TxDOT contract A00109269 bid tabulation

Widen Road - Add Lanes, FM 676 (SH 107 to TAYLOR RD.). Let by Texas DOT on May 7, 2026, Hidalgo, Pharr District. 6 bids received; low bid $24,782,061 by Texas Cordia Construction, LLC, -26% against the engineer's estimate of $33,439,910.

Owner
Texas DOT
Letting
07 MAY 2026
Pay items
213
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Texas Cordia Construction, LLC$24,782,061Low-26%
2Ioc Company LLC$26,656,017+8.0%-20%
3Reim Construction, Inc.$26,997,575+9.0%-19%
4Foremost Paving, Inc.$30,541,251+23%-9.0%
5James Construction Group, LLC$34,414,381+39%+3.0%
63LW Civil LLC$41,704,917+68%+25%
TxDOT contract A00109269: bids by rank

Engineer's estimate: $33,439,910.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Texas Cordia Construction, LLC2. Ioc Company LLC3. Reim Construction, Inc.4. Foremost Paving, Inc.5. James Construction Group, LLC6. 3LW Civil LLC
1Preparing row (100-7002)STA194$2,000.00$1,422.00$4,770.00$4,750.00$2,000.00$11,495$2,232.50
2Removing concrete (riprap) (104-7006)SY491$19.50$6.00$15.00$11.10$23.05$16.33$7.12
3Removing concrete (driveways) (104-7011)SY3,628$20.00$6.00$15.00$10.00$25.84$14.07$12.49
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY2,463$20.00$8.50$15.00$8.25$20.65$24.19$11.69
5Removing concrete (curb & gutter) (104-7017)LF5,272$9.00$5.50$3.75$3.05$9.04$6.45$4.32
6Removing concrete (gutter) (104-7019)LF377$11.00$5.50$10.00$5.50$9.04$9.15$15.98
7Excavation (roadway) (110-7001)CY77,411$9.00$6.00$5.00$6.05$14.06$12.12$18.00
8Embankment (final)(DC)(type A) (132-7002)CY7$24.00$158.00$200.00$145.00$101.00$155.65$1,080.00
9Embankment (final)(DC)(type C) (132-7006)CY1,286$6.00$3.50$10.00$6.00$99.73$187.15$19.20
10Backfill (type A) (134-7001)STA36$280.00$393.00$250.00$256.00$629.81$2,157.44$420.00
11Furn & place topsoil (vehicle) (160-7007)CY50$75.00$45.00$10.00$41.65$28.01$100.00$66.00
12Hydro mulch seed (permanent_rural_clay) (164-7018)SY24,382$0.50$0.50$0.36$0.40$0.56$0.38$0.62
13Hydro mulch seed (temporary_warm) (164-7021)SY48,373$0.40$0.50$0.25$0.30$0.51$0.28$0.58
14Vegetative watering (168-7001)TGL814$30.50$15.00$35.00$30.65$38.57$50.74$36.00
15Sprinkling (dust control) (204-7001)TGL776$10.00$18.00$1.00$30.65$1.00$26.81$24.00
16FL BS (roadway del)(type E GR 4)(final pos) (247-7277)CY20,938$54.00$45.00$25.00$35.00$26.15$45.28$75.60
17Rework BS metal (type B)(6")(DC)(org pos) (251-7034)CY25,989$4.00$3.50$3.00$4.50$7.72$26.54$62.40
18Cement (275-7001)TON3,290$220.00$200.00$189.00$214.00$181.73$209.31$276.00
19Cement TRT (existing material)(12") (275-7005)SY172,318$4.00$2.00$2.25$2.05$3.68$2.69$4.80
20Cement TRT (existing material & new base)(10") (275-7008)SY168,936$2.51$2.00$2.00$2.00$3.48$2.69$3.60
21Salvage, haul & stockpile reclaimed asphalt PV (2 to 4") (305-7003)SY83,593$17.50$3.00$2.00$3.05$1.77$3.99$4.20
22Prime coat (MC-30) (310-7004)GAL31,598$5.00$8.00$5.00$6.35$6.40$5.00$11.40
23Asphalt (tier II) (316-7266)GAL47,399$4.50$7.50$4.00$4.10$6.66$4.00$10.20
24Aggregate (type-B GR-4P sac-B) (316-7267)CY1,316$100.00$113.00$75.00$80.20$92.96$100.00$234.00
25SP mixes SP-D sac-A PG76-22 (344-7064)TON27,016$115.00$118.00$115.00$117.00$104.82$115.00$252.00
26Plane & text asphalt concrete pavement(1.5") (354-7018)SY1,167$4.50$11.00$5.00$1.65$29.47$19.34$12.00
27Plan & text concrete pavement(0" to 1.5") (354-7026)SY1,043$1.20$11.00$5.00$1.55$28.80$15.45$14.40
28Struct excavation (special) (400-7005)CY5,772$50.00$55.00$75.00$69.00$70.70$17.48$120.37
29Cut & restore asphalt paving (400-7008)SY1,385$145.00$89.00$75.00$62.20$78.78$45.98$166.76
30Cem stabil BKFL (400-7010)CY17,129$70.00$59.00$50.00$72.90$90.90$157.91$187.56
31Trench excavation protection (402-7001)LF22,356$10.00$3.00$0.10$3.60$0.11$1.09$1.20
32Temporary special shoring (403-7001)SF800$25.00$35.00$1.00$73.95$1.01$29.42$77.11
33Drilled shaft (traffic signal pole) (24 in) (416-7042)LF144$200.00$249.00$294.00$253.00$232.30$294.00$122.69
34Drilled shaft (traffic signal pole) (36 in) (416-7044)LF210$450.00$379.00$492.00$384.00$353.50$492.00$152.71
35Bridge sidewalk (422-7012)SF335$13.19$28.00$55.00$9.50$20.20$20.04$14.92
36Retaining wall (cast-in-place) (423-7016)SF2,620$107.16$47.00$75.00$32.15$45.45$108.01$84.00
37Riprap (concrete)(5 in) (432-7002)CY86$566.00$631.24$800.00$462.00$1,010.00$577.73$501.00
38Riprap (concrete)(CL B)(5 in) (432-7008)CY16$650.00$692.00$900.00$456.00$969.60$694.01$501.00
39Riprap (concrete)(flume) (432-7012)CY1$740.00$2,340.00$1,000.00$1,040.00$1,515.00$971.47$501.00
40Riprap (mow strip)(4 in) (432-7013)CY56$620.00$502.00$660.00$653.00$1,313.00$602.32$501.00
41Rail (type C221) (450-7032)LF101$170.00$75.00$265.00$387.00$79.29$169.51$198.37
42Rail (type PR11) (450-7044)LF250$130.00$185.00$100.00$155.00$135.85$131.16$140.33
43Concrete box culvert (5 FT X 5 FT) (462-7009)LF5,266$700.00$550.00$715.00$606.00$633.27$582.21$603.64
44Concrete box culvert (6 FT X 6 FT) (462-7014)LF1,978$1,200.00$588.00$780.00$754.00$749.42$722.26$755.91
45Concrete box culvert (9 FT X 5 FT) (462-7027)LF224$910.00$1,530.00$1,440.00$847.00$1,464.50$1,204.24$996.08
46RC pipe (CL III)(15 in) (464-7002)LF80$100.00$68.00$90.00$60.30$86.86$104.07$81.35
47RC pipe (CL III)(18 in) (464-7003)LF5,248$82.00$65.00$80.00$66.00$112.11$72.07$83.91
48RC pipe (CL III)(24 in) (464-7005)LF1,829$110.00$75.00$95.00$76.35$98.98$79.56$96.35
49RC pipe (CL III)(30 in) (464-7007)LF445$120.00$93.00$130.00$101.00$134.33$108.15$146.21
50RC pipe (CL III)(36 in) (464-7009)LF328$182.00$135.00$170.00$144.00$176.75$171.07$201.81
51RC pipe (CL III)(42 in) (464-7010)LF979$230.00$177.00$225.00$193.00$214.12$178.17$251.07
52RC pipe (CL III)(48 in) (464-7011)LF2,035$250.00$211.00$255.00$224.00$295.93$207.62$302.35
53RC pipe (CL III)(60 in) (464-7013)LF2,962$424.00$414.00$370.00$331.00$415.11$332.47$454.36
54RC pipe (CL III)(72 in) (464-7015)LF303$505.00$628.00$665.00$771.00$656.50$682.41$646.62
55RC pipe (CL IV)(60 in) (464-7028)LF451$560.00$434.00$435.00$376.00$429.25$363.82$516.45
56Manh (complete)(PRM)(72IN) (465-7004)EACH1$14,000$15,060$16,000$6,310.00$8,231.50$9,151.74$6,507.70
57Inlet (complete)(pcu)(3FT)(none) (465-7029)EACH19$7,000.00$3,530.00$5,000.00$6,250.00$8,433.50$7,846.96$7,305.70
58Inlet (complete)(pcu)(3FT)(left) (465-7030)EACH38$8,400.00$3,750.00$5,000.00$6,780.00$8,948.60$9,695.13$7,735.88
59Inlet (complete)(pcu)(3FT)(right) (465-7031)EACH32$8,500.00$2,950.00$4,000.00$9,220.00$11,706$10,533$10,279
60Inlet (complete)(pcu)(3FT)(both) (465-7032)EACH23$8,428.69$3,900.00$4,500.00$7,510.00$9,362.70$10,050$8,279.17
61Inlet (complete)(pcu)(4FT)(right) (465-7035)EACH2$9,479.27$5,510.00$7,500.00$5,600.00$8,249.68$9,045.23$6,488.82
62Inlet (complete)(pcu)(4FT)(both) (465-7036)EACH2$11,816$5,210.00$7,000.00$6,240.00$8,110.30$9,876.69$6,903.70
63Inlet (complete)(pcu)(5FT)(none) (465-7037)EACH2$7,380.00$6,640.00$10,000$5,220.00$9,221.30$8,789.56$6,213.70
64Inlet (complete)(pcu)(5FT)(right) (465-7039)EACH2$11,100$6,280.00$9,500.00$6,050.00$9,837.40$9,867.02$8,651.05
65Inlet (complete)(pcu)(6FT)(none) (465-7041)EACH1$11,025$9,650.00$18,000$6,840.00$10,605$11,545$7,773.70
66Inlet (complete)(pcu)(6FT)(left) (465-7042)EACH5$9,500.00$7,110.00$9,000.00$7,590.00$11,110$12,775$8,337.70
67Inlet (complete)(pcu)(6FT)(right) (465-7043)EACH2$13,303$8,970.00$13,000$10,200$13,433$15,608$11,074
68Inlet (complete)(pcu)(6FT)(both) (465-7044)EACH2$9,000.00$12,000$17,500$8,200.00$11,413$14,388$7,760.15
69Inlet (complete)(PSL)(RH)(6FTX6FT) (465-7068)EACH1$9,620.00$29,020$24,250$7,510.00$11,625$10,710$7,960.30
70Inlet (complete)(PSL)(RH)(8FTX8FT) (465-7069)EACH18$18,085$22,420$28,000$15,900$32,098$31,930$16,040
71Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH1$7,000.00$3,730.00$6,500.00$3,360.00$8,463.80$5,805.88$4,570.90
72Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX3FT) (465-7129)EACH7$8,000.00$4,990.00$6,000.00$4,600.00$9,266.75$7,543.44$5,532.36
73Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH2$40,000$24,290$35,000$49,100$40,653$39,048$14,753
74Set (type II) (15 in) (RCP) (6: 1) (P) (467-7300)EACH2$2,013.00$1,350.00$1,500.00$1,130.00$1,262.50$1,440.21$2,678.02
75Jack bor or tun pipe(60 in)(RC)(CL IV) (476-7027)LF80$1,350.00$1,850.00$1,500.00$1,820.00$2,828.00$2,365.45$1,957.77
76Adjusting manholes (479-7001)EACH46$2,600.00$5,340.00$1,500.00$805.00$1,414.00$1,606.20$847.35
77Adjusting inlets (cap) (479-7006)EACH5$3,000.00$1,800.00$2,500.00$1,910.00$2,525.00$2,910.85$3,506.60
78Removing structure (inlet) (496-7002)EACH19$1,200.00$574.00$750.00$657.00$939.30$1,083.27$1,132.73
79Removing structure (manhole) (496-7003)EACH2$1,200.00$1,990.00$1,000.00$960.00$1,287.75$833.92$1,385.62
80Removing structure (set) (496-7004)EACH139$280.00$272.00$250.00$244.00$730.23$541.63$322.77
81Removing structure (pipe) (496-7007)LF8,560$20.00$7.50$5.00$11.85$38.38$32.94$18.00
82Removing structure (box culvert) (496-7008)LF82$65.00$68.00$150.00$86.00$464.60$68.87$184.25
83Removing structure (pipe) (496-7037)EACH2$640.00$2,600.00$3,000.00$594.00$1,686.70$3,211.59$1,887.10
84Mobilization (500-7001)LS1$3,000,000$1,500,000$2,680,000$2,500,000$2,700,000$3,400,000$3,136,426
85Barricades, signs and traffic handling (502-7001)MO31$4,000.00$750.00$1,000.00$2,790.00$7,640.67$5,844.14$5,953.69
86Portable changeable message sign (503-7002)EACH12$10,100$47.00$100.00$5,580.00$7,767.19$10,742$80.40
87TMA (stationary) (505-7001)DAY956$130.00$20.00$0.10$27.90$42.46$88.63$210.00
88TMA (mobile operation) (505-7003)DAY45$180.00$59.00$0.10$112.00$0.01$599.90$240.00
89Construction exits (install) (type 2) (506-7021)SY1,560$50.00$19.00$25.00$14.15$20.25$110.00$60.00
90Construction exits (remove) (506-7024)SY1,560$10.50$6.00$10.00$8.00$13.27$35.00$15.60
91Temporary sediment control fence (install) (506-7039)LF12,005$4.20$4.00$3.25$3.85$4.30$3.80$5.70
92Temporary sediment control fence (remove) (506-7041)LF12,005$1.20$1.00$0.10$1.05$1.92$1.20$1.20
93Biodegradable erosion control logs (install) (12") (506-7044)LF2,425$5.50$6.00$3.49$3.15$6.01$6.00$8.40
94Biodegradable erosion control logs (remove) (506-7046)LF2,425$1.30$1.50$0.10$1.00$1.92$1.40$1.20
95Constructing detours (508-7001)SY19,765$60.00$32.00$28.50$40.80$44.95$31.15$57.34
96Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF7,340$35.00$16.00$10.00$53.75$25.51$42.64$42.82
97Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF3,040$35.00$20.00$25.00$56.15$31.64$42.77$79.15
98Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF4,480$8.00$7.00$4.00$5.00$15.18$7.22$4.83
99Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF1,840$8.00$7.00$4.00$5.00$7.95$8.41$12.14
100Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF7,340$9.00$6.50$5.00$5.00$17.19$9.76$6.48
101Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF3,040$15.00$11.00$5.00$5.00$11.92$9.36$6.07
102PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089)LF840$40.00$20.00$15.00$5.00$17.97$38.76$11.31
103PCTB (move)(F-shape or SNGL SLP)type 1 (512-7090)LF840$6.00$7.50$5.00$4.15$16.96$6.61$4.47
104PCTB (remove)(F-shape or SNGL SLP)type 1 (512-7092)LF840$12.00$10.00$10.00$5.00$12.75$12.57$4.95
105Concrete curb & gutter (type I) (529-7008)LF19,075$30.00$18.00$15.50$17.00$14.99$25.19$20.10
106Concrete curb & gutter (type II) (529-7009)LF5,589$30.00$16.00$15.50$17.00$16.22$33.79$20.10
107Concrete C&G (valley gutter) (529-7019)LF1,808$68.00$63.00$45.00$38.75$51.73$117.61$23.10
108Driveways (concrete) (530-7006)SY2,256$110.00$99.00$90.00$62.75$88.39$112.92$66.00
109Driveways (ACP) (530-7010)SY4,737$55.00$37.00$60.00$36.10$54.56$88.81$228.00
110Concrete sidewalks (4") (531-7001)SY12,669$75.00$55.00$41.00$40.30$62.55$68.45$55.66
111Curb ramps (type 2) (531-7006)EACH12$3,500.00$1,920.00$1,750.00$1,720.00$1,226.66$2,948.81$3,180.00
112Curb ramps (type 5) (531-7008)EACH11$4,000.00$2,980.00$1,750.00$1,920.00$1,226.66$3,225.56$3,720.00
113Curb ramps (type 10) (531-7011)EACH49$2,500.00$2,050.00$1,800.00$1,810.00$1,226.66$2,886.38$2,940.00
114Metal W-beam guard fence (timber post) (540-7001)LF1,250$30.00$31.00$31.83$33.80$30.76$24.75$30.91
115Downstream anchor terminal section (540-7015)EACH1$1,600.00$1,510.00$1,447.72$1,730.00$1,398.85$1,350.00$2,223.64
116Remove metal beam guard fence (542-7001)LF1,829$3.40$3.50$3.14$2.90$3.03$2.00$4.79
117Remove terminal anchor section (542-7002)EACH2$300.00$270.00$229.97$275.00$222.20$200.00$331.82
118Remove downstream anchor terminal (542-7003)EACH1$350.00$1,000.00$229.96$462.00$222.20$200.00$663.64
119Guardrail end treatment (install) (544-7001)EACH1$3,300.00$3,550.00$3,763.04$3,900.00$3,636.00$3,350.00$4,939.45
120Crash cushion attenuator (move & reset) (545-7002)EACH12$1,500.00$2,080.00$1,000.00$1,720.00$1,530.15$2,000.00$796.91
121Crash cushion attenuator (remove) (545-7004)EACH14$850.00$1,130.00$250.00$579.00$818.10$1,000.00$793.27
122Crash cushion attenuator (install)(R)(N)(TL3) (545-7010)EACH2$30,000$8,480.00$30,000$26,800$29,118$25,750$22,577
123Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH14$9,000.00$10,450$7,500.00$8,430.00$8,110.30$8,325.00$7,306.31
124Mailbox install-S (TWW-post) type 4 (560-7008)EACH64$375.00$515.00$297.54$247.00$287.85$285.00$270.00
125Mailbox install-D (TWW-post) type 4 (560-7009)EACH11$295.00$486.00$339.30$302.00$328.25$325.00$330.00
126Mailbox install-M (TWW-post) type 4 (560-7010)EACH9$800.00$897.00$908.29$1,040.00$878.70$870.00$1,140.00
127Conduit (PVC) (schedule 40) (1") (618-7021)LF90$17.26$6.00$11.55$6.10$5.66$11.55$21.67
128Conduit (PVC) (schedule 40) (2") (618-7030)LF765$8.00$28.00$16.00$28.50$26.26$16.00$22.27
129Conduit (PVC) (schedule 40) (4") (618-7040)LF423$25.00$35.00$24.00$35.15$32.32$24.00$24.25
130Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF295$30.00$31.00$25.00$31.85$29.29$25.00$36.37
131Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF885$40.00$37.00$35.30$37.35$34.34$35.30$39.49
132Electrical conductor (no.8) bare (620-7007)LF1,855$1.90$2.00$1.80$2.20$2.08$1.80$4.45
133Electrical conductor (no.6) bare (620-7009)LF189$2.40$2.50$2.00$2.75$2.53$2.00$4.62
134Electrical conductor (no.6) insulated (620-7010)LF365$2.70$2.50$2.35$2.75$2.53$2.35$4.92
135Tray cable (4 conductor) (12 AWG) (621-7006)LF2,422$3.10$3.00$3.10$3.30$3.03$3.10$5.28
136Ground box type A (122311)W/apron (624-7002)EACH27$1,400.00$1,410.00$1,224.30$1,430.00$1,313.00$1,224.30$1,860.00
137Ground box type D (162922)W/apron (624-7008)EACH3$1,600.00$1,840.00$1,340.65$1,870.00$1,717.00$1,340.65$1,920.00
138Zinc-coat steel wire strand (3/16") (625-7001)LF1,775$4.10$4.00$2.50$4.05$3.74$2.50$4.52
139Zinc-coat steel wire strand (5/16") (625-7003)LF4,715$4.00$4.50$2.90$4.40$4.10$2.90$4.78
140Elc SRV type D 120/240 060(NS)GS(N)TP(O) (628-7138)EACH4$3,690.00$4,650.00$6,283.00$4,720.00$4,343.00$6,283.00$4,500.00
141Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322)EACH4$2,550.46$4,220.00$4,422.00$4,280.00$3,939.00$4,422.00$4,500.00
142Aluminum signs (type A) (636-7001)SF453$35.00$19.00$25.32$30.75$24.50$30.00$44.40
143Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH104$770.00$765.00$709.93$741.00$686.80$680.00$810.00
144Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026)EACH30$950.00$861.00$730.81$1,070.00$707.00$700.00$1,170.00
145Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH40$957.00$892.00$908.29$1,210.00$878.70$870.00$1,320.00
146Remove SM RD SN sup&AM (644-7073)EACH69$112.33$263.00$114.84$71.35$111.10$110.00$78.00
147Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH6$50.00$206.00$42.81$82.00$41.41$41.00$90.00
148Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH35$100.00$235.00$78.30$104.00$75.75$75.00$114.00
149Remove delin & object marker assms (658-7078)EACH4$20.10$74.00$19.32$54.00$18.69$18.50$60.00
150Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF43,711$0.50$0.50$0.62$0.50$0.51$0.50$0.60
151Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF4,523$0.60$1.00$1.21$1.00$0.89$0.88$1.06
152Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF1,625$7.60$3.50$9.84$3.85$3.54$3.50$4.20
153Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH38$150.00$50.00$120.51$54.00$50.50$50.00$60.00
154Work zone pavement marking non-removing(W)(word) (662-7030)EACH38$200.00$75.00$120.51$82.00$75.75$75.00$90.00
155Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF4,740$0.32$0.50$0.75$0.70$0.69$0.68$0.82
156Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF70,162$0.50$0.50$0.62$0.50$0.51$0.50$0.60
157Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH1,921$4.00$5.00$4.22$5.50$5.05$5.00$6.00
158Work zone pavement marking removing (W)6"(DOT) (662-7066)LF248$2.00$2.50$2.21$2.75$2.53$2.50$3.00
159Work zone pavement marking removing (W)6"(solid) (662-7068)LF2,049$0.75$1.00$0.85$0.95$0.89$0.88$1.06
160Work zone pavement marking removing (Y)6"(solid) (662-7100)LF786$1.00$1.00$1.21$1.20$1.12$1.10$1.32
161Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF8,318$1.00$1.00$1.21$0.95$0.89$0.88$1.06
162Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF330$3.00$2.00$4.22$2.10$2.02$2.00$2.40
163Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF4,981$7.00$3.50$7.83$3.75$3.44$3.40$4.08
164Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH91$180.00$50.00$110.47$55.00$50.50$50.00$60.00
165Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH67$250.00$95.00$110.47$104.00$95.95$95.00$114.00
166Reflectorized pavement marking type I (W)(bike arrow)(100MIL) (666-7093)EACH33$210.00$75.00$160.68$82.00$75.75$75.00$90.00
167Reflectorized pavement marking type I(W)(bike syml)(100MIL) (666-7099)EACH33$255.00$150.00$160.68$165.00$151.50$150.00$180.00
168Reflectorized pavement marking type II (W) 18" (solid) (666-7183)LF24$3.50$25.00$6.83$27.00$25.25$25.00$30.00
169Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF7,221$0.60$1.00$0.65$1.05$0.95$0.94$1.13
170Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF27,757$0.50$0.50$0.68$0.70$0.69$0.68$0.82
171Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF4,590$0.52$1.00$0.75$1.05$0.95$0.94$1.13
172Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF37,797$0.60$0.50$0.68$0.70$0.69$0.68$0.82
173Reflectorized pavement marker type I-C (672-7002)EACH793$5.00$7.50$4.22$8.25$7.58$7.50$9.00
174Reflectorized pavement marker type II-A-A (672-7004)EACH1,498$4.20$7.50$4.22$8.25$7.58$7.50$9.00
175Eliminating existing PM & markers (4") (677-7001)LF26,992$0.50$0.15$0.60$0.15$0.16$0.15$0.18
176Eliminating existing PM & markers (6") (677-7002)LF2,019$0.41$0.50$0.80$0.25$0.26$0.25$0.30
177Eliminating existing PM & markers (8") (677-7004)LF896$0.82$0.50$1.41$0.40$0.36$0.35$0.42
178Eliminating existing PM & markers (12") (677-7006)LF756$1.50$0.50$1.91$0.50$0.46$0.45$0.54
179Eliminating existing PM & markers (24") (677-7008)LF361$3.00$1.00$5.02$0.80$0.76$0.75$0.90
180Eliminating existing PM & markers (arrow) (677-7009)EACH19$50.00$25.00$60.26$27.00$25.25$25.00$30.00
181Eliminating existing PM & markers (word) (677-7015)EACH10$58.00$25.00$60.26$27.00$25.25$25.00$30.00
182Install highway traffic signal (flash beacon) (680-7001)EACH1$10,000$4,980.00$11,984$5,050.00$4,646.00$11,984$4,380.00
183Install highway traffic signal (isolated) (680-7002)EACH4$30,000$26,820$34,832$27,200$25,048$34,832$26,040
184Removing traffic signals (680-7004)EACH4$6,000.00$3,790.00$4,599.00$3,840.00$3,535.00$4,599.00$4,200.00
185Temporary traffic signals (681-7001)EACH6$7,500.00$26,930$12,935$27,300$25,149$12,935$21,633
186Vehicle signal section (12")LED(green) (682-7001)EACH32$330.00$346.00$274.00$351.00$323.20$274.00$239.86
187Vehicle signal section (12")LED(green arrow) (682-7002)EACH17$350.00$346.00$274.00$351.00$323.20$274.00$239.86
188Vehicle signal section (12")LED(yel) (682-7003)EACH36$330.00$346.00$274.00$351.00$323.20$274.00$239.86
189Vehicle signal section (12")LED(yel arrow) (682-7004)EACH34$350.00$346.00$274.00$318.00$323.20$274.00$239.86
190Vehicle signal section (12")LED(red) (682-7005)EACH36$350.00$346.00$274.00$351.00$323.20$274.00$239.86
191Vehicle signal section (12")LED(red arrow) (682-7006)EACH17$360.00$346.00$274.00$351.00$323.20$274.00$239.86
192Pedestrian signal section (LED)(countdown) (682-7018)EACH32$696.00$876.00$606.00$889.00$818.10$606.00$864.00
193Backplate W/reflectorized border(4 sec) (682-7037)EACH17$240.00$260.00$255.00$264.00$242.40$255.00$259.46
194Backplate W/reflectorized border(3 sec) (682-7054)EACH32$200.00$184.00$228.00$187.00$171.70$606.00$193.46
195Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF3,825$2.00$2.00$2.30$2.20$2.08$2.30$3.10
196Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF6,480$2.10$3.50$3.40$3.55$3.29$3.40$4.06
197Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF2,447$3.20$4.50$4.41$4.65$4.30$4.41$4.84
198Install RDSD flash beacon assembly (685-7001)EACH7$6,000.00$5,730.00$5,181.00$5,820.00$5,353.00$5,181.00$3,822.85
199Remove RDSD flash beacon assembly (685-7003)EACH7$900.00$346.00$403.00$351.00$323.20$403.00$514.28
200Ins traffic signal PL AM (S)STR(type B)lum (686-7008)EACH14$9,500.00$8,540.00$9,560.00$8,670.00$7,979.00$9,560.00$7,892.57
201Pedestrian pole assembly (687-7001)EACH20$2,700.00$1,300.00$3,459.00$1,320.00$1,212.00$3,459.00$1,380.00
202Pedestrian detect push button (APS) (688-7001)EACH32$1,100.00$1,010.00$820.00$1,020.00$939.30$820.00$1,188.00
203Pedestrian detector controller unit (688-7003)EACH4$4,200.00$3,790.00$3,839.00$3,840.00$3,535.00$3,839.00$4,680.00
204Removal of conduit (690-7001)LF6,258$2.60$4.50$5.80$4.40$4.04$5.80$5.75
205Removal of ground boxes (690-7006)EACH75$230.00$89.00$350.00$90.05$82.82$350.00$240.00
206PRSSR irrig PVC pipe (18") (1000-7001)LF100$93.00$122.00$200.00$63.00$262.60$58.83$420.00
207PRSSR irrig PVC pipe (24") (1000-7002)LF342$142.00$194.00$195.00$102.00$242.40$87.19$480.00
208Bonding course (3007-7001)GAL11,060$3.40$6.00$3.00$3.00$2.64$5.00$8.40
209Impermeable liner (5030-7001)SY449$20.00$63.00$15.00$80.00$31.31$53.47$8.40
210RVDS (presence detection only) (6008-7001)EACH24$7,900.00$4,870.00$3,741.00$4,940.00$4,545.00$3,741.00$11,247
211RVDS (advance detection only) (6008-7002)EACH24$7,900.00$4,870.00$3,835.00$4,940.00$4,545.00$3,835.00$10,707
212Welded steel casing pipe (open cut)(24") (7003-7001)LF93$173.00$297.00$300.00$283.00$464.60$170.50$362.05
213Welded steel casing pipe (open cut)(30") (7003-7002)LF304$225.00$391.00$400.00$399.00$565.60$203.79$527.37
TxDOT contract A00109269: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy