Install object marker assembly (OM-2Y)(WC)GND, TxDOT 658-7056

Low bidders on TxDOT contracts carried a median of $73.35 per EACH for this item, over the 24 months to 19 NOV 2026, across 68 low bids. Half of all 423 bids fell between $65.00 and $115.00.

Owner
Texas DOT
Item
658-7056
Unit
EACH
Data through
19 NOV 2026

TxDOT prints this item as “INSTL OM ASSM (OM-2Y)(WC)GND”.

TxDOT has bid this work under more than one code: 6586047 on lettings from 09 JAN 2020 to 09 JUL 2024 (1,052 bids); 658-7056 on lettings from 06 NOV 2024 to 04 NOV 2026 (449 bids). They are combined here into one trend.

$73.35Low bidder's median, per EACH
$82.06Median of all bids, per EACH
70Contracts in the window
$80.00Engineer's estimate, median per EACH

By year of letting

Install object marker assembly (OM-2Y)(WC)GND, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204443$60.00210$65.00
20215959$64.00321$65.00
20225757$75.00247$75.00
20234747$76.50161$81.06
20243434$82.12139$89.00
20253432$80.00170$80.00
20263535$65.00245$83.25

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Paris District12$65.0071$72.00
Houston District6$120.0049$100.00
Fort Worth District6$55.0046$70.75
Austin District4$63.6737$105.00
Yoakum District6$182.5037$100.00
Waco District6$71.5031$68.95
Abilene District4$71.1023$74.20
Pharr District5$60.0023$80.00
Odessa District5$80.0019$82.50
Install object marker assembly (OM-2Y)(WC)GND, TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
2 to 417$65.00
4 to 1017$92.70
11 to 4217$71.35
44 to 20417$80.00
Install object marker assembly (OM-2Y)(WC)GND, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Install object marker assembly (OM-2Y)(WC)GND, TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00209149Laredo District8$181.35$150.00$80.007STX CivilTxDOT
04 NOV 2026A00196925Paris District32$77.00$68.25$60.009Highway 19 Construction LLCTxDOT
04 NOV 2026A00129572Dallas District10$55.00$56.79$92.004Mario Sinacola & Sons Excavating, Inc.TxDOT
06 OCT 2026A00222925Waco District25$25.00$25.00$80.003Ross Sa Enterprise LLCTxDOT
06 OCT 2026A00207643Paris District76$35.00$70.00$60.257Highway 19 Construction LLCTxDOT
06 OCT 2026A00134683Houston District7$40.00$116.77$101.679Garret Shields InfrastructureTxDOT
02 SEP 2026A00121174Pharr District49$150.00$83.25$80.007Ioc Company LLCTxDOT
02 SEP 2026A00192185Houston District4$120.00$103.00$175.0011R Construction Civil, LLCTxDOT
02 SEP 2026A00195348Paris District4$65.00$120.00$45.007Highway 19 Construction LLCTxDOT
06 AUG 2026A00193144Austin District8$56.00$100.00$120.007Hunter Industries, LTD.TxDOT
06 AUG 2026A00199843Odessa District54$80.00$80.00$80.005Dan Williams CompanyTxDOT
06 AUG 2026A00219498Wichita Falls District25$50.00$80.00$96.003Garret Shields InfrastructureTxDOT
06 AUG 2026A00124182Yoakum District22$80.00$80.00$60.003CK Newberry, LLCTxDOT
05 AUG 2026A00196471Corpus Christi District34$70.00$82.50$65.009Clark Construction of Texas, Inc.TxDOT
05 AUG 2026A00068611Houston District8$92.70$94.00$120.007Ser Construction Partners, LLCTxDOT
Latest TxDOT contracts carrying Install object marker assembly (OM-2Y)(WC)GND

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy