TxDOT contract A00211596 bid tabulation
Bridge Maintenance, US 83 (US 83 SB @ Salt Fork of Red River to .). Let by Texas DOT on May 6, 2026, Collingsworth, Childress District. 13 bids received; low bid $2,396,526 by Built Right Construction of Oklahoma, LLC, -4.4% against the engineer's estimate of $2,507,552.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Built Right Construction of Oklahoma, LLC | $2,396,526 | Low | -4.0% |
| 2 | Gibson & Associates, Inc. | $2,847,174 | +19% | +14% |
| 3 | The Truesdell Corporation | $2,867,867 | +20% | +14% |
| 4 | Icos Management, LLC | $2,888,242 | +21% | +15% |
| 5 | Blacksmith Ventures LLC | $2,894,745 | +21% | +15% |
| 6 | Myers & Sons Construction LLC | $2,896,691 | +21% | +16% |
| 7 | Ti-Zack Concrete, LLC | $2,994,452 | +25% | +19% |
| 8 | MPB, Inc. | $2,999,453 | +25% | +20% |
| 9 | Gilvin-Terrill, LTD. | $3,165,947 | +32% | +26% |
| 10 | Ragle Construction, Inc. | $3,243,483 | +35% | +29% |
| 11 | Pathfield Investments LLC | $3,394,506 | +42% | +35% |
| 12 | Scott Tucker Construction Company, LLC | $3,403,402 | +42% | +36% |
| 13 | Earth Builders, L.P. | $4,486,086 | +87% | +79% |
Engineer's estimate: $2,507,552.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Built Right Construction of Oklahoma, LLC | 2. Gibson & Associates, Inc. | 3. The Truesdell Corporation | 4. Icos Management, LLC | 5. Blacksmith Ventures LLC | 6. Myers & Sons Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 2,067 | $13.79 | $5.00 | $24.20 | $25.00 | $11.00 | $2.00 | $15.00 |
| 2 | Embankment (final)(OC)(type B) (132-7003) | CY | 522 | $34.42 | $40.00 | $85.80 | $35.00 | $43.00 | $28.00 | $130.00 |
| 3 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 3,920 | $2.03 | $18.00 | $9.78 | $7.00 | $9.00 | $10.00 | $6.49 |
| 4 | Flowable backfill (401-7001) | CY | 160 | $300.00 | $324.50 | $437.00 | $294.00 | $375.00 | $400.00 | |
| 5 | Penetrating concrete surface treatment (428-7001) | SY | 767 | $18.25 | $10.00 | $22.77 | $29.00 | $27.00 | $8.00 | $23.00 |
| 6 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 250 | $200.00 | $100.00 | $150.00 | $155.00 | $128.00 | $75.00 | $70.00 |
| 7 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 425 | $150.00 | $325.00 | $75.00 | $220.00 | $190.00 | $225.00 | $111.13 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 680 | $138.00 | $225.00 | $255.00 | $155.00 | $107.00 | $109.00 | $102.46 |
| 9 | Riprap (mow strip)(4 in) (432-7013) | CY | 92 | $870.00 | $400.00 | $770.00 | $750.00 | $642.00 | $429.00 | $805.00 |
| 10 | Riprap (stone protection)(24 in) (432-7045) | CY | 204 | $200.00 | $330.00 | $210.00 | $204.00 | $258.00 | $649.00 | |
| 11 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 1,177 | $58.00 | $30.00 | $50.00 | $65.00 | $54.00 | $42.00 | $80.00 |
| 12 | Multi-layer polymer overlay (439-7014) | SY | 4,620 | $37.00 | $33.00 | $28.50 | $54.00 | $60.00 | $60.00 | |
| 13 | Polyester polymer concrete overlay (2") (439-7017) | SY | 3,920 | $140.00 | $160.00 | $204.00 | $225.00 | $224.00 | $237.75 | $270.00 |
| 14 | Retrofit rail (type SSTR) (451-7024) | LF | 1,906 | $190.00 | $115.00 | $174.90 | $150.00 | $235.00 | $226.00 | $180.50 |
| 15 | Shot blasting (483-7016) | SY | 4,620 | $2.00 | $3.00 | $4.00 | $16.00 | $15.85 | $9.00 | |
| 16 | Mobilization (500-7001) | LS | 1 | $200,000 | $75,000 | $310,000 | $355,272 | $94,000 | $250,000 | $200,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $2,200.00 | $15,500 | $2,000.00 | $1.00 | $3,000.00 | $7,625.00 | |
| 18 | TMA (stationary) (505-7001) | DAY | 4 | $300.00 | $900.00 | $750.00 | $535.00 | $5,000.00 | $216.15 | |
| 19 | TMA (mobile operation) (505-7003) | DAY | 1 | $300.00 | $900.00 | $550.00 | $856.00 | $10,000 | $6,495.00 | |
| 20 | One-way traffic control (port traffic signal) (510-7003) | MO | 1 | $8,500.00 | $8,900.00 | $7,500.00 | $16,050 | $8,500.00 | $7,780.47 | |
| 21 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 2,970 | $63.00 | $100.00 | $50.00 | $63.00 | $86.00 | $51.00 | $25.00 |
| 22 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 2,970 | $9.00 | $15.00 | $5.00 | $10.50 | $16.00 | $5.00 | $5.00 |
| 23 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 2,970 | $14.00 | $30.00 | $15.00 | $26.00 | $16.00 | $8.40 | $2.80 |
| 24 | Metal W-beam guard fence (steel post) (540-7002) | LF | 650 | $37.00 | $35.00 | $49.50 | $38.00 | $35.00 | $35.00 | $36.50 |
| 25 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,500.00 | $2,500.00 | $3,300.00 | $2,800.00 | $2,675.00 | $2,100.00 | $2,705.00 |
| 26 | Remove metal beam guard fence (542-7001) | LF | 670 | $3.00 | $3.00 | $5.50 | $3.20 | $4.00 | $0.25 | $3.00 |
| 27 | Remove terminal anchor section (542-7002) | EACH | 2 | $290.00 | $300.00 | $550.00 | $500.00 | $428.00 | $0.25 | $220.00 |
| 28 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,480.00 | $3,500.00 | $4,070.00 | $3,800.00 | $3,500.00 | $3,250.00 | $3,550.00 |
| 29 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $330.00 | $300.00 | $550.00 | $400.00 | $428.00 | $0.25 | $330.00 |
| 30 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 3 | $2,200.00 | $3,000.00 | $2,200.00 | $1,800.00 | $4,280.00 | $3,000.00 | $1,665.00 |
| 31 | Crash cushion attenuator (remove) (545-7004) | EACH | 3 | $2,200.00 | $1,300.00 | $1,650.00 | $900.00 | $2,140.00 | $1,000.00 | $810.00 |
| 32 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 3 | $11,000 | $11,000 | $10,450 | $9,800.00 | $8,560.00 | $9,000.00 | $9,200.00 |
| 33 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 29 | $36.00 | $25.00 | $33.00 | $25.00 | $32.00 | $7.00 | $24.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 14 | $40.00 | $35.00 | $38.50 | $32.00 | $32.00 | $7.00 | $30.00 |
| 35 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 24 | $25.00 | $35.00 | $33.00 | $26.00 | $32.00 | $7.00 | $24.00 |
| 36 | Install delineator assembly (D-SY)SZ 1(BRF)GF2(BI) (658-7037) | EACH | 3 | $30.80 | $35.00 | $38.50 | $32.00 | $32.00 | $100.00 | $30.00 |
| 37 | Remove delin & object marker assms (658-7078) | EACH | 70 | $56.00 | $25.00 | $5.50 | $20.00 | $22.00 | $0.25 | $18.50 |
| 38 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 6,798 | $1.20 | $2.25 | $1.93 | $2.35 | $2.00 | $1.75 | $0.39 |
| 39 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 84 | $17.00 | $16.50 | $16.00 | $16.00 | $15.00 | $5.50 | |
| 40 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 7,517 | $1.20 | $2.00 | $1.93 | $2.30 | $2.00 | $1.75 | $0.39 |
| 41 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 1,374 | $0.60 | $2.25 | $2.31 | $2.30 | $2.50 | $2.10 | $0.75 |
| 42 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 5,073 | $0.54 | $2.25 | $2.31 | $2.30 | $2.50 | $2.10 | $0.75 |
| 43 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 240 | $2.25 | $2.31 | $2.30 | $2.50 | $2.10 | $0.75 | |
| 44 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 10,729 | $4.08 | $2.25 | $2.31 | $2.30 | $2.50 | $2.10 | $0.75 |
| 45 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 14 | $12.00 | $11.00 | $11.00 | $12.00 | $10.00 | $3.95 | |
| 46 | Eliminating existing PM & markers (4") (677-7001) | LF | 14,315 | $1.00 | $1.15 | $1.10 | $1.05 | $1.20 | $1.00 | $0.55 |
| 47 | Eliminating existing PM & markers (6") (677-7002) | LF | 13,396 | $0.41 | $1.25 | $1.21 | $1.20 | $1.20 | $1.10 | $0.55 |
| 48 | Eliminating existing PM & markers (24") (677-7008) | LF | 84 | $3.25 | $2.75 | $1.20 | $3.00 | $2.50 | $0.55 | |
| 49 | Pavement surface preparation for marking (6") (678-7002) | LF | 8,126 | $3.60 | $1.30 | $1.38 | $1.30 | $1.50 | $1.25 | $0.07 |
| 50 | CNC crack repair (discrete)(inject) (780-7002) | LF | 290 | $50.00 | $81.00 | $69.00 | $107.00 | $75.00 | $85.83 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.