TxDOT contract A00198028 bid tabulation
Construct Pedestrian Infrastructure, BU 271B (E Price St to MLK Dr). Let by Texas DOT on February 4, 2026, Lamar, Paris District. 13 bids received; low bid $727,153 by Highway 19 Construction LLC, -19% against the engineer's estimate of $898,065.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 19
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway 19 Construction LLC | $727,153 | Low | -19% |
| 2 | C & W Southern LLC | $753,594 | +4.0% | -16% |
| 3 | Garret Shields Infrastructure | $772,855 | +6.0% | -14% |
| 4 | Ti-Zack Concrete, LLC | $792,261 | +9.0% | -12% |
| 5 | Aad Contracting Inc. | $818,260 | +13% | -9.0% |
| 6 | STX Civil | $829,319 | +14% | -8.0% |
| 7 | Tucan Contracting, LLC | $835,785 | +15% | -7.0% |
| 8 | THK Construction LLC | $836,618 | +15% | -7.0% |
| 9 | Talbert Companies LLC | $864,900 | +19% | -4.0% |
| 10 | Grey Sky Construction LLC | $902,619 | +24% | +1.0% |
| 11 | RB Contracting, LLC | $1,031,405 | +42% | +15% |
| 12 | Built Right Construction of Oklahoma, LLC | $1,074,530 | +48% | +20% |
| 13 | CDM Holdings | $1,113,655 | +53% | +24% |
Engineer's estimate: $898,065.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway 19 Construction LLC | 2. C & W Southern LLC | 3. Garret Shields Infrastructure | 4. Ti-Zack Concrete, LLC | 5. Aad Contracting Inc. | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 32 | $1,500.00 | $312.00 | $200.00 | $1,000.00 | $110.00 | $1,000.00 | $405.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 2,108 | $35.00 | $25.00 | $25.00 | $20.00 | $22.71 | $25.00 | $12.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 2,394 | $32.00 | $5.00 | $20.00 | $20.00 | $10.00 | $20.00 | $7.00 |
| 4 | Excavation (special) (110-7003) | CY | 30 | $25.00 | $10.00 | $150.00 | $50.00 | $26.60 | $100.00 | $340.00 |
| 5 | Embankment (final)(OC)(type B) (132-7003) | CY | 35 | $25.00 | $50.00 | $20.00 | $50.00 | $22.80 | $55.00 | $15.00 |
| 6 | Block sodding (162-7002) | SY | 50 | $6.50 | $20.00 | $50.00 | $10.00 | $16.50 | $8.00 | $34.00 |
| 7 | Vegetative watering (OPT1) (168-7002) | TGL | 1 | $150.00 | $1,000.00 | $100.00 | $1,000.00 | $137.50 | $20.00 | $1,350.00 |
| 8 | Mobilization (500-7001) | LS | 1 | $81,642 | $90,000 | $70,000 | $80,000 | $44,258 | $100,000 | $80,000 |
| 9 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $3,500.00 | $1,700.00 | $1,500.00 | $5,000.00 | $1,650.00 | $10,000 | $1,350.00 |
| 10 | TMA (stationary) (505-7001) | DAY | 45 | $300.00 | $200.00 | $300.00 | $300.00 | $0.11 | $350.00 | $475.00 |
| 11 | TMA (mobile operation) (505-7002) | HR | 10 | $105.00 | $100.00 | $350.00 | $30.00 | $0.11 | $100.00 | $270.00 |
| 12 | Concrete curb & gutter (type II) (529-7009) | LF | 2,414 | $45.00 | $42.00 | $45.00 | $30.00 | $56.34 | $65.00 | $53.00 |
| 13 | Driveways (concrete) (530-7006) | SY | 2,071 | $105.00 | $109.00 | $100.00 | $110.00 | $115.79 | $85.00 | $115.00 |
| 14 | Concrete sidewalks (6") (531-7003) | SY | 2,366 | $100.00 | $83.00 | $90.00 | $85.00 | $111.84 | $65.00 | $110.00 |
| 15 | Curb ramps (type 1) (531-7005) | EACH | 1 | $1,500.00 | $1,100.00 | $2,500.00 | $3,000.00 | $3,893.04 | $2,100.00 | $3,350.00 |
| 16 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $350.00 | $1,000.00 | $1,000.00 | $800.00 | $1,100.00 | $2,000.00 | $1,150.00 |
| 17 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 8 | $450.00 | $350.00 | $100.00 | $500.00 | $495.00 | $500.00 | $600.00 |
| 18 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 875 | $9.50 | $9.25 | $9.25 | $12.00 | $10.18 | $5.00 | $12.00 |
| 19 | Eliminating existing PM & markers (24") (677-7008) | LF | 875 | $4.50 | $2.00 | $2.00 | $3.00 | $2.20 | $5.00 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.