TxDOT contract A00196471 bid tabulation
Roadway Rehabilitation/Reconstruction With No Added Capacity, FM 81 (US 181 to FM 1144). Let by Texas DOT on August 5, 2026, Karnes, Corpus Christi District. 9 bids received; low bid $8,343,314 by Clark Construction of Texas, Inc., -11% against the engineer's estimate of $9,367,704.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 68
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Clark Construction of Texas, Inc. | $8,343,314 | Low | -11% |
| 2 | Hunter Industries, LTD. | $8,444,530 | +1.0% | -10% |
| 3 | Texas Materials Group, Inc. | $8,995,570 | +8.0% | -4.0% |
| 4 | CK Newberry, LLC | $9,086,201 | +9.0% | -3.0% |
| 5 | Salinas Construction Technologies, LTD. | $9,964,467 | +19% | +6.0% |
| 6 | STX Civil | $10,440,128 | +25% | +11% |
| 7 | J. Carroll Weaver, Inc. | $10,746,061 | +29% | +15% |
| 8 | Anderson Columbia Co., Inc. | $11,669,937 | +40% | +25% |
| 9 | J E Construction Services, LLC | $12,677,664 | +52% | +35% |
Engineer's estimate: $9,367,704.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Clark Construction of Texas, Inc. | 2. Hunter Industries, LTD. | 3. Texas Materials Group, Inc. | 4. CK Newberry, LLC | 5. Salinas Construction Technologies, LTD. | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 285 | $500.00 | $188.00 | $443.70 | $625.00 | $100.00 | $169.97 | $235.28 |
| 2 | Excavation (roadway) (110-7001) | CY | 34,767 | $12.00 | $14.73 | $9.85 | $5.80 | $10.00 | $10.04 | $16.18 |
| 3 | Embankment (final)(OC)(type C) (132-7005) | CY | 4,327 | $10.00 | $12.82 | $9.85 | $13.20 | $15.00 | $13.92 | $30.80 |
| 4 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 4.20 | $1,500.00 | $2,250.00 | $919.60 | $1,980.00 | $1,000.00 | $1,294.45 | $1,081.83 |
| 5 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 1.04 | $1,500.00 | $3,700.00 | $919.60 | $1,650.00 | $1,000.00 | $1,367.33 | $1,081.83 |
| 6 | Vegetative watering (168-7001) | TGL | 326 | $15.00 | $32.75 | $22.75 | $44.00 | $30.00 | $49.29 | $41.17 |
| 7 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 18,443 | $70.00 | $76.38 | $63.73 | $89.00 | $80.00 | $90.02 | $88.85 |
| 8 | Cement (275-7001) | TON | 1,446 | $220.00 | $190.00 | $183.75 | $182.00 | $200.00 | $237.54 | $190.00 |
| 9 | Cement TRT (existing material)(10") (275-7004) | SY | 113,788 | $2.50 | $1.75 | $3.30 | $2.05 | $1.80 | $1.78 | $4.47 |
| 10 | Prime coat (RC-250) (310-7006) | GAL | 21,501 | $4.00 | $6.00 | $4.97 | $5.00 | $5.00 | $7.19 | $4.64 |
| 11 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 901 | $115.00 | $143.38 | $115.18 | $145.00 | $135.00 | $227.27 | $142.90 |
| 12 | Aggregate (type-PB, GR-5)(sac-B) (316-7214) | CY | 806 | $125.00 | $125.77 | $115.18 | $161.00 | $140.00 | $203.51 | $172.76 |
| 13 | Asphalt (multi option) (316-7263) | GAL | 35,417 | $3.25 | $4.91 | $4.02 | $3.93 | $4.00 | $5.64 | $3.89 |
| 14 | D-GR HMA type-B sac-B PG70-22 (341-7007) | TON | 22,591 | $95.00 | $87.93 | $89.55 | $84.00 | $97.00 | $108.01 | $107.72 |
| 15 | Tack coat (341-7082) | GAL | 8,108 | $3.50 | $3.50 | $3.06 | $3.40 | $4.00 | $5.98 | $4.06 |
| 16 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 12,233 | $110.00 | $97.10 | $93.25 | $94.00 | $110.00 | $114.21 | $130.07 |
| 17 | Cut & restoring pavement (400-7006) | SY | 180 | $150.00 | $44.00 | $120.00 | $75.00 | $170.00 | $154.20 | $220.05 |
| 18 | Cem stabil BKFL (400-7010) | CY | 205 | $150.00 | $140.00 | $134.78 | $195.00 | $75.00 | $160.23 | $144.17 |
| 19 | Flowable backfill (401-7001) | CY | 20 | $300.00 | $185.00 | $207.36 | $195.00 | $415.00 | $374.14 | $216.20 |
| 20 | Riprap (concrete)(6 in) (432-7003) | CY | 24.50 | $600.00 | $547.00 | $482.42 | $464.00 | $1,000.00 | $948.61 | $546.89 |
| 21 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 44 | $350.00 | $630.00 | $523.57 | $423.00 | $415.00 | $321.32 | $332.67 |
| 22 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 84 | $400.00 | $640.00 | $559.86 | $446.00 | $465.00 | $366.87 | $363.27 |
| 23 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 240 | $750.00 | $639.00 | $539.13 | $520.00 | $600.00 | $1,150.90 | $669.38 |
| 24 | RC pipe (CL III)(18 in) (464-7003) | LF | 3,892 | $85.00 | $74.00 | $79.83 | $77.25 | $70.00 | $60.79 | $87.27 |
| 25 | RC pipe (CL III)(30 in) (464-7007) | LF | 44 | $250.00 | $170.00 | $129.60 | $215.00 | $130.00 | $134.77 | $139.57 |
| 26 | RC pipe (CL III)(36 in) (464-7009) | LF | 308 | $150.00 | $210.00 | $165.89 | $229.00 | $185.00 | $184.34 | $189.46 |
| 27 | Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040) | EACH | 1 | $5,800.00 | $7,905.00 | $6,428.05 | $6,210.00 | $5,000.00 | $9,129.48 | $7,293.76 |
| 28 | Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041) | EACH | 1 | $6,000.00 | $8,000.00 | $6,842.76 | $6,610.00 | $5,500.00 | $9,129.48 | $7,776.09 |
| 29 | Set (type I)(S= 3 FT)(HW= 4 FT)(3:1)(C) (467-7044) | EACH | 4 | $6,200.00 | $8,100.00 | $6,635.40 | $6,390.00 | $4,000.00 | $9,629.48 | $7,529.04 |
| 30 | Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128) | EACH | 4 | $6,500.00 | $8,800.00 | $8,605.29 | $8,260.00 | $6,000.00 | $15,223 | $9,764.22 |
| 31 | Set (type I)(S= 6 FT)(HW= 4 FT)(4:1)(C) (467-7129) | EACH | 26 | $8,000.00 | $6,339.00 | $6,676.88 | $6,435.00 | $7,000.00 | $15,223 | $7,646.68 |
| 32 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 174 | $3,000.00 | $1,345.00 | $1,555.17 | $1,400.00 | $1,500.00 | $1,071.04 | $1,835.20 |
| 33 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 2 | $4,800.00 | $3,400.00 | $2,280.92 | $3,360.00 | $3,500.00 | $3,584.38 | $2,705.75 |
| 34 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 11 | $5,000.00 | $4,360.00 | $3,525.06 | $4,780.00 | $5,500.00 | $4,188.81 | $4,296.26 |
| 35 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 3 | $5,500.00 | $4,375.00 | $3,576.90 | $5,410.00 | $4,500.00 | $3,745.32 | $4,417.43 |
| 36 | Clean existing culverts (480-7001) | EACH | 4 | $750.00 | $1,600.00 | $2,280.92 | $3,530.00 | $1,800.00 | $2,222.15 | $2,505.19 |
| 37 | Removing structure (pipe) (496-7037) | EACH | 9 | $2,500.00 | $600.00 | $1,347.82 | $900.00 | $850.00 | $2,357.57 | $15.24 |
| 38 | Mobilization (500-7001) | LS | 1 | $700,000 | $328,600 | $581,454 | $818,000 | $875,000 | $568,345 | $728,381 |
| 39 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $5,000.00 | $2,436.00 | $7,576.70 | $16,800 | $2,500.00 | $1,679.60 | $2,845.40 |
| 40 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $7,500.00 | $5,115.93 | $4,200.00 | $5,000.00 | $21,402 | $7,104.03 |
| 41 | TMA (stationary) (505-7001) | DAY | 408 | $120.00 | $100.00 | $127.90 | $25.00 | $130.00 | $125.63 | $164.87 |
| 42 | TMA (mobile operation) (505-7003) | DAY | 49 | $200.00 | $200.00 | $358.12 | $50.00 | $25.00 | $256.38 | $215.14 |
| 43 | Construction exits (install) (type 2) (506-7021) | SY | 222 | $30.00 | $17.50 | $17.50 | $50.00 | $10.00 | $22.81 | $20.59 |
| 44 | Construction exits (remove) (506-7024) | SY | 222 | $25.00 | $15.40 | $15.40 | $10.00 | $5.00 | $7.06 | $18.12 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 894 | $4.00 | $4.65 | $4.98 | $5.00 | $5.00 | $4.68 | $5.86 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 894 | $1.50 | $2.10 | $0.99 | $2.00 | $1.00 | $1.54 | $1.16 |
| 47 | Intersections (ACP) (530-7002) | SY | 700 | $85.00 | $56.16 | $81.60 | $40.30 | $85.00 | $81.31 | $68.95 |
| 48 | Driveways (concrete) (530-7006) | SY | 329 | $85.00 | $101.00 | $124.50 | $122.00 | $95.00 | $98.90 | $110.50 |
| 49 | Driveways (ACP) (530-7010) | SY | 3,907 | $45.00 | $46.44 | $45.20 | $60.00 | $45.00 | $41.83 | $36.03 |
| 50 | Turnouts (ACP) (530-7018) | SY | 213 | $45.00 | $75.62 | $55.90 | $60.00 | $45.00 | $79.22 | $41.99 |
| 51 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 52,537 | $0.15 | $0.17 | $0.19 | $0.20 | $0.10 | $0.24 | $0.23 |
| 52 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 26,269 | $0.15 | $0.23 | $0.25 | $0.20 | $0.10 | $0.31 | $0.23 |
| 53 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 15 | $350.00 | $250.00 | $225.00 | $225.00 | $250.00 | $249.66 | $264.69 |
| 54 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $500.00 | $675.00 | $950.00 | $950.00 | $675.00 | $1,007.56 | $1,117.59 |
| 55 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 29 | $815.00 | $775.00 | $795.00 | $795.00 | $775.00 | $845.16 | $935.25 |
| 56 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 8 | $825.00 | $850.00 | $1,050.00 | $1,050.00 | $850.00 | $1,112.56 | $1,235.23 |
| 57 | Install small roadside sign support and assembly TYS80(1)SA(P-exal) (644-7027) | EACH | 1 | $1,000.00 | $1,100.00 | $1,850.00 | $1,850.00 | $1,100.00 | $1,952.56 | $2,176.36 |
| 58 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $870.00 | $900.00 | $1,500.00 | $1,500.00 | $900.00 | $1,585.06 | $1,764.62 |
| 59 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,092.00 | $1,300.00 | $1,450.00 | $1,450.00 | $1,300.00 | $1,532.56 | $1,705.80 |
| 60 | Remove SM RD SN sup&AM (644-7073) | EACH | 27 | $170.00 | $100.00 | $75.00 | $75.00 | $100.00 | $90.64 | $88.23 |
| 61 | Relocate SM RD SN sup & AM type temporary (644-7077) | EACH | 27 | $675.00 | $275.00 | $275.00 | $275.00 | $50.00 | $299.93 | $323.51 |
| 62 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 34 | $65.00 | $70.00 | $82.50 | $82.50 | $70.00 | $98.46 | $97.05 |
| 63 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 171,690 | $0.40 | $0.20 | $0.20 | $0.20 | $0.20 | $0.22 | $0.24 |
| 64 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 6,440 | $1.00 | $0.75 | $1.45 | $1.40 | $0.50 | $1.48 | $0.59 |
| 65 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 52,697 | $0.50 | $0.48 | $0.48 | $0.48 | $0.50 | $0.52 | $0.56 |
| 66 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 620 | $0.50 | $1.10 | $1.10 | $1.10 | $1.10 | $1.32 | $1.29 |
| 67 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 23,303 | $0.50 | $0.68 | $0.68 | $0.68 | $0.70 | $0.76 | $0.80 |
| 68 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 630 | $4.00 | $7.50 | $7.50 | $7.50 | $7.50 | $8.03 | $8.82 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.