | 64 | $30.00 | $75.00 | $50.00 | $120.00 | $10.00 | $99.00 | $66.00 |
| 27 | Concrete beam repair (788-7001) | EACH | 5 | $1,500.00 | $1,500.00 | $4,500.00 | $4,500.00 | $3,500.00 | $2,200.00 | $4,400.00 |
| 28 | Concrete beam repair (CFRP) (788-7002) | EACH | 2 | $3,000.00 | $4,275.00 | $7,500.00 | $10,700 | $5,000.00 | $4,500.00 | $8,250.00 |
| 29 | Tied-concrete block erosion control mat (2005-7001) | SF | 225 | $20.00 | $40.00 | $100.00 | $160.00 | $30.00 | $53.00 | $22.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.