TxDOT contract A00121174 bid tabulation

New Arterial, SL 195 (NEW LOCATION, FM 649 to FM 3167). Let by Texas DOT on September 2, 2026, Starr, Pharr District. 7 bids received; low bid $51,358,199 by Ioc Company LLC, -15% against the engineer's estimate of $60,647,815.

Owner
Texas DOT
Letting
02 SEP 2026
Pay items
174
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ioc Company LLC$51,358,199Low-15%
2Posillico Civil, Inc.$54,248,444+6.0%-11%
3Foremost Paving, Inc.$61,529,921+20%+1.0%
4J. Carroll Weaver, Inc.$62,241,160+21%+3.0%
5CK Newberry, LLC$65,409,797+27%+8.0%
6James Construction Group, LLC$66,420,210+29%+10%
7Anderson Columbia Co., Inc.$69,669,125+36%+15%
TxDOT contract A00121174: bids by rank

Engineer's estimate: $60,647,815.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ioc Company LLC2. Posillico Civil, Inc.3. Foremost Paving, Inc.4. J. Carroll Weaver, Inc.5. CK Newberry, LLC6. James Construction Group, LLC
1Preparing row (100-7002)STA299$10,000$5,900.00$14,000$3,500.00$3,863.68$7,500.00$18,750
2Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006)SY3,025$14.00$1.00$10.00$0.80$7.63$10.00$9.84
3Excavation (roadway) (110-7001)CY394,283$6.75$1.00$6.50$4.65$6.24$7.50$5.00
4Embankment (final)(DC)(type C) (132-7006)CY636,815$6.50$10.00$3.65$10.74$10.86$7.50$9.20
5Backfill (type A) (134-7001)STA609$250.00$175.00$200.00$107.71$292.19$120.00$290.60
6Furn & place topsoil (vehicle) (160-7007)CY50$30.00$25.00$350.00$32.56$70.16$150.00$72.00
7Drill seed (permanent_rural_clay) (164-7042)ACRE109.14$615.00$513.81$512.00$1,959.75$568.32$525.00$511.26
8Drill seed (temporary_warm) (164-7045)ACRE109.14$550.00$493.35$491.00$1,457.25$543.90$490.00$490.90
9Drill seed (temporary_cool) (164-7046)ACRE109.14$750.00$493.35$491.00$1,457.25$543.90$490.00$490.90
10Vegetative watering (168-7001)TGL9,180$15.00$25.00$15.00$35.16$27.99$20.00$20.42
11Soil ret BLKT(SL_mod_clay_long_spry) (169-7018)SY25,341$1.50$0.92$0.92$1.36$1.11$1.00$0.92
12Sprinkling (dust control) (204-7001)TGL10,914$10.00$1.00$20.00$1.00$27.99$1.00$15.41
13FL BS (roadway del)(type E GR 4)(final pos) (247-7277)CY100,327.80$32.00$20.00$20.00$24.18$34.59$30.00$34.95
14Lime (com or QK)(slurry) (260-7005)TON9,358.30$250.00$215.00$290.00$275.38$314.68$300.00$316.52
15Lime TRT (existing material)(12") (260-7009)SY315,094.80$3.00$1.00$3.00$3.42$2.98$4.25$4.45
16Cement (275-7001)TON3,386.10$200.00$173.00$200.00$200.25$219.00$200.00$194.99
17Cement TRT (new base)(12") (275-7013)SY300,983.40$2.00$1.00$1.50$3.11$1.40$1.95$2.85
18Prime coat (MC-30) (310-7004)GAL57,648.90$6.00$5.00$5.00$6.88$4.72$5.00$7.20
19SP mixes SP-D sac-B PG76-22 (344-7065)TON49,289.70$115.00$100.00$110.00$114.08$154.29$110.00$117.20
20Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON24,739.80$140.00$134.00$130.00$133.06$180.93$135.00$149.20
21Plane & text asphalt concrete pavement(1.5") (354-7018)SY1,112$4.00$10.00$15.00$28.00$15.51$7.00$17.87
22Struct excavation (special) (400-7005)CY3,819$95.00$25.00$1.00$40.20$9.12$50.00$8.68
23Cem stabil BKFL (400-7010)CY3,262.20$75.00$50.00$75.00$93.55$62.37$150.00$176.25
24Trench excavation protection (402-7001)LF750$8.00$0.10$25.00$1.01$38.28$35.00$2.16
25Drilled shaft (18 in) (416-7002)LF688$72.00$110.00$100.00$206.03$179.57$180.00$137.16
26Drilled shaft (36 in) (416-7006)LF6,335$185.00$215.00$200.00$301.50$260.28$295.00$236.88
27Drilled shaft (60 in) (416-7010)LF420$900.00$725.00$500.00$804.00$464.14$960.00$627.98
28Drilled shaft (traffic signal pole) (24 in) (416-7042)LF54$127.00$242.33$242.00$226.13$233.10$215.00$225.00
29Drilled shaft (traffic signal pole) (36 in) (416-7044)LF16$325.00$403.88$403.00$376.88$366.30$350.00$375.00
30Drilled shaft (traffic signal pole) (42 in) (416-7045)LF36$470.00$457.73$457.00$427.13$432.90$400.00$425.00
31Drilled shaft (traffic signal pole) (48 in) (416-7046)LF22$540.00$511.58$511.00$477.38$510.60$500.00$475.00
32Class C concrete (abutment) (420-7012)CY534.10$1,350.00$1,000.00$840.00$1,859.25$852.05$1,500.00$998.77
33Class C concrete (cap) (420-7022)CY615.80$1,350.00$1,000.00$1,400.00$1,366.80$1,351.04$1,200.00$1,540.03
34Class C concrete (column) (420-7038)CY380.40$2,500.00$1,650.00$1,400.00$2,170.80$1,166.28$1,200.00$1,861.94
35Class C concrete (rail foundation) (420-7052)CY663$450.00$450.00$535.00$688.43$509.99$800.00$709.72
36Reinforced concrete slab (422-7001)SF189,710$19.50$18.00$18.00$28.14$21.55$27.50$22.96
37Prestressed concrete girder (TX54) (425-7005)LF23,093.09$210.00$195.00$210.00$230.00$237.05$245.00$219.79
38Riprap (concrete)(4 in) (432-7001)CY4,669$410.00$436.00$350.00$427.13$471.75$450.00$309.21
39Riprap (concrete)(5 in) (432-7002)CY628$500.00$436.00$375.00$427.13$471.75$450.00$424.89
40Riprap (mow strip)(4 in) (432-7013)CY810$420.00$480.00$350.00$437.18$482.85$450.00$664.90
41Riprap (stone protection)(18 in) (432-7043)CY465$180.00$140.00$190.00$190.95$145.76$225.00$271.47
42Riprap (concrete)(CL B)(RR8&RR9) (432-7055)CY220$546.00$488.00$350.00$429.14$473.97$450.00$432.99
43Rail (type SSTR) (450-7024)LF13,645.20$65.00$45.00$55.00$54.93$64.66$80.00$57.67
44Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF1,041$180.00$167.00$250.00$281.40$201.89$225.00$179.87
45Concrete box culvert (6 FT X 2 FT) (462-7010)LF276$615.00$415.00$390.00$390.00$547.95$550.00$327.83
46Concrete box culvert (6 FT X 3 FT) (462-7011)LF1,928$605.00$430.00$400.00$435.00$592.05$600.00$365.68
47Concrete box culvert (8 FT X 4 FT) (462-7021)LF1,004$879.00$620.00$550.00$705.00$854.96$900.00$538.09
48Concrete box culvert (10 FT X 4 FT) (462-7032)LF516$1,300.00$894.00$750.00$957.00$777.36$950.00$749.58
49RC pipe (CL IV)(18 in) (464-7019)LF1,968$212.00$95.00$65.00$69.30$67.85$80.00$76.23
50RC pipe (CL IV)(24 in) (464-7021)LF639$120.00$105.00$60.00$153.77$99.57$105.00$79.86
51RC pipe (CL IV)(30 in) (464-7023)LF145$150.00$130.00$100.00$257.28$119.77$155.00$128.31
52RC pipe (CL IV)(36 in) (464-7024)LF146$250.00$165.00$150.00$161.81$157.97$195.00$166.15
53RC pipe (CL IV)(48 in) (464-7026)LF2,377$270.00$265.00$250.00$266.33$233.22$270.00$237.36
54Junction box(complete)(PJB)(4FTX4FT) (465-7006)EACH2$7,500.00$4,750.00$3,650.00$6,130.50$11,661$10,000$7,843.91
55Inlet (complete)(pco)(3FT)(none) (465-7013)EACH1$6,000.00$4,500.00$3,200.00$5,226.00$9,328.80$15,000$9,906.04
56Inlet (complete)(pco)(3FT)(left) (465-7014)EACH2$6,000.00$5,500.00$4,500.00$6,231.00$4,664.40$10,000$8,569.09
57Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128)EACH5$6,000.00$5,000.00$4,000.00$8,844.00$4,664.39$13,000$8,655.29
58Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH3$25,000$29,500$25,000$107,535$29,733$125,000$30,081
59Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH3$35,000$35,000$25,000$129,645$38,429$115,000$35,031
60Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH1$40,000$40,000$30,000$130,650$47,468$130,000$40,313
61Wingwall (PW - 1) (HW=9 FT) (466-7179)EACH2$50,000$44,000$30,000$145,725$56,301$120,000$48,283
62Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH1$60,000$55,000$30,000$241,200$59,244$150,000$46,236
63Set (type I)(S= 6 FT)(HW= 4 FT)(4:1)(C) (467-7129)EACH13$10,000$18,500$20,000$21,105$8,694.51$7,500.00$27,426
64Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130)EACH7$5,000.00$21,000$20,000$36,180$13,086$15,000$29,709
65Set (type I)(S= 8 FT)(HW= 5 FT)(6:1)(C) (467-7185)EACH2$30,000$31,600$30,000$66,330$26,082$35,000$28,617
66Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306)EACH1$1,400.00$1,500.00$1,250.00$1,306.50$1,768.07$6,000.00$1,459.46
67Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH55$1,400.00$1,000.00$1,300.00$1,507.50$1,769.42$1,575.00$1,696.94
68Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH18$2,000.00$1,300.00$1,700.00$2,110.50$1,905.14$1,800.00$2,041.14
69Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366)EACH4$3,900.00$8,000.00$4,750.00$7,135.50$4,334.22$7,500.00$5,630.83
70Set (type II) (48 in) (RCP) (4: 1) (C) (467-7390)EACH28$10,000$11,500$7,000.00$8,542.50$7,393.73$8,000.00$7,476.25
71Set (type II) (48 in) (RCP) (6: 1) (C) (467-7391)EACH28$10,000$14,000$8,000.00$9,849.00$8,827.94$8,500.00$8,999.98
72Mobilization (500-7001)LS1$5,500,000$5,000,000$4,873,588$3,732,000$2,720,871$6,375,000$5,760,037
73Barricades, signs and traffic handling (502-7001)MO34$5,330.00$1,000.00$10,000$2,500.00$4,995.00$5,000.00$5,108.96
74Portable changeable message sign (503-7002)EACH2$10,000$100.00$10,000$2,500.00$11,100$30,000$17,285
75TMA (stationary) (505-7001)DAY699$60.00$0.10$1.00$20.00$101.08$150.00$195.00
76TMA (mobile operation) (505-7003)DAY1,002$70.00$1.00$1.00$0.01$61.05$25.00$318.00
77Rock filter dams (install) (type 2) (506-7002)LF3,804$55.50$38.00$50.00$34.68$42.18$65.00$60.47
78Rock filter dams (remove) (506-7011)LF3,804$16.00$22.00$17.00$18.09$11.10$20.00$19.71
79Construction exits (install) (type 1) (506-7020)SY780$25.00$15.00$150.00$25.52$11.10$35.00$64.26
80Construction exits (remove) (506-7024)SY780$25.00$1.00$10.00$14.79$8.88$10.00$14.23
81Construction perimeter fence (506-7034)LF37,740$6.00$3.00$5.00$2.27$5.55$4.50$2.70
82Biodegradable erosion control logs (install) (12") (506-7044)LF1,628$7.00$3.00$10.00$5.58$6.55$10.00$8.53
83Biodegradable erosion control logs (remove) (506-7046)LF1,628$1.25$0.10$1.50$1.36$1.72$1.50$1.29
84Constructing detours (508-7001)SY3,007$60.00$35.00$63.00$43.82$50.93$65.00$108.72
85Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF1,050$45.00$20.00$51.00$41.19$100.37$120.00$94.78
86Permanent CTB (single slope) (type 1) (42 ) (514-7001)LF3,950$95.00$65.00$90.00$96.17$78.20$115.00$81.91
87Colored textured concrete (4") (527-7001)SY2,142$115.00$55.00$125.00$55.63$61.44$60.00$82.62
88Concrete curb & gutter (type I) (529-7008)LF819$20.00$20.00$25.00$15.83$17.48$16.00$30.62
89Concrete curb & gutter (type II) (529-7009)LF1,455$30.00$20.00$14.50$15.83$17.48$16.00$32.97
90Concrete curb (ribbon) (529-7028)LF509$30.00$20.00$25.00$30.15$33.30$30.00$33.38
91Driveways (ACP) (530-7010)SY4,474$50.00$45.00$20.00$49.17$38.85$40.00$70.18
92Concrete sidewalks (4") (531-7001)SY25$60.00$175.00$250.00$72.87$80.48$80.00$71.30
93Curb ramps (type 7) (531-7010)EACH8$2,500.00$1,900.00$2,500.00$2,663.25$2,941.50$3,000.00$2,960.29
94Mill rumble strips (asphalt) (shoulder) (533-7001)LF106,375$0.20$0.18$0.18$0.25$0.21$0.25$0.06
95Metal W-beam guard fence (timber post) (540-7001)LF11,962$30.00$25.85$26.00$25.68$28.69$30.00$25.85
96Metal beam guard fence trans (thrie-beam) (540-7005)EACH24$2,100.00$2,390.00$2,390.00$2,296.43$2,652.90$2,500.00$2,390.00
97Downstream anchor terminal section (540-7015)EACH21$1,600.00$1,799.00$1,800.00$1,842.17$1,998.00$2,000.00$1,799.00
98Guardrail end treatment (install) (544-7001)EACH21$3,500.00$3,560.00$3,560.00$3,539.61$3,951.60$3,750.00$3,560.00
99Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH4$23,000$26,000$28,885$26,989$32,062$25,000$28,885
100Chain link fence (install) (8') (550-7005)LF7,800$70.00$55.00$55.00$48.50$61.05$20.00$53.00
101Gate (install)(6'X10') (550-7014)EACH7$2,500.00$3,000.00$3,000.00$1,510.00$3,330.00$1,500.00$2,500.00
102Mailbox install-S (TWG-post) type 2 (560-7002)EACH2$350.00$400.00$225.00$402.00$233.10$225.00$210.00
103Conduit (PVC) (schedule 40) (1") (618-7021)LF125$15.00$10.77$10.77$10.05$13.32$12.50$10.00
104Conduit (PVC) (schedule 40) (2") (618-7030)LF1,205$10.00$16.16$16.15$15.08$17.76$16.50$15.00
105Conduit (PVC) (schedule 40) (4") (618-7040)LF2,130$20.00$21.54$21.54$20.10$19.98$20.00$20.00
106Electrical conductor (no.6) bare (620-7009)LF3,460$2.50$1.94$1.94$1.81$2.33$2.25$1.80
107Electrical conductor (no.6) insulated (620-7010)LF470$2.50$2.69$2.69$2.52$2.72$2.50$2.50
108Tray cable (4 conductor) (12 AWG) (621-7006)LF1,415$2.75$3.07$3.07$2.87$3.27$3.25$2.85
109Ground box type D (162922)W/apron (624-7008)EACH9$1,500.00$1,211.65$1,211.39$1,130.63$1,776.00$1,800.00$1,125.00
110Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322)EACH1$2,550.00$4,092.67$4,091.79$3,819.00$3,774.00$3,500.00$3,800.00
111Aluminum signs (type A) (636-7001)SF22$35.00$50.00$53.84$50.25$94.35$95.00$26.50
112Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH13$750.00$725.00$1,050.00$728.63$777.00$700.00$695.00
113Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH70$920.00$825.00$875.00$829.13$777.00$750.00$700.00
114Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH37$1,100.00$925.00$975.00$929.63$910.20$900.00$820.00
115Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH3$1,050.00$1,075.00$1,600.00$1,080.38$999.00$1,000.00$900.00
116Install small roadside sign support and assembly TYS80(2)SA(P) (644-7048)EACH2$1,400.00$1,500.00$1,800.00$1,507.50$1,332.00$1,300.00$1,200.00
117In bridge MNT clearance sign assembly(type N) (644-7061)EACH4$2,800.00$2,250.00$2,250.00$3,602.93$2,497.50$2,500.00$1,814.70
118Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014)EACH117$30.00$15.00$25.00$15.08$13.32$15.00$12.00
119Install delineator assembly (D-SY)SZ 1(yflx)GND(BR) (658-7024)EACH27$65.00$115.00$85.00$115.58$57.72$55.00$52.00
120Install delineator assembly (D-SY)SZ 1(BRF)CTB (BR) (658-7033)EACH49$25.00$15.00$25.00$15.08$13.32$15.00$12.00
121Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045)EACH17$55.00$75.00$90.00$75.38$55.50$55.00$50.00
122Install object marker assembly (OM-2Y)(WC)GND (658-7056)EACH49$80.00$150.00$85.00$150.75$83.25$80.00$75.00
123Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF2,700$0.60$0.88$0.88$0.89$0.98$1.00$0.88
124Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF2,700$0.55$0.88$0.88$0.89$0.98$1.00$0.88
125Work zone pavement marking removing (W)6"(solid) (662-7068)LF5,274$0.70$0.42$0.42$0.43$0.47$0.45$0.42
126Work zone pavement marking removing (Y)6"(solid) (662-7100)LF5,274$0.70$0.42$0.42$0.43$0.47$0.45$0.42
127Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH198$1.75$2.56$1.00$1.35$1.11$0.90$2.70
128Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF12,610$1.35$0.82$0.82$0.83$0.91$0.90$0.82
129Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF1,155$4.20$1.20$1.20$1.21$1.33$1.25$1.20
130Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF448$7.50$5.50$5.50$5.53$6.11$5.50$5.50
131RE PV marking type I(black)6"(shadow)(100MIL) (666-7138)LF1,010$1.50$1.10$1.10$1.11$1.22$1.10$1.10
132Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF4,118$1.00$2.50$2.50$2.52$2.78$2.50$2.50
133Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF1,010$1.00$5.00$5.00$5.03$1.22$5.00$5.00
134Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF4,118$1.00$2.50$2.50$2.52$2.78$2.50$2.50
135Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF15,120$1.00$0.76$0.76$0.77$0.84$0.75$0.76
136Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF56,260$0.80$0.58$0.58$0.59$0.64$0.60$0.58
137Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF90$1.00$10.00$10.00$10.05$11.10$10.00$10.00
138Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF59,077$0.90$0.58$0.58$0.59$0.64$0.65$0.58
139Prefabricated PM type C (W)(arrow) (668-7091)EACH32$220.00$125.00$125.00$125.63$138.75$130.00$125.00
140Prefabricated PM type C (W)(double arrow) (668-7093)EACH4$355.00$250.00$250.00$251.25$277.50$250.00$250.00
141Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH5$350.00$275.00$275.00$276.38$305.25$275.00$275.00
142Prefabricated PM type C (W)(word) (668-7103)EACH29$295.00$225.00$225.00$226.13$249.75$275.00$225.00
143Reflectorized pavement marker type I-C (672-7002)EACH26$4.50$25.00$25.00$25.13$27.75$25.00$25.00
144Reflectorized pavement marker type II-A-A (672-7004)EACH39$4.00$25.00$25.00$25.13$27.75$25.00$25.00
145Reflectorized pavement marker type II-C-R (672-7006)EACH1,381$4.50$5.00$5.00$5.03$5.55$5.00$5.00
146Eliminating existing PM & markers (4") (677-7001)LF7,056$0.85$0.35$0.35$0.36$0.39$0.50$0.35
147Install highway traffic signal (isolated) (680-7002)EACH1$26,000$27,572$27,566$25,728$9,546.00$9,000.00$25,600
148Vehicle signal section (12")LED(green) (682-7001)EACH14$310.00$253.10$253.05$236.18$377.40$350.00$235.00
149Vehicle signal section (12")LED(green arrow) (682-7002)EACH2$310.00$253.10$253.05$236.18$377.40$350.00$235.00
150Vehicle signal section (12")LED(yel) (682-7003)EACH14$310.00$253.10$253.05$236.18$377.40$350.00$235.00
151Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$310.00$253.10$253.05$236.18$377.40$350.00$235.00
152Vehicle signal section (12")LED(red) (682-7005)EACH14$310.00$253.10$253.05$236.18$377.40$350.00$235.00
153Vehicle signal section (12")LED(red arrow) (682-7006)EACH2$310.00$253.10$253.05$236.18$377.40$350.00$235.00
154Pedestrian signal section (LED)(countdown) (682-7018)EACH12$750.00$484.66$484.55$452.25$832.50$800.00$450.00
155Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH14$225.00$123.86$123.83$115.58$155.40$150.00$115.00
156Backplate W/ref border(4 sec)(vent)aluminum (682-7043)EACH2$250.00$188.48$188.44$175.88$188.70$175.00$175.00
157Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF3,135$1.65$2.10$2.10$1.96$1.94$2.00$1.95
158Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF4,324$2.60$2.69$2.69$2.52$3.50$3.25$2.50
159Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF798$3.20$4.31$4.31$4.02$5.05$5.00$4.00
160Ins traffic signal PL AM(S)1 arm(40')lum (686-7043)EACH1$15,200$17,232$17,229$16,080$20,313$20,000$16,000
161Ins traffic signal PL AM(S)1 arm(50')lum (686-7055)EACH1$36,000$40,927$40,918$38,190$44,733$42,500$38,000
162Ins traffic signal PL AM(S)2 arm(40-36')lum (686-7147)EACH2$21,000$22,348$22,343$20,854$25,863$25,000$20,750
163Pedestrian pole assembly (687-7001)EACH5$2,850.00$1,292.42$1,292.14$1,206.00$1,332.00$1,300.00$1,200.00
164Pedestrian push button pole (687-7002)EACH4$2,500.00$694.68$694.53$648.23$1,054.50$1,000.00$645.00
165Pedestrian detect push button (APS) (688-7001)EACH12$1,000.00$823.92$823.74$768.83$1,221.00$1,200.00$765.00
166Install of FND for ground MNT cabinets (690-7036)EACH1$6,500.00$1,938.63$1,938.22$1,809.00$3,996.00$4,000.00$1,800.00
167Install of control cabinet(GRND MNT) (690-7040)EACH1$14,600$807.76$807.59$753.75$24,420$22,500$750.00
168Bonding course (3007-7001)GAL40,353$3.50$1.00$5.00$2.78$5.55$4.00$4.00
169Tip testing(drilled shaft) (4003-7001)EACH22$6,000.00$2,137.00$2,250.00$10,050$5,488.95$10,000$8,500.00
170Amphibian/reptile exclusion fence inst (5003-7001)LF55,180$4.00$2.75$4.00$3.22$3.83$4.50$4.09
171Amphibian/reptile exclusion fence rem (5003-7002)LF55,180$1.00$1.00$1.00$1.01$1.28$1.50$1.29
172Bird exclusion method (5029-7001)SF11,200$3.35$2.00$5.00$12.06$13.32$10.00$12.00
173RVDS (presence and advance detection) (6008-7003)EACH6$9,000.00$8,400.75$8,398.94$7,839.00$9,324.00$9,000.00$7,800.00
174Radar presence detector comm cable (6008-7009)LF1,970$2.00$2.69$2.69$2.52$2.16$2.00$2.50
TxDOT contract A00121174: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy