TxDOT contract A00216530 bid tabulation
BRIDGE RAIL REPAIR, US0080 (VARIOUS BRIDGES to IN THE TYLER DISTRICT). Let by Texas DOT on November 12, 2025, Wood, Tyler District. 7 bids received; low bid $143,287 by Red Baron Building Company, LLC, -6.2% against the engineer's estimate of $152,821.
- Owner
- Texas DOT
- Letting
- 12 NOV 2025
- Pay items
- 25
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Red Baron Building Company, LLC | $143,287 | Low | -6.0% |
| 2 | GHB Equipment Company, L.L.C. | $159,836 | +12% | +5.0% |
| 3 | Structural Integrity Group LLC | $168,812 | +18% | +10% |
| 4 | Aad Contracting Inc. | $180,827 | +26% | +18% |
| 5 | BK Field Operations LLC | $197,574 | +38% | +29% |
| 6 | Scout 5 Construction LLC | $206,650 | +44% | +35% |
| 7 | Cross Plus Construction, LLC | $215,137 | +50% | +41% |
Engineer's estimate: $152,821.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Red Baron Building Company, LLC | 2. GHB Equipment Company, L.L.C. | 3. Structural Integrity Group LLC | 4. Aad Contracting Inc. | 5. BK Field Operations LLC | 6. Scout 5 Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 5 | $50.00 | $50.00 | $100.00 | $150.00 | $25.00 | $500.00 | $225.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 3 | $16.00 | $100.00 | $250.00 | $75.00 | $25.00 | $2,000.00 | $250.00 |
| 3 | Class C concrete (rac-R) (420-7055) | CY | 3 | $1,940.00 | $650.00 | $1,000.00 | $6,135.00 | $3,000.00 | $3,000.00 | $1,000.00 |
| 4 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 2 | $200.00 | $165.00 | $150.00 | $1,700.00 | $200.00 | $800.00 | $125.00 |
| 5 | Riprap (mow strip)(4 in) (432-7013) | CY | 15 | $750.00 | $650.00 | $600.00 | $875.00 | $600.00 | $1,000.00 | $500.00 |
| 6 | Retrofit rail (type T223) (451-7008) | LF | 55 | $155.00 | $400.00 | $650.00 | $349.00 | $220.00 | $1,100.00 | $125.00 |
| 7 | Mobilization (500-7001) | LS | 1 | $14,000 | $20,000 | $15,000 | $16,000 | $35,000 | $15,000 | $55,174 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $3,000.00 | $1,500.00 | $1,200.00 | $8,500.00 | $7,000.00 | $1.00 | $0.01 |
| 9 | Portable changeable message sign (503-7001) | DAY | 42 | $200.00 | $125.00 | $200.00 | $50.00 | $350.00 | $1.00 | $0.01 |
| 10 | TMA (stationary) (505-7001) | DAY | 42 | $300.00 | $250.00 | $450.00 | $1.00 | $350.00 | $1.00 | $0.01 |
| 11 | Temporary sediment control fence (install) (506-7039) | LF | 450 | $5.00 | $2.00 | $20.00 | $2.00 | $4.00 | $1.00 | $20.00 |
| 12 | Temporary sediment control fence (remove) (506-7041) | LF | 450 | $2.00 | $1.50 | $7.00 | $1.00 | $1.00 | $1.00 | $10.00 |
| 13 | Metal W-beam guard fence (timber post) (540-7001) | LF | 132 | $25.00 | $30.00 | $40.00 | $30.00 | $36.00 | $40.00 | $200.00 |
| 14 | Metal thrie-beam guard fence (timber post) (540-7019) | EACH | 2 | $2,220.00 | $2,500.00 | $2,500.00 | $2,500.00 | $1,900.00 | $2,500.00 | $1,500.00 |
| 15 | Remove metal beam guard fence (542-7001) | LF | 180 | $16.00 | $7.00 | $13.00 | $8.00 | $4.00 | $10.00 | $130.00 |
| 16 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,200.00 | $4,000.00 | $2,500.00 | $3,300.00 | $4,000.00 | $4,500.00 | $2,500.00 |
| 17 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $360.00 | $400.00 | $600.00 | $400.00 | $1,100.00 | $1,000.00 | $1,250.00 |
| 18 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 6 | $30.00 | $12.00 | $13.00 | $25.00 | $90.00 | $200.00 | $125.00 |
| 19 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 1 | $35.00 | $15.00 | $13.00 | $100.00 | $90.00 | $100.00 | $125.00 |
| 20 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 1 | $70.00 | $200.00 | $1,500.00 | $300.00 | $1,200.00 | $1,200.00 | $225.00 |
| 21 | Repair (steel rail) (776-7001) | LF | 125 | $34.50 | $75.00 | $75.00 | $30.00 | $55.00 | $180.00 | $150.00 |
| 22 | Concrete rail repair (in-kind) (778-7001) | LF | 18 | $1,000.00 | $1,000.00 | $400.00 | $1,150.00 | $600.00 | $800.00 | $250.00 |
| 23 | Concrete rail repair (miscellaneous) (778-7002) | LF | 33 | $1,000.00 | $500.00 | $400.00 | $390.00 | $500.00 | $800.00 | $1,000.00 |
| 24 | Concrete post repair (778-7003) | EACH | 3 | $1,000.00 | $1,200.00 | $400.00 | $2,550.00 | $100.00 | $1,200.00 | $125.00 |
| 25 | Maintenance speed limit signing (7010-7001) | EACH | 6 | $600.00 | $500.00 | $500.00 | $100.00 | $800.00 | $1.00 | $700.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 12, 2025. Compiled by Mirage Metrics.