TxDOT contract A00223826 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, US0287 (Various Locations ~ See Plans to Various Locations ~ See Plans). Let by Texas DOT on November 4, 2026, Donley, Childress District. 16 bids received; low bid $701,941 by Blacksmith Ventures LLC, -38% against the engineer's estimate of $1,130,180.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 15
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Blacksmith Ventures LLC | $701,941 | Low | -38% |
| 2 | Icos Management, LLC | $745,061 | +6.0% | -34% |
| 3 | Rear Contractors LLC | $819,576 | +17% | -27% |
| 4 | Coppell Construction Co., Inc. | $832,395 | +19% | -26% |
| 5 | Structural Integrity Group LLC | $896,400 | +28% | -21% |
| 6 | Ti-Zack Concrete, LLC | $912,899 | +30% | -19% |
| 7 | Ragle Construction, Inc. | $974,424 | +39% | -14% |
| 8 | Scott Tucker Construction Company, LLC | $992,803 | +41% | -12% |
| 9 | O. Trevino Construction, LLC | $994,725 | +42% | -12% |
| 10 | Cross Plus Construction, LLC | $1,006,039 | +43% | -11% |
| 11 | Pathfield Investments LLC | $1,008,340 | +44% | -11% |
| 12 | THK Construction LLC | $1,159,846 | +65% | +3.0% |
| 13 | Premier Contractors LLC | $1,198,771 | +71% | +6.0% |
| 14 | SCR Civil Construction, LLC | $1,240,152 | +77% | +10% |
| 15 | Southern Road & Bridge, LLC | $1,958,205 | +179% | +73% |
| 16 | Built Right Construction of Oklahoma, LLC | $2,160,400 | +208% | +91% |
Engineer's estimate: $1,130,180.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Blacksmith Ventures LLC | 2. Icos Management, LLC | 3. Rear Contractors LLC | 4. Coppell Construction Co., Inc. | 5. Structural Integrity Group LLC | 6. Ti-Zack Concrete, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Class C concrete (pile encasement) (420-7060) | CY | 3.50 | $1,900.00 | $2,000.00 | $2,100.00 | $2,000.00 | $8,500.00 | $1,933.00 | $1,380.00 |
| 2 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 85 | $120.00 | $95.00 | $84.00 | $110.00 | $172.00 | $95.00 | $144.90 |
| 3 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 75 | $120.00 | $95.00 | $136.50 | $150.00 | $200.00 | $89.00 | $287.50 |
| 4 | Concrete structure repair(rapid deck rep(full DPT)) (429-7006) | SF | 430 | $175.00 | $125.00 | $147.00 | $150.00 | $110.00 | $124.00 | $253.00 |
| 5 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 5,431 | $140.00 | $99.00 | $94.50 | $120.00 | $65.00 | $119.00 | $74.75 |
| 6 | Joint sealant (454-7010) | LF | 140 | $20.00 | $25.00 | $52.50 | $50.00 | $114.00 | $60.00 | $51.75 |
| 7 | Mobilization (500-7001) | LS | 1 | $100,000 | $1.00 | $42,500 | $30,000 | $70,000 | $1.00 | $39,100 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $2,500.00 | $1.00 | $1.10 | $1.00 | $16,500 | $1.00 | $6,325.00 |
| 9 | TMA (stationary) (505-7001) | DAY | 15 | $200.00 | $321.00 | $262.50 | $250.00 | $250.00 | $1.00 | $402.50 |
| 10 | Steel bridge zone painting ref STR #4 (4010-7005) | EACH | 1 | $87,960 | $30,000 | $60,900 | $10,000 | $84,000 | $83,353 | $136,850 |
| 11 | Steel bridge zone painting ref STR #11 (4010-7012) | EACH | 1 | $4,480.00 | $10,000 | $4,000.00 | $5,000.00 | $20,000 | $16,700 | $13,800 |
| 12 | Steel bridge zone painting ref STR #14 (4010-7016) | EACH | 1 | $24,380 | $10,000 | $4,200.00 | $5,000.00 | $20,000 | $16,700 | $43,700 |
| 13 | Steel bridge zone painting ref STR #15 (4010-7017) | EACH | 1 | $13,200 | $10,000 | $6,300.00 | $5,000.00 | $20,000 | $16,700 | $28,750 |
| 14 | Steel bridge zone painting ref STR #21 (4010-7024) | EACH | 1 | $5,920.00 | $10,000 | $5,250.00 | $5,000.00 | $20,000 | $16,700 | $17,250 |
| 15 | Steel bridge zone painting ref STR #22 (4010-7025) | EACH | 1 | $12,000 | $10,000 | $9,450.00 | $5,000.00 | $20,000 | $16,700 | $28,750 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way