TxDOT contract A00124687 bid tabulation

Bridge Replacement, FM 2039 (AT PORTER CREEK to .). Let by Texas DOT on December 2, 2025, Burleson, Bryan District. 9 bids received; low bid $2,315,333 by Larry Young Paving, Inc., -3.3% against the engineer's estimate of $2,394,608.

Owner
Texas DOT
Letting
02 DEC 2025
Pay items
95
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Larry Young Paving, Inc.$2,315,333Low-3.0%
2STX Civil$2,373,773+3.0%-1.0%
3Texas Steel Industrial Placing, LLC$2,508,182+8.0%+5.0%
4R Construction Civil, LLC$2,594,067+12%+8.0%
5Knife River Corporation - South$2,612,038+13%+9.0%
6Texas Materials Group, Inc.$2,782,468+20%+16%
7Hodges and Son Construction Company, Inc.$2,948,270+27%+23%
8C. E. Barker, LTD.$3,748,865+62%+57%
9Fuqua Construction Co., Inc.$4,259,517+84%+78%
TxDOT contract A00124687: bids by rank

Engineer's estimate: $2,394,608.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Larry Young Paving, Inc.2. STX Civil3. Texas Steel Industrial Placing, LLC4. R Construction Civil, LLC5. Knife River Corporation - South6. Texas Materials Group, Inc.
1Preparing row (100-7002)STA13.79$4,000.00$910.00$500.00$4,000.00$4,400.00$4,058.00$3,700.00
2Remove (14") TRT/untrt base & asphalt pavement (105-7034)SY2,089$20.00$14.00$12.00$20.00$20.00$6.58$28.00
3Excavation (roadway) (110-7001)CY846$21.00$43.00$35.00$20.00$57.00$12.95$42.00
4Embankment (final)(DC)(type C) (132-7006)CY1,295$32.00$23.00$45.00$25.00$26.00$12.60$35.00
5Furn & place topsoil (4") (160-7002)SY4,221$4.00$3.00$5.00$2.50$8.00$1.27$2.30
6Hydro mulch seed (permanent_rural_sandy) (164-7017)SY4,221$2.00$0.75$0.93$0.83$0.80$0.57$0.82
7Hydro mulch seed (temporary_warm) (164-7021)SY2,111$2.00$0.50$0.93$1.00$0.80$0.46$0.70
8Hydro mulch seed (temporary_cool) (164-7022)SY2,111$2.00$0.75$0.93$1.00$0.80$0.61$0.70
9Vegetative watering (168-7001)TGL42.20$67.00$32.00$70.00$1.00$250.00$47.50$55.00
10Soil ret BLKT(SL_mod_sand_long) (169-7004)SY284$1.75$4.35$6.70$4.00$1.53$4.00
11FL BS (compacted in place)(type A GR 1-2) (8") (247-7067)SY3,036$20.00$36.00$32.00$30.00$18.00$21.50$32.00
12Lime (com or QK)(slurry) or QK(dry) (260-7001)TON21$350.00$410.00$445.00$370.00$345.00$348.00$382.00
13Lime TRT (existing material)(8") (260-7007)SY1,583$7.00$14.00$8.00$10.00$6.00$8.95$12.50
14Cement (275-7001)TON15$300.00$260.00$235.00$300.00$300.00$288.00$242.00
15Cement TRT (existing material)(8") (275-7003)SY1,583$6.00$7.00$5.00$10.00$12.00$4.25$6.00
16Prime coat(MC-30 or AE-P) (310-7013)GAL586$13.00$9.25$8.60$8.00$11.00$9.95$10.00
17Asphalt (AC-20XP) (316-7006)GAL1,615$3.50$8.25$4.00$8.00$17.00$6.20$3.75
18Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241)CY32$550.00$740.00$995.00$850.00$500.00$272.00$485.00
19SP mixes SP-C PG64-22 (344-7009)TON322$200.00$180.00$150.00$200.00$230.00$207.00$188.00
20SP mixes SP-C sac-A PG64-22 (344-7010)TON380$215.00$190.00$180.00$200.00$210.00$208.00$197.00
21SP mixes SP-C PG64-22 (level-UP) (344-7012)TON29$180.00$140.00$230.00$210.00$399.00$235.00
22Planing asphalt concrete pavement(0" to 2") (354-7032)SY558$15.00$25.00$4.00$16.00$7.70$9.00
23Cem stabil BKFL (400-7010)CY211$274.00$130.00$180.00$200.00$130.00$99.40$145.00
24Trench excavation protection (402-7001)LF34$30.00$1.50$50.00$100.00$5.00$625.00$80.00
25Temporary special shoring (403-7001)SF3,611$30.00$36.00$15.00$28.00$45.00$65.00$62.00
26Drilled shaft (24 in) (416-7004)LF420$142.00$250.00$246.65$235.00$233.25$270.00
27Class C concrete (abutment) (420-7012)CY27.30$1,500.00$1,000.00$1,400.00$1,800.00$1,897.00$1,975.00
28Reinforced concrete slab (422-7001)SF2,118$23.00$28.00$27.00$34.00$45.30$49.00
29Approach slab (422-7013)CY65$1,000.00$850.00$725.00$1,500.00$882.90$715.00
30Prestressed concrete slab beam (4SB15) (425-7018)LF396$250.00$250.00$285.52$230.00$224.45$235.00
31Prestressed concrete slab beam (5SB15) (425-7019)LF99$250.00$350.00$348.88$290.00$296.00$290.00
32Riprap (mow strip)(4 in) (432-7013)CY75$700.00$600.00$650.00$725.00$565.00$950.00$964.00
33Riprap (stone protection)(18 in) (432-7043)CY1,287$167.00$170.00$175.00$180.00$240.00$180.00$170.00
34Rail (type T223) (450-7008)LF361$150.00$160.00$185.00$165.00$140.00$237.00$180.00
35Armor joint (sealed) (454-7003)LF84$99.00$215.00$145.00$69.00$101.00$141.00
36Concrete box culvert (10 FT X 10 FT) (462-7038)LF128$1,400.00$1,500.00$1,520.00$1,650.00$1,300.00$2,000.00$1,896.00
37RC pipe (CL III)(18 in) (464-7003)LF83$62.00$90.00$60.00$115.00$97.00$97.00
38Wingwall (PW - 1) (HW=13 FT) (466-7183)EACH1$24,000$96,000$105,000$80,000$115,000$77,575$119,000
39Wingwall (PW - 1) (HW=14 FT) (466-7184)EACH1$44,000$110,000$110,000$90,000$140,000$84,580$132,000
40Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH4$1,300.00$1,250.00$1,000.00$1,400.00$1,410.00$2,075.00
41Removing structure (wingwall) (496-7005)EACH2$2,500.00$9,500.00$2,600.00$3,500.00$2,300.00$7,850.00$4,276.00
42Removing structure (pipe) (496-7007)LF55$28.00$22.00$20.00$41.00$24.00$56.00
43Removing structure (box culvert) (496-7008)LF96$500.00$290.00$125.00$225.00$95.00$523.00$267.00
44Removing structure (bridge 0 - 99 FT length) (496-7009)EACH1$20,000$25,000$50,000$40,000$14,400$35,000
45Removing rock riprap (496-7040)LF46$55.00$27.00$65.00$100.00$24.00$92.40$140.00
46Mobilization (500-7001)LS1$239,500$180,000$185,000$250,592$150,000$249,600$317,400
47Barricades, signs and traffic handling (502-7001)MO12$6,800.00$2,600.00$1,500.00$3,000.00$1,100.00$5,236.00$750.00
48Portable changeable message sign (503-7002)EACH2$8,000.00$2,100.00$7,500.00$20,000$20,000$13,000$3,545.00
49TMA (stationary) (505-7001)DAY18$290.00$260.00$65.00$250.00$225.00$500.00$335.00
50TMA (mobile operation) (505-7003)DAY10$500.00$710.00$65.00$1.00$350.00$900.00$335.00
51Rock filter dams (install) (type 2) (506-7002)LF132$50.00$50.00$50.00$40.00$45.00$41.39$49.00
52Rock filter dams (remove) (506-7011)LF132$19.00$16.00$10.00$10.00$16.00$13.45$11.00
53Construction exits (install) (type 1) (506-7020)SY600$36.00$36.00$50.00$40.00$70.00$29.67$38.00
54Construction exits (remove) (506-7024)SY600$13.00$12.00$10.00$10.00$15.00$10.00$13.00
55Temporary sediment control fence (install) (506-7039)LF2,572$4.75$4.50$5.00$4.00$5.50$3.79$3.80
56Temporary sediment control fence (remove) (506-7041)LF2,572$1.00$1.25$1.00$1.00$1.00$1.00$1.00
57One-way traffic control (port traffic signal) (510-7003)MO7$5,000.00$5,500.00$6,150.00$6,000.00$3,300.00$1,090.00$4,430.00
58Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF540$77.00$64.00$110.00$70.00$75.00$28.00$21.00
59Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF270$65.00$13.00$35.00$20.00$3.00$11.00$17.00
60Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF540$35.00$13.00$45.00$25.00$5.00$28.00$20.00
61Driveways (ACP) (530-7010)SY262$45.00$110.00$65.00$99.00$58.50$64.00
62Turnouts (ACP) (530-7018)SY41$47.00$120.00$100.00$99.00$73.70$87.00
63Metal W-beam guard fence (timber post) (540-7001)LF775$27.00$31.00$28.00$26.00$24.00$25.00$26.00
64Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$2,000.00$2,400.00$2,300.00$2,000.00$1,800.00$2,535.00$2,776.00
65Driveway terminal anchor section (540-7014)EACH1$780.00$1,800.00$1,250.00$2,700.00$1,576.00$1,765.00
66Downstream anchor terminal section (540-7015)EACH1$1,600.00$1,800.00$1,500.00$2,500.00$1,630.00$1,775.00
67Metal W-beam guard fence (special) (540-7017)LF80$31.00$47.00$38.00$34.00$41.30$46.00
68Remove metal beam guard fence (542-7001)LF162.50$4.00$3.00$3.00$2.55$3.00$3.25
69Remove downstream anchor terminal (542-7003)EACH1$260.00$310.00$300.00$170.00$300.00$163.00
70RM metal beam guard fence trans (thrie-beam) (542-7004)EACH4$330.00$185.00$300.00$225.00$163.00$217.00
71Guardrail end treatment (install) (544-7001)EACH6$3,200.00$3,800.00$3,750.00$3,000.00$3,300.00$3,260.00$3,353.00
72Guardrail end treatment (remove) (544-7003)EACH3$330.00$350.00$275.00$225.00$300.00$217.00
73Crash cushion attenuator (move & reset) (545-7002)EACH2$1,700.00$1,600.00$2,130.00$1,750.00$1,700.00$1,630.00$1,910.00
74Crash cushion attenuator (remove) (545-7004)EACH2$1,000.00$1,100.00$1,150.00$1,000.00$500.00$490.00$1,128.00
75Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$9,250.00$7,900.00$9,400.00$8,500.00$6,500.00$9,510.00$1,910.00
76Mailbox install-S (WC-post) type 3 (560-7004)EACH2$420.00$500.00$400.00$77.00$353.25$342.00
77Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH19$750.00$920.00$720.00$800.00$430.00$631.00$668.00
78Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH1$790.00$420.00$800.00$115.00$368.00$598.00
79Remove SM RD SN sup&AM (644-7073)EACH14$115.00$160.00$118.00$150.00$130.00$100.00$107.00
80Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH8$25.00$59.00$35.00$30.00$22.00$24.00$27.00
81Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH23$30.00$59.00$35.00$30.00$28.00$38.00$39.00
82Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH240$6.00$5.25$4.97$4.00$4.50$4.35$4.35
83Work zone pavement marking removing (W)6"(solid) (662-7068)LF3,384$1.00$1.00$1.06$1.00$1.15$0.92$1.10
84Work zone pavement marking removing (W)24"(solid) (662-7077)LF24$18.00$10.00$9.94$10.00$11.00$8.70$11.00
85Work zone pavement marking removing (Y)6"(solid) (662-7100)LF9,600$1.50$1.00$1.06$1.00$1.15$0.92$1.10
86Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH425$1.00$0.75$1.55$1.00$1.15$2.00$1.10
87Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF3,170$3.00$1.75$1.68$1.00$1.15$1.47$1.10
88Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF9,902$1.90$1.75$1.68$1.00$1.15$1.47$1.10
89Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF570$2.25$1.75$1.68$1.25$1.50$1.47$1.35
90Pavement sler 6" (666-7347)LF420$1.25$1.24$0.55$0.65$1.09$0.60
91Prefabricated PM type C (W)(24")(solid) (668-7089)LF10$39.00$37.60$12.00$14.00$33.00$13.00
92Reflectorized pavement marker type II-A-A (672-7004)EACH155$7.00$6.75$6.53$4.50$5.00$5.70$4.90
93Eliminating existing PM & markers (4") (677-7001)LF500$0.25$1.25$1.24$0.95$1.15$1.09$1.00
94Pavement surface preparation for marking (6") (678-7002)LF420$0.25$0.31$0.65$0.80$0.27$0.70
95Bonding course (3007-7001)GAL707$8.00$8.25$6.00$6.00$8.00$5.00$4.55
TxDOT contract A00124687: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy