TxDOT contract A00045322 bid tabulation
Bridge Replacement, FM 604 (AT JIM NED CREEK to .). Let by Texas DOT on December 3, 2025, Taylor, Abilene District. 9 bids received; low bid $2,697,516 by J. H. Strain & Sons, Inc., -16% against the engineer's estimate of $3,220,743.
- Owner
- Texas DOT
- Letting
- 03 DEC 2025
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J. H. Strain & Sons, Inc. | $2,697,516 | Low | -16% |
| 2 | STX Civil | $3,269,199 | +21% | +2.0% |
| 3 | Hodges and Son Construction Company, Inc. | $3,629,241 | +35% | +13% |
| 4 | James Construction Group, LLC | $3,825,931 | +42% | +19% |
| 5 | Earth Builders, L.P. | $4,096,531 | +52% | +27% |
| 6 | THK Construction LLC | $4,215,697 | +56% | +31% |
| 7 | Gilvin-Terrill, LTD. | $4,466,115 | +66% | +39% |
| 8 | Coppell Construction Co., Inc. | $4,677,220 | +73% | +45% |
| 9 | C. E. Barker, LTD. | $4,985,765 | +85% | +55% |
Engineer's estimate: $3,220,743.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J. H. Strain & Sons, Inc. | 2. STX Civil | 3. Hodges and Son Construction Company, Inc. | 4. James Construction Group, LLC | 5. Earth Builders, L.P. | 6. THK Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 16 | $530.00 | $1,400.00 | $800.00 | $2,500.00 | $22,750 | $8,000.00 | $2,000.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 194 | $55.50 | $25.00 | $10.00 | $10.00 | $24.97 | $15.00 | $40.00 |
| 3 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 3,430 | $13.50 | $12.00 | $8.00 | $8.00 | $7.26 | $15.00 | $20.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 3,093 | $17.00 | $12.00 | $20.00 | $25.00 | $15.04 | $18.00 | $25.00 |
| 5 | Embankment (final)(DC)(type A) (132-7002) | CY | 7,928 | $32.50 | $18.00 | $25.00 | $20.00 | $31.91 | $32.00 | $25.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 14,843 | $1.90 | $2.50 | $3.00 | $4.00 | $0.35 | $4.00 | $4.00 |
| 7 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 14,843 | $1.00 | $0.62 | $1.50 | $0.70 | $1.92 | $1.00 | $0.67 |
| 8 | Vegetative watering (168-7001) | TGL | 148 | $80.00 | $35.00 | $25.00 | $1.00 | $43.35 | $50.00 | $10.00 |
| 9 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 14,843 | $2.95 | $2.10 | $3.00 | $2.50 | $0.52 | $3.00 | $2.20 |
| 10 | FL BS (compacted in place)(type D GR 4) (6") (247-7058) | SY | 923 | $20.00 | $15.85 | $40.00 | $40.00 | $17.08 | $23.00 | $60.00 |
| 11 | FL BS (compacted in place)(type D GR 4) (10") (247-7104) | SY | 5,554 | $27.20 | $26.55 | $40.00 | $40.00 | $22.58 | $27.00 | $60.00 |
| 12 | Prime coat (MC-30) (310-7004) | GAL | 1,295 | $9.00 | $10.00 | $5.00 | $12.00 | $7.50 | $14.00 | $14.30 |
| 13 | Aggregate (type-PB, GR-3)(sac-B) (316-7208) | CY | 52 | $475.00 | $175.00 | $800.00 | $690.00 | $660.00 | $900.00 | $880.00 |
| 14 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 7 | $180.00 | $225.00 | $800.00 | $1,500.00 | $900.00 | $2,200.00 | $2,200.00 |
| 15 | Asphalt (multi option) (316-7263) | GAL | 2,950 | $15.00 | $10.00 | $20.00 | $12.00 | $6.50 | $14.00 | $13.37 |
| 16 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 895 | $120.00 | $137.66 | $160.00 | $220.00 | $193.00 | $215.00 | $280.16 |
| 17 | SP mixes SP-D sac-B PG70-22 (344-7053) | TON | 439 | $120.00 | $139.66 | $240.00 | $300.00 | $200.00 | $295.00 | $319.00 |
| 18 | Tack coat (344-7077) | GAL | 1,647 | $6.50 | $5.00 | $5.00 | $2.00 | $5.00 | $3.00 | $1.65 |
| 19 | Cem stabil BKFL (400-7010) | CY | 333 | $160.00 | $250.00 | $180.00 | $300.00 | $262.97 | $400.00 | $350.00 |
| 20 | Temporary special shoring (403-7001) | SF | 3,665 | $20.00 | $28.00 | $5.00 | $25.00 | $58.56 | $30.00 | $60.00 |
| 21 | Drilled shaft (18 in) (416-7002) | LF | 102 | $148.00 | $175.00 | $165.00 | $120.00 | $148.47 | $150.00 | $256.34 |
| 22 | Drilled shaft (36 in) (416-7006) | LF | 450 | $322.00 | $320.00 | $295.00 | $315.00 | $316.76 | $400.00 | $345.89 |
| 23 | Class C concrete (abutment)(HPC) (420-7013) | CY | 57.50 | $1,700.00 | $1,400.00 | $1,200.00 | $1,900.00 | $1,798.01 | $2,200.00 | $1,500.00 |
| 24 | Class C concrete (cap)(HPC) (420-7023) | CY | 43.80 | $2,000.00 | $1,325.00 | $1,700.00 | $2,000.00 | $1,961.87 | $2,200.00 | $2,000.00 |
| 25 | Class C concrete (column)(HPC) (420-7039) | CY | 16.80 | $1,900.00 | $1,150.00 | $1,900.00 | $2,200.00 | $3,242.81 | $2,200.00 | $2,500.00 |
| 26 | Reinforced concrete slab (HPC) (422-7002) | SF | 6,762 | $32.00 | $32.00 | $27.50 | $40.00 | $47.46 | $45.00 | $40.00 |
| 27 | Approach slab (HPC) (422-7014) | CY | 99.90 | $1,060.00 | $900.00 | $850.00 | $950.00 | $915.34 | $1,000.00 | $900.00 |
| 28 | Prestressed concrete girder (TX28) (425-7001) | LF | 956.54 | $249.00 | $252.00 | $260.00 | $280.00 | $301.47 | $250.00 | $279.26 |
| 29 | Silicone resin paint finish (427-7004) | SF | 1,479 | $12.40 | $6.75 | $8.00 | $8.00 | $7.50 | $10.00 | $8.25 |
| 30 | Riprap (mow strip)(4 in) (432-7013) | CY | 25 | $735.00 | $885.00 | $650.00 | $800.00 | $899.88 | $700.00 | $800.00 |
| 31 | Riprap (stone type R)(dry)(18 in) (432-7024) | CY | 620 | $190.00 | $100.00 | $225.00 | $200.00 | $217.14 | $320.00 | $200.00 |
| 32 | Rail (type T223) (450-7008) | LF | 369 | $155.00 | $115.00 | $160.00 | $175.00 | $127.44 | $200.00 | $200.00 |
| 33 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 94 | $240.00 | $235.00 | $225.00 | $225.00 | $258.67 | $250.00 | $200.00 |
| 34 | RC pipe (CL III)(24 in) (464-7005) | LF | 140 | $117.00 | $95.00 | $110.00 | $90.00 | $131.60 | $130.00 | $100.00 |
| 35 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,100.00 | $2,000.00 | $1,800.00 | $2,200.00 | $2,517.04 | $1,500.00 | $3,000.00 |
| 36 | Removing structure (pipe) (496-7007) | LF | 162 | $35.50 | $13.00 | $20.00 | $15.00 | $20.77 | $25.00 | $20.00 |
| 37 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $75,000 | $99,500 | $45,000 | $80,000 | $61,378 | $70,000 | $260,000 |
| 38 | Removing structure (small) (496-7036) | EACH | 3,171 | $10.00 | $5.00 | $10.00 | $2.50 | $6.79 | $0.01 | $20.00 |
| 39 | Mobilization (500-7001) | LS | 1 | $322,800 | $100,000 | $240,000 | $315,000 | $324,019 | $400,000 | $320,000 |
| 40 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $9,300.00 | $5,000.00 | $1,400.00 | $6,000.00 | $9,963.14 | $2,700.00 | $2,235.27 |
| 41 | TMA (stationary) (505-7001) | DAY | 4 | $280.00 | $250.00 | $65.00 | $300.00 | $848.04 | $300.00 | $400.00 |
| 42 | TMA (mobile operation) (505-7003) | DAY | 9 | $505.00 | $400.00 | $65.00 | $300.00 | $1,295.42 | $650.00 | $400.00 |
| 43 | Rock filter dams (install) (type 1) (506-7001) | LF | 870 | $22.00 | $38.00 | $45.00 | $1.00 | $34.71 | $40.00 | $35.20 |
| 44 | Rock filter dams (remove) (506-7011) | LF | 870 | $16.00 | $11.00 | $10.00 | $1.00 | $12.39 | $5.00 | $2.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 3,045 | $4.50 | $5.00 | $4.00 | $1.00 | $3.49 | $3.00 | $3.30 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 3,045 | $1.25 | $1.50 | $1.00 | $1.00 | $0.99 | $1.00 | $1.10 |
| 47 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 50 | $1.00 | $8.00 | $8.00 | $5.00 | $5.74 | $8.00 | $6.60 |
| 48 | Biodegradable erosion control logs (remove) (506-7046) | LF | 50 | $1.00 | $3.00 | $1.00 | $2.00 | $1.62 | $3.00 | $3.30 |
| 49 | Constructing detours (508-7001) | SY | 1,620 | $96.00 | $66.00 | $180.00 | $140.00 | $105.05 | $150.00 | $125.00 |
| 50 | One-way traffic control (port traffic signal) (510-7003) | MO | 7 | $6,100.00 | $5,000.00 | $7,000.00 | $5,000.00 | $3,858.00 | $4,500.00 | $5,000.00 |
| 51 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 1,650 | $25.00 | $27.14 | $65.00 | $55.00 | $13.78 | $55.00 | $25.00 |
| 52 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 1,530 | $12.00 | $15.24 | $15.00 | $6.00 | $5.73 | $20.00 | $10.00 |
| 53 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 1,620 | $17.00 | $23.40 | $25.00 | $55.00 | $2.71 | $35.00 | $25.00 |
| 54 | Metal W-beam guard fence (timber post) (540-7001) | LF | 312.50 | $32.00 | $42.80 | $32.00 | $25.00 | $22.00 | $30.00 | $27.72 |
| 55 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,400.00 | $6,325.00 | $2,500.00 | $1,600.00 | $1,575.00 | $1,800.00 | $1,732.50 |
| 56 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,590.00 | $1,560.00 | $1,500.00 | $1,300.00 | $1,300.00 | $1,600.00 | $1,430.00 |
| 57 | Remove metal beam guard fence (542-7001) | LF | 336 | $4.50 | $2.24 | $1.00 | $3.00 | $2.50 | $6.00 | $2.75 |
| 58 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,500.00 | $3,750.00 | $3,350.00 | $3,000.00 | $3,000.00 | $3,600.00 | $3,300.00 |
| 59 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $2,200.00 | $2,875.00 | $1,800.00 | $2,200.00 | $2,200.00 | $3,000.00 | $2,420.00 |
| 60 | Crash cushion attenuator (remove) (545-7004) | EACH | 3 | $1,500.00 | $1,150.00 | $1,500.00 | $800.00 | $800.00 | $1,400.00 | $880.00 |
| 61 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 3 | $9,800.00 | $9,200.00 | $9,000.00 | $9,000.00 | $8,850.00 | $11,000 | $9,735.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $700.00 | $820.00 | $850.00 | $1,200.00 | $714.00 | $1,600.00 | $1,500.00 |
| 63 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 6 | $900.00 | $1,105.00 | $1,000.00 | $1,200.00 | $961.00 | $1,600.00 | $1,500.00 |
| 64 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,000.00 | $1,280.00 | $1,000.00 | $1,500.00 | $1,114.00 | $1,600.00 | $1,500.00 |
| 65 | Remove SM RD SN sup&AM (644-7073) | EACH | 8 | $125.00 | $125.00 | $100.00 | $50.00 | $124.00 | $250.00 | $250.00 |
| 66 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 9 | $49.00 | $44.80 | $30.00 | $45.00 | $45.00 | $65.00 | $49.50 |
| 67 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $44.00 | $44.80 | $40.00 | $45.00 | $45.00 | $65.00 | $49.50 |
| 68 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 2 | $81.00 | $68.00 | $80.00 | $500.00 | $59.00 | $65.00 | $66.00 |
| 69 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 9,256 | $1.30 | $1.50 | $2.00 | $1.50 | $1.30 | $2.50 | $3.25 |
| 70 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 20 | $17.00 | $17.25 | $30.00 | $25.00 | $15.00 | $22.00 | $27.78 |
| 71 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 268 | $1.00 | $2.90 | $1.75 | $5.00 | $2.50 | $3.00 | $1.65 |
| 72 | Pavement sler 6" (666-7347) | LF | 494 | $1.26 | $2.30 | $3.50 | $5.00 | $2.00 | $3.00 | $3.30 |
| 73 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 2,979 | $1.14 | $2.20 | $3.50 | $3.50 | $1.90 | $3.50 | $3.58 |
| 74 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 390 | $1.14 | $4.60 | $3.75 | $3.50 | $4.00 | $4.50 | $3.85 |
| 75 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 261 | $1.61 | $4.60 | $3.50 | $5.00 | $4.00 | $4.50 | $3.58 |
| 76 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 19 | $8.75 | $17.25 | $30.00 | $25.00 | $15.00 | $18.00 | $27.50 |
| 77 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,572 | $1.76 | $1.15 | $1.75 | $1.50 | $1.00 | $3.50 | $1.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.