TxDOT contract A00043203 bid tabulation
Bridge Replacement, N TRINITY RD (TRINITY ROAD AT COOPER CREEK to IN CITY OF DENTON). Let by Texas DOT on September 4, 2025, Denton, Dallas District. 8 bids received; low bid $1,636,169 by Skyline Bridge LLC, -2.6% against the engineer's estimate of $1,679,259.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Skyline Bridge LLC | $1,636,169 | Low | -3.0% |
| 2 | Hodges and Son Construction Company, Inc. | $1,651,972 | +1.0% | -2.0% |
| 3 | Ed Bell Construction Company | $1,659,811 | +1.0% | -1.0% |
| 4 | Ragle Construction, Inc. | $1,683,730 | +3.0% | 0.0% |
| 5 | Ibctx, LLC | $1,783,810 | +9.0% | +6.0% |
| 6 | STX Civil | $1,915,320 | +17% | +14% |
| 7 | Grey Sky Construction LLC | $1,938,217 | +18% | +15% |
| 8 | C. E. Barker, LTD. | $1,959,319 | +20% | +17% |
Engineer's estimate: $1,679,259.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Skyline Bridge LLC | 2. Hodges and Son Construction Company, Inc. | 3. Ed Bell Construction Company | 4. Ragle Construction, Inc. | 5. Ibctx, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 5.44 | $6,500.00 | $3,500.00 | $4,500.00 | $17,500 | $30,000 | $13,000 | $6,500.00 |
| 2 | Remove (0"-6") TRT/untrt base & asphalt pavement (105-7046) | SY | 1,568 | $12.00 | $15.00 | $20.00 | $6.50 | $9.10 | $8.00 | $7.50 |
| 3 | Excavation (roadway) (110-7001) | CY | 1,749 | $25.00 | $16.00 | $25.00 | $20.00 | $24.10 | $45.00 | $20.00 |
| 4 | Excavation (channel) (110-7002) | CY | 473 | $28.00 | $20.00 | $25.00 | $35.00 | $30.00 | $63.00 | $30.00 |
| 5 | Embankment (final)(DC)(type C1) (132-7008) | CY | 431 | $25.00 | $40.00 | $30.00 | $30.00 | $20.50 | $63.00 | $40.00 |
| 6 | Embankment (final)(DC)(type C2) (132-7010) | CY | 606 | $80.00 | $50.00 | $30.00 | $50.00 | $34.00 | $87.00 | $40.00 |
| 7 | Block sodding (162-7002) | SY | 2,444 | $8.00 | $5.00 | $8.00 | $5.25 | $10.75 | $10.00 | $7.50 |
| 8 | Vegetative watering (168-7001) | TGL | 364 | $20.00 | $1.00 | $1.00 | $3.15 | $10.00 | $1.00 | $55.00 |
| 9 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 1,904 | $38.00 | $60.00 | $50.00 | $40.00 | $26.10 | $35.00 | $72.00 |
| 10 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 381 | $8.00 | $22.00 | $10.00 | $11.00 | $6.10 | $11.00 | $7.00 |
| 11 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 187 | $180.00 | $265.00 | $220.00 | $240.00 | $232.00 | $225.00 | $315.00 |
| 12 | Drilled shaft (36 in) (416-7006) | LF | 354 | $275.00 | $265.00 | $235.00 | $260.00 | $257.00 | $320.00 | $288.00 |
| 13 | Drilled shaft (42 in) (416-7007) | LF | 305 | $350.00 | $375.00 | $345.00 | $360.00 | $346.00 | $420.00 | $392.00 |
| 14 | Class A concrete (miscellaneous) (420-7002) | CY | 1.90 | $1,400.00 | $3,500.00 | $1,200.00 | $1,500.00 | $925.00 | $3,500.00 | $2,500.00 |
| 15 | Class C concrete (abutment)(HPC) (420-7013) | CY | 215.30 | $1,350.00 | $1,125.00 | $900.00 | $900.00 | $761.00 | $925.00 | $1,800.00 |
| 16 | Reinforced concrete slab (HPC) (422-7002) | SF | 2,210 | $30.00 | $34.00 | $35.00 | $37.00 | $33.00 | $40.00 | $40.00 |
| 17 | Approach slab (HPC) (422-7014) | CY | 52.80 | $800.00 | $850.00 | $1,000.00 | $800.00 | $582.00 | $1,050.00 | $850.00 |
| 18 | Prestressed concrete girder (TX28) (425-7001) | LF | 258 | $285.00 | $400.00 | $380.00 | $360.00 | $300.00 | $383.00 | $470.00 |
| 19 | Riprap (mow strip)(4 in) (432-7013) | CY | 25 | $700.00 | $750.05 | $750.00 | $750.00 | $633.00 | $825.00 | $800.00 |
| 20 | Riprap (stone protection)(30 in) (432-7047) | CY | 1,468 | $210.00 | $185.00 | $230.00 | $185.00 | $145.00 | $150.00 | $165.00 |
| 21 | Rail (type T223)(HPC) (450-7009) | LF | 276 | $165.00 | $185.00 | $160.00 | $135.00 | $130.00 | $220.00 | $285.00 |
| 22 | Type A joint (454-7001) | LF | 68 | $65.00 | $100.00 | $90.00 | $20.00 | $87.00 | $35.00 | $50.00 |
| 23 | RC pipe (CL III)(36 in) (464-7009) | LF | 152 | $180.00 | $200.00 | $180.00 | $175.00 | $140.00 | $315.00 | $168.00 |
| 24 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 1 | $6,600.00 | $9,000.00 | $8,500.00 | $12,000 | $7,600.00 | $13,600 | $11,800 |
| 25 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 1 | $4,500.00 | $4,000.00 | $5,000.00 | $6,000.00 | $3,730.00 | $3,300.00 | $4,200.00 |
| 26 | Removing structure (pipe) (496-7007) | LF | 172 | $25.00 | $10.00 | $30.00 | $30.00 | $21.00 | $16.00 | $15.00 |
| 27 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $35,000 | $21,000 | $50,000 | $50,000 | $100,000 | $50,000 | $40,000 |
| 28 | Mobilization (500-7001) | LS | 1 | $150,000 | $150,000 | $145,000 | $156,000 | $160,000 | $178,000 | $158,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $4,500.00 | $2,500.00 | $7,500.00 | $8,400.00 | $21,250 | $2,500.00 | $1,600.00 |
| 30 | Rock filter dams (install) (type 1) (506-7001) | LF | 53 | $40.00 | $55.00 | $1.00 | $35.00 | $28.00 | $30.00 | $35.00 |
| 31 | Rock filter dams (install) (type 3) (506-7003) | LF | 33 | $80.00 | $75.00 | $1.00 | $90.00 | $80.00 | $85.00 | $97.00 |
| 32 | Rock filter dams (remove) (506-7011) | LF | 86 | $15.00 | $5.00 | $1.00 | $20.00 | $18.00 | $20.00 | $22.00 |
| 33 | Construction exits (install) (type 1) (506-7020) | SY | 160 | $35.00 | $15.00 | $1.00 | $35.00 | $35.00 | $37.00 | $42.00 |
| 34 | Construction exits (remove) (506-7024) | SY | 160 | $10.00 | $5.00 | $1.00 | $11.00 | $11.00 | $12.00 | $15.00 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 1,127 | $4.00 | $3.75 | $1.00 | $4.00 | $3.50 | $10.00 | $5.00 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 1,127 | $1.00 | $1.50 | $1.00 | $1.00 | $1.00 | $5.00 | $1.00 |
| 37 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 48 | $10.00 | $12.00 | $5.00 | $6.00 | $4.25 | $14.00 | $5.00 |
| 38 | Biodegradable erosion control logs (remove) (506-7046) | LF | 48 | $1.50 | $6.00 | $1.00 | $1.50 | $1.25 | $7.00 | $1.00 |
| 39 | Metal W-beam guard fence (steel post) (540-7002) | LF | 200 | $35.00 | $35.00 | $30.00 | $30.64 | $30.69 | $30.00 | $40.00 |
| 40 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $1,400.00 | $1,500.00 | $1,500.00 | $2,688.22 | $1,475.00 | $1,250.00 | $1,150.00 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,700.00 | $1,750.00 | $1,500.00 | $1,290.00 | $1,569.00 | $1,350.00 | $1,510.00 |
| 42 | Remove metal beam guard fence (542-7001) | LF | 219 | $4.00 | $5.00 | $1.00 | $10.75 | $3.75 | $10.00 | $6.00 |
| 43 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,300.00 | $3,400.00 | $500.00 | $3,171.25 | $3,190.00 | $3,150.00 | $4,400.00 |
| 44 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 5 | $930.00 | $1,400.00 | $2,000.00 | $860.00 | $655.00 | $700.00 | $965.00 |
| 45 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $1,200.00 | $1,500.00 | $2,000.00 | $967.50 | $715.00 | $700.00 | $1,087.00 |
| 46 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 2 | $600.00 | $500.00 | $250.00 | $860.00 | $605.00 | $700.00 | $966.00 |
| 47 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $30.00 | $50.00 | $20.00 | $21.50 | $15.00 | $30.00 | $50.00 |
| 48 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 5 | $35.00 | $50.00 | $20.00 | $26.88 | $25.00 | $35.00 | $50.00 |
| 49 | Pavement sler 6" (666-7347) | LF | 424 | $1.00 | $1.00 | $2.00 | $2.15 | $2.00 | $2.00 | $0.70 |
| 50 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 1,170 | $1.50 | $3.25 | $4.00 | $3.76 | $3.50 | $3.00 | $3.38 |
| 51 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 1,114 | $1.50 | $3.25 | $4.00 | $3.76 | $3.50 | $3.00 | $3.32 |
| 52 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 18 | $17.00 | $35.00 | $20.00 | $59.13 | $55.00 | $20.00 | $37.47 |
| 53 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 18 | $8.00 | $25.00 | $20.00 | $21.50 | $20.00 | $7.00 | $19.04 |
| 54 | Pavement surface preparation for marking (6") (678-7002) | LF | 424 | $1.00 | $0.50 | $1.00 | $3.23 | $3.00 | $1.00 | $0.21 |
| 55 | Full - width mowing (730-7019) | CYC | 2 | $4,000.00 | $2,500.00 | $500.00 | $1,200.00 | $100.00 | $800.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.