Low bidders on TxDOT contracts carried a median of $25.00 per SY for this item, over the 24 months to 19 NOV 2026, across 42 low bids. Half of all 258 bids fell between $22.05 and $50.00.

Owner
Texas DOT
Item
506-7021
Unit
SY
Data through
19 NOV 2026

TxDOT prints this item as “CONSTRUCTION EXITS (INSTALL) (TY 2)”.

TxDOT has bid this work under more than one code: 5066021002 on lettings from 10 JAN 2020 to 03 MAY 2024 (49 bids); 5066021004 on lettings from 04 JUN 2020 to 04 SEP 2020 (47 bids); 5066021005 on lettings from 02 DEC 2020 to 10 JUL 2024 (280 bids); 506-7021 on lettings from 06 NOV 2024 to 03 NOV 2026 (277 bids). They are combined here into one trend.

$25.00Low bidder's median, per SY
$32.32Median of all bids, per SY
45Contracts in the window
$30.00Engineer's estimate, median per SY

By year of letting

Construction exits (install) (type 2), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201312$37.2576$35.00
20211414$20.5080$27.50
20221111$44.0051$44.77
20231917$30.0074$36.89
20242120$39.5095$37.48
20252019$30.00105$30.07
20262422$24.50147$38.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Pharr District17$25.0093$27.25
Bryan District6$18.5043$40.00
Corpus Christi District4$32.5035$37.31
Lufkin District3$20.0028$35.50
Houston District3$20.0016$39.00
Fort Worth District3$50.5113$50.00
Construction exits (install) (type 2), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (SY)Low bidsLow-bid median
78 to 15610$31.50
222 to 44611$30.00
468 to 66910$23.59
702 to 15,98811$19.00
Construction exits (install) (type 2), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Construction exits (install) (type 2), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
03 NOV 2026A00204003Bryan District78$10.00$66.62$25.0012C & W Southern LLCTxDOT
06 OCT 2026A00186301Waco District446$70.00$46.00$30.006Big Creek Construction, LTD.TxDOT
03 SEP 2026A00123454Pharr District936$16.55$22.00$40.005Reim Construction, Inc.TxDOT
02 SEP 2026A00210535Paris District472n/a$39.00$25.003Highway 19 Construction LLCTxDOT
05 AUG 2026A00196471Corpus Christi District222$17.50$22.81$30.009Clark Construction of Texas, Inc.TxDOT
05 AUG 2026A00131912Pharr District312$25.00$25.00$32.007Ioc Company LLCTxDOT
05 AUG 2026A00189992Bryan District312n/a$35.00$45.006THK Construction LLCTxDOT
02 JUL 2026A00184725San Antonio District156$24.00$20.00$79.653Dan Williams CompanyTxDOT
02 JUL 2026A00214821Bryan District234$25.00$25.00n/a3Taylor Bridge LLCTxDOT
02 JUL 2026A00064356Lufkin District888$20.00$39.50$35.006Posillico Civil, Inc.TxDOT
01 JUL 2026A00008199Fort Worth District702$60.00$45.00$70.006Indus Road & Bridge, Inc.TxDOT
03 JUN 2026A00190949Corpus Christi District156$39.05$42.35$44.0010J. Carroll Weaver, Inc.TxDOT
03 JUN 2026A00214818Bryan District78$10.00$78.50$45.004Jackson Excavation, LLCTxDOT
02 JUN 2026A00193114Pharr District468$22.18$21.09$27.446Foremost Paving, Inc.TxDOT
07 MAY 2026A00109269Pharr District1,560$19.00$22.62$50.006Texas Cordia Construction, LLCTxDOT
Latest TxDOT contracts carrying Construction exits (install) (type 2)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy