TxDOT contract A00215429 bid tabulation

ILLUMINATION MAINTENANCE, IH0035 (VARIOUS LOCATIONS IN to THE AUSTIN DISTRICT). Let by Texas DOT on December 10, 2025, Travis, Austin District. 3 bids received; low bid $455,590 by Austin Traffic Signal Construction Co., Inc., -24% against the engineer's estimate of $599,664.

Owner
Texas DOT
Letting
10 DEC 2025
Pay items
61
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Austin Traffic Signal Construction Co., Inc.$455,590Low-24%
2E-Z Bel Construction, LLC$751,627+65%+25%
3Elecnor Belco Electric, Inc.$1,445,050+217%+141%
TxDOT contract A00215429: bids by rank

Engineer's estimate: $599,664.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Austin Traffic Signal Construction Co., Inc.2. E-Z Bel Construction, LLC3. Elecnor Belco Electric, Inc.
1Removing concrete (riprap) (104-7006)SY10$1,220.00$250.00$50.00$200.00
2Removing concrete (sidewalk, ramp or shared use path) (104-7014)CY10$200.00$250.00$100.00$200.00
3Removing concrete (foundations) (104-7024)CY10$685.00$500.00$100.00$1,000.00
4Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF100$250.00$200.00$300.00$400.00
5Riprap (concrete) (CL B) (4 in) (432-7007)CY10$528.00$500.00$1,000.00$1,000.00
6Mobilization (callout 1) (500-7003)EACH40$2,400.00$1,600.00$4,000.00$5,500.00
7Mobilization (callout 2) (500-7004)EACH5$3,500.00$2,000.00$4,000.00$9,000.00
8Portable changeable message sign (503-7001)DAY10$120.00$500.00$90.00$500.00
9TMA (stationary) (505-7001)DAY30$150.00$250.00$275.00$400.00
10TMA (mobile operation) (505-7002)HR180$60.00$50.00$0.01$250.00
11Biodegradable erosion control logs (install) (12") (506-7044)LF500$6.50$4.00$10.00$10.00
12Biodegradable erosion control logs (remove) (506-7046)LF500$2.50$2.00$1.00$5.00
13In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH4$950.00$1,300.00$1,000.00$1,200.00
14In RD IL (U/P) (type 2) (150W EQ) LED (610-7016)EACH4$1,386.05$1,300.00$1,000.00$1,200.00
15In RD IL (type SA) 40S-8 (250W EQ) LED (610-7116)EACH4$5,800.00$3,800.00$5,000.00$5,800.00
16In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH4$6,700.00$3,900.00$5,300.00$6,300.00
17In RD IL (type SP) 48S-10-10(400W EQ)LED (610-7175)EACH4$6,000.00$6,235.00$7,200.00$9,200.00
18In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198)EACH4$6,501.42$5,000.00$5,600.00$6,600.00
19Conduit (PVC) (schedule 40) (2") (618-7030)LF1,000$15.87$15.00$20.00$28.00
20Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF200$26.34$60.00$100.00$48.00
21Conduit (RM) (1 1/2") (618-7076)LF200$22.61$17.00$30.00$70.00
22Conduit (RM) (2") (618-7078)LF100$32.85$19.00$35.00$90.00
23Electrical conductor (no.10) bare (620-7005)LF500$1.32$1.00$2.00$2.00
24Electrical conductor (no.10) insulated (620-7006)LF1,000$1.31$1.00$2.00$2.00
25Electrical conductor (no.8) bare (620-7007)LF1,500$1.73$3.00$3.00$3.00
26Electrical conductor (no.8) insulated (620-7008)LF4,000$1.90$4.00$3.00$3.00
27Electrical conductor (no.6) bare (620-7009)LF200$2.14$4.00$3.00$4.00
28Electrical conductor (no.6) insulated (620-7010)LF500$2.46$5.00$3.00$4.00
29Electrical conductor (no.4) bare (620-7011)LF200$2.56$4.00$3.00$5.00
30Electrical conductor (no.4) insulated (620-7012)LF200$3.23$5.00$3.00$5.00
31Electrical conductor (no.2) bare (620-7015)LF500$3.89$4.00$5.00$6.00
32Electrical conductor (no.2) insulated (620-7016)LF500$4.04$5.00$5.00$6.00
33Ground box type A (122311)W/apron (624-7002)EACH10$1,556.47$850.00$1,250.00$1,700.00
34Remove ground box (624-7013)EACH4$543.00$175.00$300.00$500.00
35Remove electrical services (628-7002)EACH4$1,208.30$450.00$500.00$1,000.00
36Elc SRV type A 120/240 100(NS)SS(E)GC(O) (628-7022)EACH1$5,000.00$4,500.00$12,000$8,500.00
37Elc SRV type A 120/240 100(NS)SS(E)SP(O) (628-7025)EACH1$5,000.00$5,000.00$11,000$8,500.00
38Elc SRV type A 240/480 100(NS)SS(E)GC(O) (628-7076)EACH1$5,500.00$4,500.00$13,000$8,500.00
39Elc SRV type A 240/480 100(NS)SS(E)PS(U) (628-7078)EACH2$5,500.00$5,000.00$11,000$9,000.00
40Elc SRV type A 240/480 100(NS)SS(E)SP(O) (628-7079)EACH1$5,500.00$5,000.00$10,000$9,500.00
41Replace luminaire pole (690-7126)EACH35$400.00$1,200.00$1,700.00$7,000.00
42Install electrical splice (690-7157)EACH50$116.46$100.00$100.00$100.00
43Repair underground conduit (690-7159)EACH4$26.25$400.00$1,000.00$2,500.00
44Repair underground duct cable (690-7160)EACH4$500.00$500.00$1,000.00$1,000.00
45Maintain high mast illumination (690-7185)EACH10$1,923.28$500.00$1,000.00$3,500.00
46Maintain underpass fixture (690-7187)EACH10$52.50$250.00$500.00$1,500.00
47Maintain induction fluorescent fixture (690-7188)EACH10$146.58$250.00$500.00$1,500.00
48Replace transformer base (690-7197)EACH20$1,115.28$400.00$1,250.00$10,000
49Install ground rod (690-7200)EACH40$69.33$50.00$100.00$350.00
50Replace fuse (690-7218)EACH100$56.59$50.00$100.00$125.00
51Replace fuse holder (690-7219)EACH4$120.00$125.00$100.00$250.00
52Replace breakaway fuse holder (690-7220)EACH40$108.99$200.00$100.00$350.00
53Replace hand-off-auto switch (690-7229)EACH4$293.04$100.00$200.00$3,500.00
54Replace contactor (690-7230)EACH4$415.71$100.00$200.00$2,000.00
55Replace breaker panel (690-7233)EACH4$2,300.16$500.00$200.00$3,500.00
56Install circuit breaker (690-7234)EACH10$633.25$100.00$100.00$300.00
57Replace circuit breaker (690-7235)EACH4$286.07$100.00$100.00$300.00
58Troubleshoot for repairs (690-7242)HR25$183.33$250.00$175.00$150.00
59Replace luminaires (690-7244)EACH200$468.62$165.00$500.00$660.00
60Replace photocell (690-7245)EACH20$86.22$100.00$200.00$350.00
61Subsurface util locate (non-paved area) (5061-7001)EACH5$750.00$500.00$1,000.00$1,000.00
TxDOT contract A00215429: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of December 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy