TxDOT contract A00133631 bid tabulation
Install/Upgrade Drainage Structure(S), FM 3257 (1.44 Miles North of US 287, North to 1.88 Miles North of US 287). Let by Texas DOT on November 5, 2025, Donley, Childress District. 6 bids received; low bid $1,781,819 by Earth Builders, L.P., -17% against the engineer's estimate of $2,141,909.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 33
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Earth Builders, L.P. | $1,781,819 | Low | -17% |
| 2 | Gilvin-Terrill, LTD. | $1,932,978 | +8.0% | -10% |
| 3 | J. Lee Milligan, Inc. | $1,955,763 | +10% | -9.0% |
| 4 | STX Civil | $2,069,711 | +16% | -3.0% |
| 5 | Ti-Zack Concrete, LLC | $2,095,592 | +18% | -2.0% |
| 6 | C. E. Barker, LTD. | $2,436,653 | +37% | +14% |
Engineer's estimate: $2,141,909.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Earth Builders, L.P. | 2. Gilvin-Terrill, LTD. | 3. J. Lee Milligan, Inc. | 4. STX Civil | 5. Ti-Zack Concrete, LLC | 6. C. E. Barker, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 2 | $3,500.00 | $3,500.00 | $5,000.00 | $11,500 | $4,000.00 | $2,200.00 | $7,196.25 |
| 2 | Excavation (roadway) (110-7001) | CY | 490 | $33.00 | $25.00 | $27.50 | $75.00 | $35.00 | $275.00 | $26.48 |
| 3 | Embankment (final)(DC)(type A) (132-7002) | CY | 8,471 | $18.00 | $35.00 | $27.50 | $26.00 | $30.00 | $27.50 | $35.12 |
| 4 | Blading (150-7002) | HR | 35 | $200.00 | $100.00 | $160.00 | $535.00 | $180.00 | $275.00 | $120.90 |
| 5 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 3.72 | $900.00 | $2,100.00 | $1,000.00 | $1,000.00 | $6,000.00 | $1,100.00 | $1,727.10 |
| 6 | Vegetative watering (168-7001) | TGL | 90 | $40.00 | $50.00 | $10.00 | $50.00 | $100.00 | $605.00 | $120.90 |
| 7 | FL BS (compacted in place)(type A GR 3) (12") (247-7114) | SY | 7,349 | $33.00 | $48.00 | $50.00 | $50.00 | $50.00 | $38.50 | $46.09 |
| 8 | Prime coat (MC-30) (310-7004) | GAL | 2,201 | $15.00 | $6.00 | $5.00 | $5.50 | $15.00 | $82.50 | $17.27 |
| 9 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 1,380 | $4.00 | $6.00 | $5.00 | $5.40 | $10.00 | $16.50 | $25.61 |
| 10 | Asphalt (CRS-2P) (316-7012) | GAL | 7,391 | $6.00 | $8.00 | $7.00 | $4.40 | $6.00 | $5.50 | $23.03 |
| 11 | Aggregate (type-E, GR-4S)(sac-A) (316-7117) | CY | 120 | $115.00 | $250.00 | $150.00 | $130.00 | $280.00 | $825.00 | $656.30 |
| 12 | Struct excavation (400-7001) | CY | 102 | $28.00 | $25.00 | $50.00 | $30.00 | $60.00 | $60.50 | $51.81 |
| 13 | Flowable backfill (401-7001) | CY | 10 | $645.00 | $300.00 | $500.00 | $325.00 | $1,000.00 | $825.00 | $270.58 |
| 14 | Temporary special shoring (403-7001) | SF | 1,746 | $65.00 | $10.00 | $100.00 | $20.00 | $50.00 | $73.70 | $15.54 |
| 15 | Riprap (mow strip)(4 in) (432-7013) | CY | 15 | $800.00 | $800.00 | $800.00 | $845.00 | $800.00 | $742.50 | $921.12 |
| 16 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 100 | $165.00 | $230.00 | $500.00 | $430.00 | $250.00 | $357.50 | $270.58 |
| 17 | Rail (type T631) (450-7020) | LF | 244 | $105.00 | $120.00 | $125.00 | $135.00 | $115.00 | $275.00 | $143.93 |
| 18 | Concrete box culvert (10 FT X 8 FT) (462-7036) | LF | 136 | $2,000.00 | $1,750.00 | $3,000.00 | $1,600.00 | $2,000.00 | $1,980.00 | $4,450.00 |
| 19 | Wingwall (PW - 1) (HW=14 FT) (466-7184) | EACH | 2 | $50,000 | $120,000 | $70,000 | $134,350 | $105,000 | $27,500 | $125,000 |
| 20 | Removing structure (box culvert) (496-7001) | EACH | 1 | $270.00 | $45,000 | $15,000 | $65,000 | $15,000 | $13,200 | $87,500 |
| 21 | Mobilization (500-7001) | LS | 1 | $194,711 | $180,000 | $157,500 | $195,000 | $145,000 | $160,000 | $220,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $10,000 | $4,000.00 | $6,200.00 | $32,500 | $3,000.00 | $24,050 | $4,074.80 |
| 23 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 692 | $9.50 | $15.00 | $6.00 | $10.00 | $10.00 | $5.50 | $23.03 |
| 24 | Biodegradable erosion control logs (remove) (506-7046) | LF | 692 | $2.50 | $3.00 | $1.00 | $5.50 | $3.00 | $2.20 | $11.51 |
| 25 | Constructing detours (508-7001) | SY | 2,420 | $325.00 | $50.00 | $55.00 | $48.50 | $165.00 | $36.30 | $23.98 |
| 26 | Metal W-beam guard fence (steel post) (540-7002) | LF | 100 | $39.00 | $32.00 | $45.00 | $45.50 | $38.00 | $82.50 | $49.51 |
| 27 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,500.00 | $4,000.00 | $4,225.00 | $3,800.00 | $5,940.00 | $4,605.60 |
| 28 | Relocate existing mailbox (560-7012) | EACH | 1 | $450.00 | $250.00 | $300.00 | $325.00 | $480.00 | $825.00 | $35.69 |
| 29 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $110.00 | $150.00 | $150.00 | $160.00 | $100.00 | $715.00 | $345.42 |
| 30 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 14 | $50.00 | $35.00 | $31.00 | $35.00 | $50.00 | $27.50 | $172.71 |
| 31 | Remove delin & object marker assms (658-7078) | EACH | 4 | $21.00 | $20.00 | $15.00 | $20.00 | $1.00 | $110.00 | $17.27 |
| 32 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,600 | $0.55 | $2.70 | $2.50 | $2.64 | $0.50 | $2.75 | $2.88 |
| 33 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 4,600 | $0.55 | $2.70 | $2.50 | $2.64 | $0.90 | $2.75 | $2.88 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way