TxDOT contract A00124687 bid tabulation
Bridge Replacement, FM 2039 (AT PORTER CREEK to .). Let by Texas DOT on December 2, 2025, Burleson, Bryan District. 9 bids received; low bid $2,315,333 by Larry Young Paving, Inc., -3.3% against the engineer's estimate of $2,394,608.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 95
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Larry Young Paving, Inc. | $2,315,333 | Low | -3.0% |
| 2 | STX Civil | $2,373,773 | +3.0% | -1.0% |
| 3 | Texas Steel Industrial Placing, LLC | $2,508,182 | +8.0% | +5.0% |
| 4 | R Construction Civil, LLC | $2,594,067 | +12% | +8.0% |
| 5 | Knife River Corporation - South | $2,612,038 | +13% | +9.0% |
| 6 | Texas Materials Group, Inc. | $2,782,468 | +20% | +16% |
| 7 | Hodges and Son Construction Company, Inc. | $2,948,270 | +27% | +23% |
| 8 | C. E. Barker, LTD. | $3,748,865 | +62% | +57% |
| 9 | Fuqua Construction Co., Inc. | $4,259,517 | +84% | +78% |
Engineer's estimate: $2,394,608.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Larry Young Paving, Inc. | 2. STX Civil | 3. Texas Steel Industrial Placing, LLC | 4. R Construction Civil, LLC | 5. Knife River Corporation - South | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13.79 | $4,000.00 | $910.00 | $500.00 | $4,000.00 | $4,400.00 | $4,058.00 | $3,700.00 |
| 2 | Remove (14") TRT/untrt base & asphalt pavement (105-7034) | SY | 2,089 | $20.00 | $14.00 | $12.00 | $20.00 | $20.00 | $6.58 | $28.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 846 | $21.00 | $43.00 | $35.00 | $20.00 | $57.00 | $12.95 | $42.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,295 | $32.00 | $23.00 | $45.00 | $25.00 | $26.00 | $12.60 | $35.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 4,221 | $4.00 | $3.00 | $5.00 | $2.50 | $8.00 | $1.27 | $2.30 |
| 6 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 4,221 | $2.00 | $0.75 | $0.93 | $0.83 | $0.80 | $0.57 | $0.82 |
| 7 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 2,111 | $2.00 | $0.50 | $0.93 | $1.00 | $0.80 | $0.46 | $0.70 |
| 8 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 2,111 | $2.00 | $0.75 | $0.93 | $1.00 | $0.80 | $0.61 | $0.70 |
| 9 | Vegetative watering (168-7001) | TGL | 42.20 | $67.00 | $32.00 | $70.00 | $1.00 | $250.00 | $47.50 | $55.00 |
| 10 | Soil ret BLKT(SL_mod_sand_long) (169-7004) | SY | 284 | $1.75 | $4.35 | $6.70 | $4.00 | $1.53 | $4.00 | |
| 11 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 3,036 | $20.00 | $36.00 | $32.00 | $30.00 | $18.00 | $21.50 | $32.00 |
| 12 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 21 | $350.00 | $410.00 | $445.00 | $370.00 | $345.00 | $348.00 | $382.00 |
| 13 | Lime TRT (existing material)(8") (260-7007) | SY | 1,583 | $7.00 | $14.00 | $8.00 | $10.00 | $6.00 | $8.95 | $12.50 |
| 14 | Cement (275-7001) | TON | 15 | $300.00 | $260.00 | $235.00 | $300.00 | $300.00 | $288.00 | $242.00 |
| 15 | Cement TRT (existing material)(8") (275-7003) | SY | 1,583 | $6.00 | $7.00 | $5.00 | $10.00 | $12.00 | $4.25 | $6.00 |
| 16 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 586 | $13.00 | $9.25 | $8.60 | $8.00 | $11.00 | $9.95 | $10.00 |
| 17 | Asphalt (AC-20XP) (316-7006) | GAL | 1,615 | $3.50 | $8.25 | $4.00 | $8.00 | $17.00 | $6.20 | $3.75 |
| 18 | Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241) | CY | 32 | $550.00 | $740.00 | $995.00 | $850.00 | $500.00 | $272.00 | $485.00 |
| 19 | SP mixes SP-C PG64-22 (344-7009) | TON | 322 | $200.00 | $180.00 | $150.00 | $200.00 | $230.00 | $207.00 | $188.00 |
| 20 | SP mixes SP-C sac-A PG64-22 (344-7010) | TON | 380 | $215.00 | $190.00 | $180.00 | $200.00 | $210.00 | $208.00 | $197.00 |
| 21 | SP mixes SP-C PG64-22 (level-UP) (344-7012) | TON | 29 | $180.00 | $140.00 | $230.00 | $210.00 | $399.00 | $235.00 | |
| 22 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 558 | $15.00 | $25.00 | $4.00 | $16.00 | $7.70 | $9.00 | |
| 23 | Cem stabil BKFL (400-7010) | CY | 211 | $274.00 | $130.00 | $180.00 | $200.00 | $130.00 | $99.40 | $145.00 |
| 24 | Trench excavation protection (402-7001) | LF | 34 | $30.00 | $1.50 | $50.00 | $100.00 | $5.00 | $625.00 | $80.00 |
| 25 | Temporary special shoring (403-7001) | SF | 3,611 | $30.00 | $36.00 | $15.00 | $28.00 | $45.00 | $65.00 | $62.00 |
| 26 | Drilled shaft (24 in) (416-7004) | LF | 420 | $142.00 | $250.00 | $246.65 | $235.00 | $233.25 | $270.00 | |
| 27 | Class C concrete (abutment) (420-7012) | CY | 27.30 | $1,500.00 | $1,000.00 | $1,400.00 | $1,800.00 | $1,897.00 | $1,975.00 | |
| 28 | Reinforced concrete slab (422-7001) | SF | 2,118 | $23.00 | $28.00 | $27.00 | $34.00 | $45.30 | $49.00 | |
| 29 | Approach slab (422-7013) | CY | 65 | $1,000.00 | $850.00 | $725.00 | $1,500.00 | $882.90 | $715.00 | |
| 30 | Prestressed concrete slab beam (4SB15) (425-7018) | LF | 396 | $250.00 | $250.00 | $285.52 | $230.00 | $224.45 | $235.00 | |
| 31 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 99 | $250.00 | $350.00 | $348.88 | $290.00 | $296.00 | $290.00 | |
| 32 | Riprap (mow strip)(4 in) (432-7013) | CY | 75 | $700.00 | $600.00 | $650.00 | $725.00 | $565.00 | $950.00 | $964.00 |
| 33 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,287 | $167.00 | $170.00 | $175.00 | $180.00 | $240.00 | $180.00 | $170.00 |
| 34 | Rail (type T223) (450-7008) | LF | 361 | $150.00 | $160.00 | $185.00 | $165.00 | $140.00 | $237.00 | $180.00 |
| 35 | Armor joint (sealed) (454-7003) | LF | 84 | $99.00 | $215.00 | $145.00 | $69.00 | $101.00 | $141.00 | |
| 36 | Concrete box culvert (10 FT X 10 FT) (462-7038) | LF | 128 | $1,400.00 | $1,500.00 | $1,520.00 | $1,650.00 | $1,300.00 | $2,000.00 | $1,896.00 |
| 37 | RC pipe (CL III)(18 in) (464-7003) | LF | 83 | $62.00 | $90.00 | $60.00 | $115.00 | $97.00 | $97.00 | |
| 38 | Wingwall (PW - 1) (HW=13 FT) (466-7183) | EACH | 1 | $24,000 | $96,000 | $105,000 | $80,000 | $115,000 | $77,575 | $119,000 |
| 39 | Wingwall (PW - 1) (HW=14 FT) (466-7184) | EACH | 1 | $44,000 | $110,000 | $110,000 | $90,000 | $140,000 | $84,580 | $132,000 |
| 40 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 4 | $1,300.00 | $1,250.00 | $1,000.00 | $1,400.00 | $1,410.00 | $2,075.00 | |
| 41 | Removing structure (wingwall) (496-7005) | EACH | 2 | $2,500.00 | $9,500.00 | $2,600.00 | $3,500.00 | $2,300.00 | $7,850.00 | $4,276.00 |
| 42 | Removing structure (pipe) (496-7007) | LF | 55 | $28.00 | $22.00 | $20.00 | $41.00 | $24.00 | $56.00 | |
| 43 | Removing structure (box culvert) (496-7008) | LF | 96 | $500.00 | $290.00 | $125.00 | $225.00 | $95.00 | $523.00 | $267.00 |
| 44 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $20,000 | $25,000 | $50,000 | $40,000 | $14,400 | $35,000 | |
| 45 | Removing rock riprap (496-7040) | LF | 46 | $55.00 | $27.00 | $65.00 | $100.00 | $24.00 | $92.40 | $140.00 |
| 46 | Mobilization (500-7001) | LS | 1 | $239,500 | $180,000 | $185,000 | $250,592 | $150,000 | $249,600 | $317,400 |
| 47 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $6,800.00 | $2,600.00 | $1,500.00 | $3,000.00 | $1,100.00 | $5,236.00 | $750.00 |
| 48 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $2,100.00 | $7,500.00 | $20,000 | $20,000 | $13,000 | $3,545.00 |
| 49 | TMA (stationary) (505-7001) | DAY | 18 | $290.00 | $260.00 | $65.00 | $250.00 | $225.00 | $500.00 | $335.00 |
| 50 | TMA (mobile operation) (505-7003) | DAY | 10 | $500.00 | $710.00 | $65.00 | $1.00 | $350.00 | $900.00 | $335.00 |
| 51 | Rock filter dams (install) (type 2) (506-7002) | LF | 132 | $50.00 | $50.00 | $50.00 | $40.00 | $45.00 | $41.39 | $49.00 |
| 52 | Rock filter dams (remove) (506-7011) | LF | 132 | $19.00 | $16.00 | $10.00 | $10.00 | $16.00 | $13.45 | $11.00 |
| 53 | Construction exits (install) (type 1) (506-7020) | SY | 600 | $36.00 | $36.00 | $50.00 | $40.00 | $70.00 | $29.67 | $38.00 |
| 54 | Construction exits (remove) (506-7024) | SY | 600 | $13.00 | $12.00 | $10.00 | $10.00 | $15.00 | $10.00 | $13.00 |
| 55 | Temporary sediment control fence (install) (506-7039) | LF | 2,572 | $4.75 | $4.50 | $5.00 | $4.00 | $5.50 | $3.79 | $3.80 |
| 56 | Temporary sediment control fence (remove) (506-7041) | LF | 2,572 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | One-way traffic control (port traffic signal) (510-7003) | MO | 7 | $5,000.00 | $5,500.00 | $6,150.00 | $6,000.00 | $3,300.00 | $1,090.00 | $4,430.00 |
| 58 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 540 | $77.00 | $64.00 | $110.00 | $70.00 | $75.00 | $28.00 | $21.00 |
| 59 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 270 | $65.00 | $13.00 | $35.00 | $20.00 | $3.00 | $11.00 | $17.00 |
| 60 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 540 | $35.00 | $13.00 | $45.00 | $25.00 | $5.00 | $28.00 | $20.00 |
| 61 | Driveways (ACP) (530-7010) | SY | 262 | $45.00 | $110.00 | $65.00 | $99.00 | $58.50 | $64.00 | |
| 62 | Turnouts (ACP) (530-7018) | SY | 41 | $47.00 | $120.00 | $100.00 | $99.00 | $73.70 | $87.00 | |
| 63 | Metal W-beam guard fence (timber post) (540-7001) | LF | 775 | $27.00 | $31.00 | $28.00 | $26.00 | $24.00 | $25.00 | $26.00 |
| 64 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,000.00 | $2,400.00 | $2,300.00 | $2,000.00 | $1,800.00 | $2,535.00 | $2,776.00 |
| 65 | Driveway terminal anchor section (540-7014) | EACH | 1 | $780.00 | $1,800.00 | $1,250.00 | $2,700.00 | $1,576.00 | $1,765.00 | |
| 66 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,600.00 | $1,800.00 | $1,500.00 | $2,500.00 | $1,630.00 | $1,775.00 | |
| 67 | Metal W-beam guard fence (special) (540-7017) | LF | 80 | $31.00 | $47.00 | $38.00 | $34.00 | $41.30 | $46.00 | |
| 68 | Remove metal beam guard fence (542-7001) | LF | 162.50 | $4.00 | $3.00 | $3.00 | $2.55 | $3.00 | $3.25 | |
| 69 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $260.00 | $310.00 | $300.00 | $170.00 | $300.00 | $163.00 | |
| 70 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $330.00 | $185.00 | $300.00 | $225.00 | $163.00 | $217.00 | |
| 71 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,200.00 | $3,800.00 | $3,750.00 | $3,000.00 | $3,300.00 | $3,260.00 | $3,353.00 |
| 72 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $330.00 | $350.00 | $275.00 | $225.00 | $300.00 | $217.00 | |
| 73 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $1,700.00 | $1,600.00 | $2,130.00 | $1,750.00 | $1,700.00 | $1,630.00 | $1,910.00 |
| 74 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,000.00 | $1,100.00 | $1,150.00 | $1,000.00 | $500.00 | $490.00 | $1,128.00 |
| 75 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $9,250.00 | $7,900.00 | $9,400.00 | $8,500.00 | $6,500.00 | $9,510.00 | $1,910.00 |
| 76 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 2 | $420.00 | $500.00 | $400.00 | $77.00 | $353.25 | $342.00 | |
| 77 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 19 | $750.00 | $920.00 | $720.00 | $800.00 | $430.00 | $631.00 | $668.00 |
| 78 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 1 | $790.00 | $420.00 | $800.00 | $115.00 | $368.00 | $598.00 | |
| 79 | Remove SM RD SN sup&AM (644-7073) | EACH | 14 | $115.00 | $160.00 | $118.00 | $150.00 | $130.00 | $100.00 | $107.00 |
| 80 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 8 | $25.00 | $59.00 | $35.00 | $30.00 | $22.00 | $24.00 | $27.00 |
| 81 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 23 | $30.00 | $59.00 | $35.00 | $30.00 | $28.00 | $38.00 | $39.00 |
| 82 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 240 | $6.00 | $5.25 | $4.97 | $4.00 | $4.50 | $4.35 | $4.35 |
| 83 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 3,384 | $1.00 | $1.00 | $1.06 | $1.00 | $1.15 | $0.92 | $1.10 |
| 84 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 24 | $18.00 | $10.00 | $9.94 | $10.00 | $11.00 | $8.70 | $11.00 |
| 85 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 9,600 | $1.50 | $1.00 | $1.06 | $1.00 | $1.15 | $0.92 | $1.10 |
| 86 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 425 | $1.00 | $0.75 | $1.55 | $1.00 | $1.15 | $2.00 | $1.10 |
| 87 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 3,170 | $3.00 | $1.75 | $1.68 | $1.00 | $1.15 | $1.47 | $1.10 |
| 88 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 9,902 | $1.90 | $1.75 | $1.68 | $1.00 | $1.15 | $1.47 | $1.10 |
| 89 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 570 | $2.25 | $1.75 | $1.68 | $1.25 | $1.50 | $1.47 | $1.35 |
| 90 | Pavement sler 6" (666-7347) | LF | 420 | $1.25 | $1.24 | $0.55 | $0.65 | $1.09 | $0.60 | |
| 91 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 10 | $39.00 | $37.60 | $12.00 | $14.00 | $33.00 | $13.00 | |
| 92 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 155 | $7.00 | $6.75 | $6.53 | $4.50 | $5.00 | $5.70 | $4.90 |
| 93 | Eliminating existing PM & markers (4") (677-7001) | LF | 500 | $0.25 | $1.25 | $1.24 | $0.95 | $1.15 | $1.09 | $1.00 |
| 94 | Pavement surface preparation for marking (6") (678-7002) | LF | 420 | $0.25 | $0.31 | $0.65 | $0.80 | $0.27 | $0.70 | |
| 95 | Bonding course (3007-7001) | GAL | 707 | $8.00 | $8.25 | $6.00 | $6.00 | $8.00 | $5.00 | $4.55 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.