Concrete structure repair (epoxy mortar), TxDOT 429-7002
Low bidders on TxDOT contracts carried a median of $175.00 per SF for this item, over the 24 months to 19 NOV 2026, across 37 low bids. Half of all 292 bids fell between $125.00 and $300.00.
- Owner
- Texas DOT
- Item
- 429-7002
- Unit
- SF
- Data through
- 19 NOV 2026
TxDOT prints this item as “CONC STR REPAIR (EPOXY MORTAR)”.
TxDOT has bid this work under more than one code: 4296002 on lettings from 08 APR 2020 to 10 JUL 2024 (156 bids); 429-7002 on lettings from 21 NOV 2024 to 04 NOV 2026 (294 bids); 429-6002 on lettings from 07 JAN 2025 to 07 JAN 2025 (4 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 3 | 3 | $325.00 | 13 | $300.00 |
| 2021 | 8 | 7 | $200.00 | 36 | $299.00 |
| 2022 | 9 | 9 | $215.00 | 44 | $300.00 |
| 2023 | 8 | 8 | $275.00 | 33 | $320.00 |
| 2024 | 7 | 7 | $250.00 | 34 | $412.50 |
| 2025 | 17 | 17 | $200.00 | 101 | $250.00 |
| 2026 | 19 | 19 | $100.00 | 185 | $165.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Childress District | 5 | $95.00 | 62 | $144.95 |
| Austin District | 6 | $205.50 | 54 | $217.50 |
| San Antonio District | 7 | $100.00 | 44 | $200.00 |
| Tyler District | 5 | $200.00 | 37 | $200.00 |
| Paris District | 3 | $175.00 | 16 | $200.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 2 to 14 | 9 | $325.00 |
| 18 to 48 | 9 | $200.00 |
| 50 to 165 | 9 | $95.00 |
| 167 to 550 | 10 | $122.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Built Right Construction of Oklahoma, LLC | 23 | 6 (26%) |
| Structural Integrity Group LLC | 21 | 6 (29%) |
| Ragle Construction, Inc. | 17 | 6 (35%) |
| Gibson & Associates, Inc. | 19 | 4 (21%) |
| Aad Contracting Inc. | 6 | 4 (67%) |
| MPB, Inc. | 6 | 3 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00223826 | Childress District | 85 | $95.00 | $144.90 | $120.00 | 15 | Blacksmith Ventures LLC | TxDOT |
| 03 NOV 2026 | A00211095 | Odessa District | 53 | $180.00 | $236.30 | $324.30 | 7 | The Truesdell Corporation | TxDOT |
| 03 NOV 2026 | A00223831 | Childress District | 165 | $73.50 | $150.00 | $120.00 | 15 | Icos Management, LLC | TxDOT |
| 16 SEP 2026 | A00222875 | Tyler District | 400 | $104.00 | $175.50 | $200.00 | 8 | Red Baron Building Company Municipal Projects Division LLC | TxDOT |
| 10 SEP 2026 | A00221261 | San Angelo District | 245 | $100.00 | $110.00 | $140.00 | 10 | 12Twelve Road and Bridge LLC | TxDOT |
| 03 SEP 2026 | A00221262 | San Angelo District | 40 | $185.00 | $185.00 | $150.00 | 11 | The Truesdell Corporation | TxDOT |
| 11 AUG 2026 | A00221404 | Tyler District | 55 | $50.00 | $189.00 | $200.00 | 12 | 12Twelve Road and Bridge LLC | TxDOT |
| 06 AUG 2026 | A00211130 | Dallas District | 24 | $300.00 | $170.00 | $200.00 | 9 | Rear Contractors LLC | TxDOT |
| 02 JUL 2026 | A00064356 | Lufkin District | 18 | $300.00 | $137.50 | $330.00 | 6 | Posillico Civil, Inc. | TxDOT |
| 02 JUL 2026 | A00186990 | San Antonio District | 100 | $75.00 | $275.00 | n/a | 7 | Taylor Bridge LLC | TxDOT |
| 03 JUN 2026 | A00210143 | Amarillo District | 256 | $97.00 | $147.68 | $300.00 | 10 | Gibson & Associates, Inc. | TxDOT |
| 02 JUN 2026 | A00206681 | Paris District | 20 | $140.00 | $250.00 | $75.00 | 5 | THK Construction LLC | TxDOT |
| 06 MAY 2026 | A00211596 | Childress District | 250 | $100.00 | $128.00 | $200.00 | 13 | Built Right Construction of Oklahoma, LLC | TxDOT |
| 18 MAR 2026 | A00214342 | San Antonio District | 2 | $500.00 | $329.40 | $69.32 | 6 | Diamond R Contracting, LLC | TxDOT |
| 18 MAR 2026 | A00218464 | San Antonio District | 14 | $100.00 | $125.00 | $69.32 | 6 | BK Field Operations LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way