TxDOT contract A00211479 bid tabulation
Bridge Maintenance, US 79 (US 79 at Drain to #14-246-0-0204-01-008.). Let by Texas DOT on October 6, 2026, Williamson, Austin District. 14 bids received; low bid $344,329 by Taylor Bridge LLC, -43% against the engineer's estimate of $607,197.
- Owner
- Texas DOT
- Letting
- 06 OCT 2026
- Pay items
- 24
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Taylor Bridge LLC | $344,329 | Low | -43% |
| 2 | Garret Shields Infrastructure | $487,798 | +42% | -20% |
| 3 | Premier Contractors LLC | $498,376 | +45% | -18% |
| 4 | Structural Integrity Group LLC | $510,474 | +48% | -16% |
| 5 | SCR Civil Construction, LLC | $517,906 | +50% | -15% |
| 6 | The Truesdell Corporation | $535,535 | +56% | -12% |
| 7 | Restek, Inc. | $563,640 | +64% | -7.0% |
| 8 | Pathfield Investments LLC | $577,405 | +68% | -5.0% |
| 9 | MPB, Inc. | $577,661 | +68% | -5.0% |
| 10 | Roy Jorgensen Associates, Inc. | $598,765 | +74% | -1.0% |
| 11 | Blacksmith Ventures LLC | $787,525 | +129% | +30% |
| 12 | Rear Contractors LLC | $989,002 | +187% | +63% |
| 13 | Built Right Construction of Oklahoma, LLC | $1,246,263 | +262% | +105% |
| 14 | Southern Road & Bridge, LLC | $1,501,594 | +336% | +147% |
Engineer's estimate: $607,197.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Taylor Bridge LLC | 2. Garret Shields Infrastructure | 3. Premier Contractors LLC | 4. Structural Integrity Group LLC | 5. SCR Civil Construction, LLC | 6. The Truesdell Corporation |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Flowable backfill (401-7001) | CY | 4 | $500.00 | $300.00 | $500.00 | $520.00 | $2,000.00 | $1,300.00 | |
| 2 | Penetrating concrete surface treatment (428-7001) | SY | 770 | $15.00 | $20.00 | $10.00 | $15.00 | $25.00 | $61.00 | $25.00 |
| 3 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 2,346 | $85.00 | $30.00 | $70.00 | $30.00 | $43.00 | $32.70 | $36.00 |
| 4 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 138 | $750.00 | $175.00 | $450.00 | $467.00 | $200.00 | $175.00 | |
| 5 | Riprap (stone common)(grout)(12 in) (432-7038) | CY | 36 | $350.00 | $200.00 | $400.00 | $335.00 | $605.00 | $550.00 | |
| 6 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 1,596 | $25.00 | $30.00 | $50.00 | $40.00 | $29.00 | $45.00 | |
| 7 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 20 | $50.00 | $50.00 | $100.00 | $45.00 | $50.00 | $200.00 | |
| 8 | Clean & paint existing piling (system I) (446-7007) | LS | 1 | $60,000 | $50,000 | $110,000 | $60,850 | $79,800 | $80,000 | |
| 9 | Mobilization (500-7001) | LS | 1 | $60,175 | $7,000.00 | $50,000 | $40,000 | $50,000 | $51,700 | $120,155 |
| 10 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $2,500.00 | $1.00 | $5,000.00 | $1.00 | $5,000.00 | $4,700.00 | $750.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 87 | $165.00 | $1.00 | $300.00 | $1.00 | $1.00 | $200.00 | $1.00 |
| 12 | TMA (mobile operation) (505-7003) | DAY | 6 | $282.00 | $1.00 | $300.00 | $1,000.00 | $1.00 | $800.00 | $1.00 |
| 13 | Rock filter dams (install) (type 2) (506-7002) | LF | 431 | $50.00 | $5.00 | $20.00 | $50.00 | $70.65 | $40.80 | $45.00 |
| 14 | Rock filter dams (remove) (506-7011) | LF | 431 | $16.50 | $0.50 | $10.00 | $20.00 | $34.00 | $27.30 | $10.00 |
| 15 | Temporary sediment control fence (install) (506-7039) | LF | 300 | $4.25 | $1.00 | $5.00 | $10.00 | $3.05 | $3.10 | $1.00 |
| 16 | Temporary sediment control fence (remove) (506-7041) | LF | 300 | $0.95 | $0.50 | $1.00 | $1.00 | $0.72 | $1.10 | $1.00 |
| 17 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,953 | $5.60 | $1.00 | $5.00 | $10.00 | $4.15 | $4.35 | $1.00 |
| 18 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,953 | $1.30 | $0.50 | $1.00 | $1.00 | $0.50 | $1.05 | $1.00 |
| 19 | PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089) | LF | 90 | $20.00 | $150.00 | $80.00 | $50.00 | $125.00 | $115.00 | |
| 20 | PCTB (remove)(F-shape or SNGL SLP)type 1 (512-7092) | LF | 90 | $10.00 | $40.00 | $30.00 | $50.00 | $125.00 | $55.00 | |
| 21 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $500.00 | $500.00 | $2,000.00 | $6,000.00 | $1,500.00 | $1,500.00 | |
| 22 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 2 | $6,500.00 | $10,000 | $8,000.00 | $5,000.00 | $6,500.00 | $12,000 | |
| 23 | Crack cleaning and sealing (JCP) (713-7004) | LF | 80 | $25.00 | $50.00 | $50.00 | $60.00 | $50.00 | $75.00 | |
| 24 | Concrete rail replacement (in-kind) (778-7004) | LF | 16 | $500.00 | $500.00 | $700.00 | $935.00 | $1,500.00 | $1,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.