TxDOT contract A00045322 bid tabulation

Bridge Replacement, FM 604 (AT JIM NED CREEK to .). Let by Texas DOT on December 3, 2025, Taylor, Abilene District. 9 bids received; low bid $2,697,516 by J. H. Strain & Sons, Inc., -16% against the engineer's estimate of $3,220,743.

Owner
Texas DOT
Letting
03 DEC 2025
Pay items
77
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1J. H. Strain & Sons, Inc.$2,697,516Low-16%
2STX Civil$3,269,199+21%+2.0%
3Hodges and Son Construction Company, Inc.$3,629,241+35%+13%
4James Construction Group, LLC$3,825,931+42%+19%
5Earth Builders, L.P.$4,096,531+52%+27%
6THK Construction LLC$4,215,697+56%+31%
7Gilvin-Terrill, LTD.$4,466,115+66%+39%
8Coppell Construction Co., Inc.$4,677,220+73%+45%
9C. E. Barker, LTD.$4,985,765+85%+55%
TxDOT contract A00045322: bids by rank

Engineer's estimate: $3,220,743.

Bid tabulation

LinePay itemUnitQuantityEstimate1. J. H. Strain & Sons, Inc.2. STX Civil3. Hodges and Son Construction Company, Inc.4. James Construction Group, LLC5. Earth Builders, L.P.6. THK Construction LLC
1Preparing row (100-7002)STA16$530.00$1,400.00$800.00$2,500.00$22,750$8,000.00$2,000.00
2Removing concrete (riprap) (104-7006)SY194$55.50$25.00$10.00$10.00$24.97$15.00$40.00
3Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008)SY3,430$13.50$12.00$8.00$8.00$7.26$15.00$20.00
4Excavation (roadway) (110-7001)CY3,093$17.00$12.00$20.00$25.00$15.04$18.00$25.00
5Embankment (final)(DC)(type A) (132-7002)CY7,928$32.50$18.00$25.00$20.00$31.91$32.00$25.00
6Furn & place topsoil (4") (160-7002)SY14,843$1.90$2.50$3.00$4.00$0.35$4.00$4.00
7Hydro mulch seed (permanent_rural_sandy) (164-7017)SY14,843$1.00$0.62$1.50$0.70$1.92$1.00$0.67
8Vegetative watering (168-7001)TGL148$80.00$35.00$25.00$1.00$43.35$50.00$10.00
9Soil ret BLKT(SL_mod_clay_short_roll) (169-7009)SY14,843$2.95$2.10$3.00$2.50$0.52$3.00$2.20
10FL BS (compacted in place)(type D GR 4) (6") (247-7058)SY923$20.00$15.85$40.00$40.00$17.08$23.00$60.00
11FL BS (compacted in place)(type D GR 4) (10") (247-7104)SY5,554$27.20$26.55$40.00$40.00$22.58$27.00$60.00
12Prime coat (MC-30) (310-7004)GAL1,295$9.00$10.00$5.00$12.00$7.50$14.00$14.30
13Aggregate (type-PB, GR-3)(sac-B) (316-7208)CY52$475.00$175.00$800.00$690.00$660.00$900.00$880.00
14Aggregate (type-PB, GR-4)(sac-B) (316-7211)CY7$180.00$225.00$800.00$1,500.00$900.00$2,200.00$2,200.00
15Asphalt (multi option) (316-7263)GAL2,950$15.00$10.00$20.00$12.00$6.50$14.00$13.37
16SP mixes SP-B sac-B PG64-22 (344-7002)TON895$120.00$137.66$160.00$220.00$193.00$215.00$280.16
17SP mixes SP-D sac-B PG70-22 (344-7053)TON439$120.00$139.66$240.00$300.00$200.00$295.00$319.00
18Tack coat (344-7077)GAL1,647$6.50$5.00$5.00$2.00$5.00$3.00$1.65
19Cem stabil BKFL (400-7010)CY333$160.00$250.00$180.00$300.00$262.97$400.00$350.00
20Temporary special shoring (403-7001)SF3,665$20.00$28.00$5.00$25.00$58.56$30.00$60.00
21Drilled shaft (18 in) (416-7002)LF102$148.00$175.00$165.00$120.00$148.47$150.00$256.34
22Drilled shaft (36 in) (416-7006)LF450$322.00$320.00$295.00$315.00$316.76$400.00$345.89
23Class C concrete (abutment)(HPC) (420-7013)CY57.50$1,700.00$1,400.00$1,200.00$1,900.00$1,798.01$2,200.00$1,500.00
24Class C concrete (cap)(HPC) (420-7023)CY43.80$2,000.00$1,325.00$1,700.00$2,000.00$1,961.87$2,200.00$2,000.00
25Class C concrete (column)(HPC) (420-7039)CY16.80$1,900.00$1,150.00$1,900.00$2,200.00$3,242.81$2,200.00$2,500.00
26Reinforced concrete slab (HPC) (422-7002)SF6,762$32.00$32.00$27.50$40.00$47.46$45.00$40.00
27Approach slab (HPC) (422-7014)CY99.90$1,060.00$900.00$850.00$950.00$915.34$1,000.00$900.00
28Prestressed concrete girder (TX28) (425-7001)LF956.54$249.00$252.00$260.00$280.00$301.47$250.00$279.26
29Silicone resin paint finish (427-7004)SF1,479$12.40$6.75$8.00$8.00$7.50$10.00$8.25
30Riprap (mow strip)(4 in) (432-7013)CY25$735.00$885.00$650.00$800.00$899.88$700.00$800.00
31Riprap (stone type R)(dry)(18 in) (432-7024)CY620$190.00$100.00$225.00$200.00$217.14$320.00$200.00
32Rail (type T223) (450-7008)LF369$155.00$115.00$160.00$175.00$127.44$200.00$200.00
33Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF94$240.00$235.00$225.00$225.00$258.67$250.00$200.00
34RC pipe (CL III)(24 in) (464-7005)LF140$117.00$95.00$110.00$90.00$131.60$130.00$100.00
35Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$2,100.00$2,000.00$1,800.00$2,200.00$2,517.04$1,500.00$3,000.00
36Removing structure (pipe) (496-7007)LF162$35.50$13.00$20.00$15.00$20.77$25.00$20.00
37Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$75,000$99,500$45,000$80,000$61,378$70,000$260,000
38Removing structure (small) (496-7036)EACH3,171$10.00$5.00$10.00$2.50$6.79$0.01$20.00
39Mobilization (500-7001)LS1$322,800$100,000$240,000$315,000$324,019$400,000$320,000
40Barricades, signs and traffic handling (502-7001)MO13$9,300.00$5,000.00$1,400.00$6,000.00$9,963.14$2,700.00$2,235.27
41TMA (stationary) (505-7001)DAY4$280.00$250.00$65.00$300.00$848.04$300.00$400.00
42TMA (mobile operation) (505-7003)DAY9$505.00$400.00$65.00$300.00$1,295.42$650.00$400.00
43Rock filter dams (install) (type 1) (506-7001)LF870$22.00$38.00$45.00$1.00$34.71$40.00$35.20
44Rock filter dams (remove) (506-7011)LF870$16.00$11.00$10.00$1.00$12.39$5.00$2.00
45Temporary sediment control fence (install) (506-7039)LF3,045$4.50$5.00$4.00$1.00$3.49$3.00$3.30
46Temporary sediment control fence (remove) (506-7041)LF3,045$1.25$1.50$1.00$1.00$0.99$1.00$1.10
47Biodegradable erosion control logs (install) (12") (506-7044)LF50$1.00$8.00$8.00$5.00$5.74$8.00$6.60
48Biodegradable erosion control logs (remove) (506-7046)LF50$1.00$3.00$1.00$2.00$1.62$3.00$3.30
49Constructing detours (508-7001)SY1,620$96.00$66.00$180.00$140.00$105.05$150.00$125.00
50One-way traffic control (port traffic signal) (510-7003)MO7$6,100.00$5,000.00$7,000.00$5,000.00$3,858.00$4,500.00$5,000.00
51Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF1,650$25.00$27.14$65.00$55.00$13.78$55.00$25.00
52Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF1,530$12.00$15.24$15.00$6.00$5.73$20.00$10.00
53Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF1,620$17.00$23.40$25.00$55.00$2.71$35.00$25.00
54Metal W-beam guard fence (timber post) (540-7001)LF312.50$32.00$42.80$32.00$25.00$22.00$30.00$27.72
55Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,400.00$6,325.00$2,500.00$1,600.00$1,575.00$1,800.00$1,732.50
56Downstream anchor terminal section (540-7015)EACH1$1,590.00$1,560.00$1,500.00$1,300.00$1,300.00$1,600.00$1,430.00
57Remove metal beam guard fence (542-7001)LF336$4.50$2.24$1.00$3.00$2.50$6.00$2.75
58Guardrail end treatment (install) (544-7001)EACH3$3,500.00$3,750.00$3,350.00$3,000.00$3,000.00$3,600.00$3,300.00
59Crash cushion attenuator (move & reset) (545-7002)EACH2$2,200.00$2,875.00$1,800.00$2,200.00$2,200.00$3,000.00$2,420.00
60Crash cushion attenuator (remove) (545-7004)EACH3$1,500.00$1,150.00$1,500.00$800.00$800.00$1,400.00$880.00
61Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH3$9,800.00$9,200.00$9,000.00$9,000.00$8,850.00$11,000$9,735.00
62Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH2$700.00$820.00$850.00$1,200.00$714.00$1,600.00$1,500.00
63Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH6$900.00$1,105.00$1,000.00$1,200.00$961.00$1,600.00$1,500.00
64Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,000.00$1,280.00$1,000.00$1,500.00$1,114.00$1,600.00$1,500.00
65Remove SM RD SN sup&AM (644-7073)EACH8$125.00$125.00$100.00$50.00$124.00$250.00$250.00
66Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH9$49.00$44.80$30.00$45.00$45.00$65.00$49.50
67Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH10$44.00$44.80$40.00$45.00$45.00$65.00$49.50
68Install object marker assembly (OM-2Y)(WC)GND (658-7056)EACH2$81.00$68.00$80.00$500.00$59.00$65.00$66.00
69Work zone pavement marking removing (W)6"(solid) (662-7068)LF9,256$1.30$1.50$2.00$1.50$1.30$2.50$3.25
70Work zone pavement marking removing (W)24"(solid) (662-7077)LF20$17.00$17.25$30.00$25.00$15.00$22.00$27.78
71Work zone pavement marking removing (Y)6"(solid) (662-7100)LF268$1.00$2.90$1.75$5.00$2.50$3.00$1.65
72Pavement sler 6" (666-7347)LF494$1.26$2.30$3.50$5.00$2.00$3.00$3.30
73Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF2,979$1.14$2.20$3.50$3.50$1.90$3.50$3.58
74Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF390$1.14$4.60$3.75$3.50$4.00$4.50$3.85
75Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF261$1.61$4.60$3.50$5.00$4.00$4.50$3.58
76Reflectorized pavement marker type II-A-A (672-7004)EACH19$8.75$17.25$30.00$25.00$15.00$18.00$27.50
77Eliminating existing PM & markers (6") (677-7002)LF4,572$1.76$1.15$1.75$1.50$1.00$3.50$1.65
TxDOT contract A00045322: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy