Concrete box culvert (6 FT X 6 FT), TxDOT 462-7014
Low bidders on TxDOT contracts carried a median of $825.00 per LF for this item, over the 24 months to 19 NOV 2026, across 9 low bids. Half of all 65 bids fell between $729.00 and $1,200.00.
- Owner
- Texas DOT
- Item
- 462-7014
- Unit
- LF
- Data through
- 19 NOV 2026
TxDOT prints this item as “CONC BOX CULV (6 FT X 6 FT)”.
TxDOT has bid this work under more than one code: 4626013002 on lettings from 09 JAN 2020 to 09 JUL 2024 (143 bids); 462-7014 on lettings from 04 MAR 2025 to 07 MAY 2026 (65 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 7 | $709.10 | 36 | $700.70 |
| 2021 | 8 | 8 | $616.52 | 42 | $700.00 |
| 2022 | 3 | 3 | $988.62 | 14 | $956.50 |
| 2023 | 5 | 5 | $750.00 | 23 | $900.00 |
| 2024 | 8 | 8 | $964.90 | 28 | $927.90 |
| 2025 | 7 | 7 | $978.61 | 50 | $1,000.00 |
| 2026 | 2 | 2 | $639.50 | 15 | $690.00 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 8 | 4 (50%) |
| Hunter Industries, LTD. | 11 | 2 (18%) |
| A. L. Helmcamp, Inc. | 5 | 1 (20%) |
| Texas Materials Group, Inc. | 7 | 0 (0%) |
| CK Newberry, LLC | 7 | 0 (0%) |
| James Construction Group, LLC | 5 | 0 (0%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 MAY 2026 | A00109269 | Pharr District | 1,978 | $588.00 | $751.71 | $1,200.00 | 6 | Texas Cordia Construction, LLC | TxDOT |
| 06 MAY 2026 | A00014162 | Dallas District | 264 | $691.00 | $490.14 | $1,500.00 | 9 | Webber, LLC | TxDOT |
| 05 NOV 2025 | A00063983 | Austin District | 96 | $825.00 | $1,289.50 | $825.00 | 8 | Joe Bland Construction LLC | TxDOT |
| 05 NOV 2025 | A00135331 | Austin District | 56 | $1,600.00 | $962.50 | $875.00 | 10 | Posillico Civil, Inc. | TxDOT |
| 08 OCT 2025 | A00062536 | Abilene District | 131 | $978.61 | $774.29 | n/a | 9 | James Construction Group, LLC | TxDOT |
| 05 SEP 2025 | A00123610 | Corpus Christi District | 218 | $740.00 | $819.00 | $775.00 | 7 | Bay LTD. | TxDOT |
| 05 JUN 2025 | A00195596 | Yoakum District | 64 | $790.84 | $1,200.00 | $1,300.00 | 5 | Hunter Industries, LTD. | TxDOT |
| 04 APR 2025 | A00197887 | Beaumont District | 32 | $1,320.00 | $1,200.00 | $655.00 | 5 | Texas Materials Group, Inc. | TxDOT |
| 04 MAR 2025 | A00124556 | Yoakum District | 12 | $1,562.00 | $1,321.01 | $800.00 | 6 | Clark Construction of Texas, Inc. | TxDOT |
| 09 JUL 2024 | 07243004 | Laredo District | 198 | $770.00 | $870.00 | $968.75 | 2 | Hunter Industries, LTD. | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 54 | $1,350.00 | $1,350.00 | $992.83 | 3 | Harper Brothers Construction LLC | TxDOT |
| 05 JUN 2024 | 06243047 | Corpus Christi District | 366 | $774.53 | $900.00 | $1,000.00 | 5 | J. Carroll Weaver, Inc. | TxDOT |
| 05 APR 2024 | 04243207 | Beaumont District | 44 | $1,050.00 | $847.28 | $795.00 | 2 | Texas Materials Group, Inc. | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 2,327 | $686.68 | $634.34 | $750.00 | 2 | Sema Construction, Inc. | TxDOT |
| 06 MAR 2024 | 03243205 | Pharr District | 1,439 | $1,170.00 | $1,140.00 | $430.00 | 5 | Texas Cordia Construction, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.