TxDOT contract A00194184 bid tabulation

Bridge Replacement, HAMMAN ST (At Cottonwood Creek to STR# B009-60-001). Let by Texas DOT on October 8, 2025, Matagorda, Yoakum District. 5 bids received; low bid $4,866,603 by E-Z Bel Construction, LLC, +7.6% against the engineer's estimate of $4,523,384.

Owner
Texas DOT
Letting
08 OCT 2025
Pay items
92
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1E-Z Bel Construction, LLC$4,866,603Low+8.0%
2STX Civil$4,876,7480.0%+8.0%
3C. E. Barker, LTD.$5,212,443+7.0%+15%
4Ragle Construction, Inc.$6,726,952+38%+49%
5Forde Construction Company, Inc.$6,788,622+39%+50%
TxDOT contract A00194184: bids by rank

Engineer's estimate: $4,523,384.

Bid tabulation

LinePay itemUnitQuantityEstimate1. E-Z Bel Construction, LLC2. STX Civil3. C. E. Barker, LTD.4. Ragle Construction, Inc.5. Forde Construction Company, Inc.
1Preparing row (100-7002)STA8.70$2,500.00$1,800.00$8,500.00$55,000$59,700$15,000
2Removing concrete (pavement) (104-7001)SY1,178$38.00$25.00$14.03$10.00$56.00
3Excavation (roadway) (110-7001)CY705$22.00$25.00$20.00$56.10$75.00$77.00
4Excavation (channel) (110-7002)CY1,332$20.00$25.00$25.00$34.78$19.00$69.00
5Embankment (final)(OC)(type C) (132-7005)CY1,167$30.00$40.00$50.00$34.78$30.00$88.00
6Blading (150-7002)HR48$120.00$50.00$100.00$117.81$177.00$125.00
7Block sodding (162-7002)SY2,373$7.50$8.00$6.00$11.22$12.00$13.00
8Broadcast seed (permanent_rural_sand) (164-7001)SY1,225$0.16$1.00$1.12$1.00$3.40
9Broadcast seed (temporary_warm) (164-7005)SY902$1.00$1.00$1.00$1.12$0.75$3.00
10Broadcast seed (temporary_cool) (164-7006)SY902$1.00$1.00$1.00$1.12$0.75$3.00
11Vegetative watering (168-7001)TGL46.50$100.00$72.00$50.00$117.81$117.00$93.00
12FL BS (compacted in place)(type E GR 5)(final pos) (247-7196)CY620$129.00$175.00$130.00$142.38$134.00$207.00
13Lime (com or QK)(slurry) (260-7005)TON24$375.00$470.00$394.94$352.00$542.00
14Lime TRT (existing material)(8") (260-7007)SY1,485$11.00$14.00$5.89$7.10$32.00
15Asphalt (RC-250) (316-7016)GAL465$15.00$18.00$15.00$11.22$17.75$6.00
16Aggregate (type-E, GR-5)(sac-B) (316-7194)CY19.50$550.00$1,000.00$1,200.00$841.50$1,000.00$1,100.00
17Aggregate (type-PE, GR-4)(sac-B) (316-7232)CY19.60$1,300.00$1,005.00$1,250.00$841.50$1,005.00$1,100.00
18Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264)GAL790$20.00$15.00$15.00$11.22$15.10$5.00
19D-GR HMA type-B PG64-22 (341-7001)TON413$181.00$200.00$196.35$210.00$262.00
20D-GR HMA type D sac-B PG70-22 (341-7050)TON125$225.00$180.00$200.00$218.79$290.00$435.00
21Concrete pavement (CPCD) (7") (360-7017)SY1,802$150.00$110.00$105.80$70.50$143.00
22Cem stabil BKFL (400-7010)CY1,137$150.00$360.00$150.00$98.18$140.00$170.00
23Trench excavation protection (402-7001)LF244$22.00$1.00$35.00$46.00$56.00$5.00
24Temporary special shoring (403-7001)SF2,800$4.00$20.00$33.66$120.00$55.00
25Temporary special shoring (cofferdam) (403-7002)SF3,000$50.00$50.00$16.83$70.00$20.00
26Sheet piling (PZ - 40) (407-7004)SF5,381$90.00$100.00$76.55$85.00$138.00
27Prestressed concrete pil (18 in SQ) (409-7002)LF924$250.00$250.00$303.65$169.00$350.00
28Drilled shaft (30 in) (416-7005)LF495$360.00$290.00$360.00$345.58$299.00$500.00
29Class C concrete (abutment) (420-7012)CY73$1,200.00$1,000.00$1,350.00$2,401.08$1,052.00$3,900.00
30Class C concrete (rail foundation) (420-7052)CY69.50$400.00$1,300.00$830.28$680.00$1,400.00
31Class C concrete (miscellaneous) (420-7067)CY3.70$509.00$1,000.00$830.28$870.00$1,800.00
32Reinforced concrete slab (box beam) (422-7005)SF4,755$30.00$20.00$30.00$37.61$25.00$34.00
33Bridge sidewalk (422-7012)SF467$25.00$10.00$35.00$10.38$17.00$67.00
34Shear key (422-7020)CY36.10$700.00$805.00$850.00$392.70$554.00$250.00
35Prestressed concrete box beam (4B20) (425-7026)LF238$325.00$340.00$299.80$303.00$410.00
36Prestressed concrete box beam (5B20) (425-7027)LF119$325.00$340.00$299.80$369.00$436.00
37Prestressed concrete box beam (5B28) (425-7029)LF625.50$370.00$325.00$340.00$337.10$320.00$420.00
38Riprap (stone protection)(18 in) (432-7043)CY818$200.00$350.00$220.00$163.81$209.00$330.00
39STR steel (miscellaneous non-bridge) (442-7007)LB140$30.00$32.00$20.00$28.05$33.00$60.00
40Rail (type T223) (450-7008)LF152$160.00$200.00$180.92$134.00$225.00
41Rail (type C223) (450-7034)LF411.40$75.00$140.00$240.00$309.95$165.00$252.00
42Armor joint (sealed) (454-7003)LF112$150.00$108.00$160.00$112.20$120.00$230.00
43Concrete box culvert (9 FT X 9 FT) (462-7031)LF558$1,550.00$1,700.00$1,613.82$1,640.00$2,000.00
44RC pipe (CL III)(18 in) (464-7003)LF124$140.00$102.00$104.86$121.00$120.00
45RC pipe (CL III)(24 in) (464-7005)LF103$170.00$205.00$120.00$116.27$137.00$150.00
46RC pipe (CL III)(42 in) (464-7010)LF25$200.00$318.00$280.00$218.88$323.00$530.00
47RC pipe (CL III)(54 in) (464-7012)LF90$400.00$490.00$575.00$369.90$501.00$478.00
48RC pipe (CL III)(60 in) (464-7013)LF78$450.00$561.00$675.00$413.14$576.00$555.00
49Junction box(complete)(PJB)(3FTX3FT) (465-7005)EACH1$13,482$2,800.00$7,923.00$5,100.00$13,000
50Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070)EACH1$7,500.00$13,936$8,000.00$12,321$8,820.00$15,200
51Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH3$8,557.00$4,000.00$8,953.00$5,800.00$15,300
52Inlet (complete)(PSL)(FG)(4FTX5FT-4FTX4FT) (465-7132)EACH1$10,000$15,020$22,000$13,563$18,000$18,000
53Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$2,085.00$1,300.00$3,146.42$2,350.00$2,800.00
54Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH1$3,000.00$2,939.00$2,300.00$3,700.80$3,100.00$6,600.00
55Removing structure (manhole) (496-7003)EACH2$1,200.00$3,802.00$500.00$701.25$1,300.00$12,000
56Removing structure (bridge 0 - 99 FT length) (496-7009)EACH3$25,000$32,000$30,000$41,234$400,000$50,000
57Removing structure (small) (496-7036)EACH11$1,500.00$1,354.00$250.00$1,178.10$5,000.00$1,200.00
58Mobilization (500-7001)LS1$410,000$300,000$360,000$450,000$600,000$660,000
59Barricades, signs and traffic handling (502-7001)MO18$2,500.00$1,500.00$2,800.00$3,646.50$10,000$2,500.00
60Portable changeable message sign (503-7002)EACH2$10,000$2,500.00$1.00$22,440$12,000$14,000
61Rock filter dams (install) (type 1) (506-7006)CY18$320.00$150.00$280.00$56.10$150.00$400.00
62Rock filter dams (remove) (506-7012)CY18$70.00$65.00$10.00$22.44$65.00$144.00
63Sandbags for erosion control (506-7035)EACH90$21.50$16.00$1.00$22.44$16.00$11.00
64Temporary sediment control fence (install) (506-7039)LF1,471$4.00$5.00$1.00$5.61$5.00$8.00
65Temporary sediment control fence (remove) (506-7041)LF1,471$1.00$3.00$1.00$2.24$2.50$2.30
66Biodegradable erosion control logs (install) (6") (506-7042)LF100$7.50$10.00$1.00$11.22$10.00$14.00
67Biodegradable erosion control logs (install) (8") (506-7043)LF65$10.00$1.00$16.83$10.00$14.00
68Biodegradable erosion control logs (remove) (506-7046)LF165$2.50$5.00$1.00$8.98$5.00$3.00
69Concrete curb (mono) (type II) (529-7007)LF486$23.00$30.00$8.42$15.00$28.00
70Concrete curb & gutter (type II) (529-7009)LF33$90.00$34.00$50.00$8.42$45.00$250.00
71Concrete curb & gutter (slotted) (529-7021)LF260$60.00$45.00$60.00$8.42$34.00$45.00
72Driveways (ACP) (530-7010)SY190$60.00$75.00$110.00$56.10$84.00$150.00
73Concrete sidewalks (5") (531-7002)SY287$105.00$150.00$95.00$103.79$73.00$120.00
74Curb ramps (type 7) (531-7020)SY8$2,958.00$280.00$103.79$241.00$630.00
75Curb ramps (type 10) (531-7021)SY25$2,800.00$280.00$103.79$362.00$380.00
76Metal W-beam guard fence (timber post) (540-7001)LF50$36.00$32.00$39.27$36.45$64.00
77Metal beam guard fence trans (TL2) (540-7006)EACH4$1,855.00$1,800.00$2,805.00$1,855.00$3,300.00
78Downstream anchor terminal section (540-7015)EACH2$1,290.00$1,500.00$2,805.00$1,290.00$2,300.00
79Guardrail end treatment (install) (544-7001)EACH2$3,650.00$3,400.00$3,927.00$3,650.00$6,400.00
80Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH5$525.00$810.00$1,000.00$841.50$550.00$960.00
81Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH18$25.00$21.00$35.00$56.10$24.50$43.00
82Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH6$28.00$35.00$56.10$30.00$52.00
83Remove delin & object marker assms (658-7078)EACH8$25.00$55.00$1.00$22.44$55.00$33.00
84Install delineator assembly (D-SW)SZ 1(WFLX)GNDLL (658-7105)EACH12$60.00$106.00$485.00$56.10$70.00$123.00
85Install object marker assembly (OM-2Y)(WC)GNDLL (658-7246)EACH2$195.00$485.00$56.10$84.00$147.00
86Install object marker assembly (OM-3L)(TWT)GNDLL (658-7270)EACH4$375.00$390.00$485.00$56.10$265.00$463.00
87Install object marker assembly (OM-3R)(TWT)GNDLL (658-7278)EACH4$375.00$390.00$485.00$56.10$265.00$463.00
88Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF720$1.50$2.00$1.80$13.46$2.00$2.50
89Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF720$1.50$2.00$1.80$13.46$2.00$2.50
90Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF720$2.50$3.00$3.50$13.46$2.50$5.30
91Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF720$2.50$3.00$3.50$13.46$2.50$5.30
92Pavement surface preparation for marking (6") (678-7002)LF280$3.60$1.00$0.10$5.61$1.00$0.10
TxDOT contract A00194184: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy