TxDOT letting results, December 10, 2025
24 contracts let by Texas DOT on December 10, 2025, $8,217,528 in low bids, a median of 4 bidders per contract. On the 24 with an engineer's estimate, the low bid came in under it 19 times; median low bid -21% against the estimate.
- Owner
- Texas DOT
- Contracts
- 24
- Low bids, total
- $8,217,528
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| A00218379 | SWEEPING AND DEBRIS REMOVAL, IH0030 (VARIOUS LOCATIONS WITHIN to WEST DALLAS COUNTY MAINTENANCE SECTION) | Dallas District | 4 | Professional Traffic Control LLC | $858,725 | $950,820 | +11% | -13% | TxDOT |
| A00218213 | CRACK SEAL, US0287 (Districtwide Locations to in WFS District) | Wichita Falls District | 3 | Hazmat International, Inc. | $816,731 | $885,989 | +8.0% | +28% | TxDOT |
| A00215939 | HERBICIDE/INSECTICIDE, IH0035 (VARIOUS ROADWAYS to DENTON COUNTY MAINTENANCE SECTION) | Dallas District | 3 | Opterra Solutions, Inc. | $766,890 | $847,300 | +10% | +10% | TxDOT |
| A00218244 | MILL AND INLAY, BS0035L (FM 1069 to SL 70) | Corpus Christi District | 4 | CK Newberry, LLC | $698,456 | $743,974 | +7.0% | -19% | TxDOT |
| A00218387 | HOT MIX, SH0036 (Various to Various) | Bryan District | 2 | Big Creek Construction, LTD. | $581,200 | $627,800 | +8.0% | -11% | TxDOT |
| A00218378 | SWEEPING AND DEBRIS REMOVAL, IH0030 (VARIOUS LOCATIONS WITHIN to EAST DALLAS COUNTY MAINTENANCE SECTION) | Dallas District | 4 | Fireman Excavating, Inc. | $561,164 | $648,940 | +16% | -15% | TxDOT |
| A00215429 | ILLUMINATION MAINTENANCE, IH0035 (VARIOUS LOCATIONS IN to THE AUSTIN DISTRICT) | Austin District | 3 | Austin Traffic Signal Construction Co., Inc. | $455,590 | $751,627 | +65% | -24% | TxDOT |
| A00217794 | ROW Traffic Materials, IH0035E (Dallas to DIstrict) | Dallas District | 2 | Consolidated Traffic Controls, Inc. | $450,645 | $499,998 | +11% | +4.0% | TxDOT |
| A00218012 | DEBRIS REMOVAL, IH0040 (Various Locations- See Plan Sheets to Various Locations-See Plan Sheets) | Amarillo District | 1 | Panhandle Sweeping & Maintenance, LLC | $387,018 | -17% | TxDOT | ||
| A00217116 | MOWING HIGHWAY RIGHT OF WAY, SH0031 (Various Roadways in to Navarro County Maintenance Section) | Dallas District | 10 | Cross Plus Construction, LLC | $379,653 | $430,501 | +13% | -34% | TxDOT |
| A00218326 | HOT MIX, SH0006 (Various to Various) | Bryan District | 2 | Big Creek Construction, LTD. | $297,600 | $321,600 | +8.0% | -15% | TxDOT |
| A00218315 | METAL BEAM GUARD FENCE REPAIR, IH0045 (Various to Various) | Bryan District | 5 | Rhino Equity, LLC | $268,385 | $324,000 | +21% | -31% | TxDOT |
| A00217333 | HERBICIDE/INSECTICIDE, IH0035E (Various Roadways in the to Ellis County Maintenance Section) | Dallas District | 3 | Jasco | $241,101 | $571,550 | +137% | -34% | TxDOT |
| A00217226 | MOWING HIGHWAY RIGHT OF WAY, SH0031 (Various Roadways to Navarro County Maintenance Section) | Dallas District | 11 | Cross Plus Construction, LLC | $229,215 | $261,863 | +14% | -37% | TxDOT |
| A00217341 | PAVEMENT MARKINGS, IH0020 (Various Roadways in the Kaufman - to Rockwall Maintenance Section) | Dallas District | 5 | Stripe-A-Zone, LLC | $170,770 | $218,956 | +28% | -47% | TxDOT |
| A00218010 | DEBRIS REMOVAL, IH0040 (Various Locations- See Plan Sheets to Various Locations-See Plan Sheets) | Amarillo District | 3 | Panhandle Sweeping & Maintenance, LLC | $156,618 | $198,000 | +26% | -27% | TxDOT |
| A00218332 | MOWING HIGHWAY RIGHT OF WAY, US0183 (VARIOUS LOCATIONS IN TRAVIS AND to WILLIAMSON COUNTIES) | Austin District | 4 | T&L Cleaning Services LLC | $147,484 | $171,506 | +16% | +8.0% | TxDOT |
| A00217117 | BRIDGE PREVENTATIVE MAINTENANCE, FM0709 (Navarro to Navarro County Maintenance Section) | Dallas District | 11 | Shalom Services Corporation | $134,302 | $148,616 | +11% | -53% | TxDOT |
| A00218328 | FLOWABLE FILL, SH0006 (Various to Various) | Bryan District | 2 | Value Drilling Company Inc | $127,395 | $172,500 | +35% | -18% | TxDOT |
| A00217115 | REPAIR/REPLACE CONCRETE BARRIER, IH0045 (Navarro to Maintenance Section) | Dallas District | 9 | Fireman Excavating, Inc. | $124,287 | $175,290 | +41% | -61% | TxDOT |
| A00218562 | TREE TRIMMING AND BRUSH REMOVAL, FM0774 (Various to .) | Corpus Christi District | 6 | Allies Land Clearing | $97,500 | $120,010 | +23% | -39% | TxDOT |
| A00218219 | TREE REMOVAL, US0079 (Various to Various) | Bryan District | 5 | Jackson Excavation, LLC | $94,750 | $100,000 | +6.0% | -25% | TxDOT |
| A00217375 | REPAIR/REPLACE CONCRETE BARRIER, US0075 (VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION) | Dallas District | 7 | Fireman Excavating, Inc. | $89,809 | $175,900 | +96% | -64% | TxDOT |
| A00217176 | LIMESTONE ROCK ASPHALT, US0380 (Denton County to Maintenance Section) | Dallas District | 2 | Vulcan Construction Materials, LLC | $82,240 | $82,505 | 0.0% | +4.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.