TxDOT contract A00135331 bid tabulation
Widen Road - Add Shoulders, FM 112 (CR 438 to CR 492). Let by Texas DOT on November 5, 2025, Williamson, Austin District. 10 bids received; low bid $4,482,347 by Posillico Civil, Inc., -13% against the engineer's estimate of $5,142,434.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Posillico Civil, Inc. | $4,482,347 | Low | -13% |
| 2 | Hunter Industries, LTD. | $4,523,618 | +1.0% | -12% |
| 3 | Joe Bland Construction LLC | $4,614,424 | +3.0% | -10% |
| 4 | Chasco Constructors | $4,844,488 | +8.0% | -6.0% |
| 5 | STX Civil | $5,117,875 | +14% | 0.0% |
| 6 | Aaron Concrete Contractors, LLC | $5,165,235 | +15% | 0.0% |
| 7 | Texas Materials Group, Inc. | $5,213,821 | +16% | +1.0% |
| 8 | Patin Construction LLC | $5,301,387 | +18% | +3.0% |
| 9 | Knife River Corporation - South | $5,578,412 | +24% | +8.0% |
| 10 | Grey Sky Construction LLC | $5,787,116 | +29% | +13% |
Engineer's estimate: $5,142,434.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Posillico Civil, Inc. | 2. Hunter Industries, LTD. | 3. Joe Bland Construction LLC | 4. Chasco Constructors | 5. STX Civil | 6. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 120 | $3,000.00 | $1,200.00 | $519.20 | $1,000.00 | $400.00 | $369.00 | $300.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 10,612 | $21.00 | $6.00 | $15.40 | $12.00 | $20.00 | $36.00 | $16.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 9,488 | $22.50 | $12.00 | $15.40 | $10.00 | $35.00 | $38.00 | $36.00 |
| 4 | Backfill (type A) (134-7001) | STA | 24 | $150.00 | $600.00 | $151.80 | $1,275.00 | $210.00 | $251.00 | $2,600.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 27,363 | $2.25 | $1.00 | $1.15 | $2.00 | $1.50 | $0.50 | $2.00 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 27,363 | $0.22 | $0.14 | $0.14 | $0.25 | $0.50 | $0.50 | $0.35 |
| 7 | Vegetative watering (168-7001) | TGL | 462 | $35.00 | $30.00 | $26.40 | $40.00 | $25.00 | $100.00 | $32.00 |
| 8 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 8,168 | $80.00 | $65.00 | $72.12 | $108.00 | $65.00 | $75.00 | $75.00 |
| 9 | Prime coat (AE-P) (310-7001) | GAL | 4,303 | $5.50 | $3.00 | $4.51 | $4.00 | $3.50 | $4.00 | $4.00 |
| 10 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 17,374 | $4.75 | $3.00 | $3.74 | $3.50 | $3.50 | $4.00 | $4.00 |
| 11 | Aggregate (type-PD, GR-4)(sac-B) (316-7224) | CY | 381 | $175.00 | $189.00 | $136.05 | $200.00 | $198.00 | $200.00 | $235.00 |
| 12 | D-GR HMA type-C PG76-22 (341-7030) | TON | 3,994 | $125.00 | $122.00 | $101.20 | $130.00 | $128.00 | $132.00 | $145.00 |
| 13 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 2,767 | $130.00 | $115.00 | $103.40 | $125.00 | $121.00 | $125.00 | $142.00 |
| 14 | Flexible pavement structure repair(6") (351-7005) | SY | 4,533 | $65.00 | $65.00 | $46.23 | $51.00 | $80.00 | $55.00 | $71.00 |
| 15 | Flowable backfill (401-7001) | CY | 76 | $300.00 | $275.00 | $150.00 | $220.00 | $215.00 | $227.00 | $255.00 |
| 16 | Trench excavation protection (402-7001) | LF | 60 | $25.00 | $10.00 | $25.00 | $4.00 | $25.00 | $13.00 | $15.00 |
| 17 | Temporary special shoring (403-7001) | SF | 160 | $35.00 | $175.00 | $10.00 | $125.00 | $25.00 | $23.00 | $35.00 |
| 18 | Riprap (concrete)(5 in) (432-7002) | CY | 399.82 | $600.00 | $650.00 | $750.00 | $575.00 | $650.00 | $606.00 | $688.00 |
| 19 | Riprap (mow strip)(4 in) (432-7013) | CY | 117.50 | $565.00 | $750.00 | $815.00 | $740.00 | $775.00 | $875.00 | $890.00 |
| 20 | Riprap (stone common)(dry)(8 in) (432-7030) | CY | 19.30 | $175.00 | $115.00 | $150.00 | $235.00 | $280.00 | $227.00 | $442.00 |
| 21 | Rirrap (stone common)(dry)(15 in) (432-7032) | CY | 17 | $275.00 | $175.00 | $175.00 | $245.00 | $290.00 | $227.00 | $492.00 |
| 22 | Concrete box culvert (6 FT X 6 FT) (462-7014) | LF | 56 | $875.00 | $1,600.00 | $1,200.00 | $925.00 | $830.00 | $725.00 | $1,012.00 |
| 23 | Concrete box culvert (11 FT X 9 FT) (462-7044) | LF | 47 | $2,500.00 | $3,200.00 | $2,200.00 | $1,950.00 | $2,100.00 | $2,315.00 | $2,348.00 |
| 24 | RC pipe (CL III)(18 in) (464-7003) | LF | 468 | $100.00 | $68.00 | $120.00 | $95.00 | $80.00 | $67.00 | $125.00 |
| 25 | RC pipe (CL III)(24 in) (464-7005) | LF | 40 | $140.00 | $91.00 | $122.00 | $165.00 | $110.00 | $82.00 | $220.00 |
| 26 | RC pipe (CL III)(30 in) (464-7007) | LF | 148 | $150.00 | $226.00 | $100.00 | $170.00 | $120.00 | $105.00 | $260.00 |
| 27 | RC pipe (CL III)(36 in) (464-7009) | LF | 73 | $220.00 | $170.00 | $430.00 | $295.00 | $250.00 | $145.00 | $430.00 |
| 28 | RC pipe (CL III)(42 in) (464-7010) | LF | 58 | $250.00 | $221.00 | $380.00 | $415.00 | $350.00 | $194.00 | $425.00 |
| 29 | Headwall (CH - PW - 0) (diameter= 42 in) (466-7106) | EACH | 2 | $14,500 | $16,000 | $17,500 | $12,500 | $11,000 | $19,415 | $20,000 |
| 30 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 2 | $30,000 | $35,000 | $33,500 | $22,250 | $26,000 | $30,000 | $28,000 |
| 31 | Wingwall (PW - 1) (HW=11 FT) (466-7181) | EACH | 1 | $60,000 | $95,000 | $62,500 | $41,750 | $48,000 | $73,500 | $53,000 |
| 32 | Wingwall (PW - 1) (HW=12 FT) (466-7182) | EACH | 1 | $71,000 | $100,000 | $72,000 | $49,800 | $51,000 | $75,000 | $56,000 |
| 33 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 2 | $1,700.00 | $1,200.00 | $2,250.00 | $4,150.00 | $2,300.00 | $1,650.00 | $1,100.00 |
| 34 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 2 | $1,750.00 | $1,725.00 | $2,600.00 | $4,150.00 | $2,700.00 | $1,850.00 | $1,200.00 |
| 35 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 19 | $1,800.00 | $2,500.00 | $3,100.00 | $3,000.00 | $3,000.00 | $2,000.00 | $1,400.00 |
| 36 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 6 | $3,750.00 | $4,300.00 | $5,200.00 | $5,500.00 | $6,500.00 | $4,500.00 | $3,200.00 |
| 37 | Removing structure (set) (496-7004) | EACH | 23 | $500.00 | $250.00 | $300.00 | $575.00 | $500.00 | $675.00 | $690.00 |
| 38 | Removing structure (wingwall) (496-7005) | EACH | 13 | $1,750.00 | $1,500.00 | $3,500.00 | $500.00 | $1,000.00 | $3,000.00 | $1,600.00 |
| 39 | Removing structure (headwall) (496-7006) | EACH | 6 | $2,750.00 | $1,632.40 | $750.00 | $1,000.00 | $750.00 | $1,500.00 | $1,800.00 |
| 40 | Removing structure (pipe) (496-7007) | LF | 431 | $35.00 | $30.06 | $20.00 | $30.00 | $35.00 | $39.00 | $63.00 |
| 41 | Removing structure (box culvert) (496-7008) | LF | 60 | $150.00 | $290.96 | $300.00 | $75.00 | $80.00 | $125.00 | $186.00 |
| 42 | Mobilization (500-7001) | LS | 1 | $378,600 | $400,000 | $446,574 | $150,000 | $418,776 | $400,000 | $392,000 |
| 43 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $10,000 | $1,100.00 | $8,250.00 | $7,500.00 | $5,000.00 | $1,500.00 | $1,200.00 |
| 44 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $20,000 | $5,105.85 | $23,950 | $7,000.00 | $5,000.00 | $10,000 |
| 45 | TMA (stationary) (505-7001) | DAY | 279 | $225.00 | $75.00 | $153.18 | $210.00 | $355.00 | $120.00 | $175.00 |
| 46 | TMA (mobile operation) (505-7003) | DAY | 24 | $250.00 | $300.00 | $255.29 | $105.00 | $865.00 | $300.00 | $762.00 |
| 47 | Rock filter dams (install) (type 2) (506-7002) | LF | 800 | $45.00 | $35.00 | $50.00 | $40.00 | $30.00 | $55.00 | $35.00 |
| 48 | Rock filter dams (remove) (506-7011) | LF | 800 | $15.00 | $10.00 | $12.00 | $20.00 | $11.00 | $5.00 | $18.00 |
| 49 | Temporary sediment control fence (install) (506-7039) | LF | 12,645 | $3.50 | $3.50 | $3.30 | $5.00 | $4.00 | $4.00 | $3.40 |
| 50 | Temporary sediment control fence (remove) (506-7041) | LF | 12,645 | $1.00 | $1.00 | $1.00 | $1.00 | $0.50 | $0.50 | $0.80 |
| 51 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 1,000 | $7.25 | $4.00 | $4.00 | $6.00 | $5.00 | $5.50 | $5.80 |
| 52 | One-way traffic control (port traffic signal) (510-7003) | MO | 5 | $5,500.00 | $6,000.00 | $18,279 | $7,500.00 | $4,700.00 | $5,770.00 | $18,000 |
| 53 | Intersections (ACP) (530-7002) | SY | 408 | $95.00 | $75.00 | $48.40 | $50.00 | $90.00 | $52.00 | $57.00 |
| 54 | Driveways (ACP) (530-7010) | SY | 988 | $60.00 | $60.00 | $48.40 | $40.00 | $55.00 | $40.00 | $43.00 |
| 55 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,125 | $28.00 | $21.00 | $21.00 | $27.00 | $22.00 | $26.00 | $32.00 |
| 56 | Metal W-beam guard fence (steel post) (540-7002) | LF | 587.50 | $40.00 | $23.00 | $31.00 | $32.00 | $33.00 | $29.50 | $37.00 |
| 57 | Guardrail end treatment (install) (544-7001) | EACH | 12 | $3,500.00 | $2,540.00 | $3,000.00 | $3,500.00 | $3,150.00 | $3,135.00 | $4,200.00 |
| 58 | Wire fence (type A) (552-7001) | LF | 1,325 | $25.00 | $12.50 | $15.50 | $7.00 | $24.00 | $25.00 | $25.00 |
| 59 | Wire fence (remove) (552-7011) | LF | 1,325 | $3.50 | $3.00 | $4.65 | $3.00 | $2.50 | $5.00 | $3.50 |
| 60 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 4 | $650.00 | $550.00 | $550.00 | $550.00 | $575.00 | $760.00 | $640.00 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 41 | $750.00 | $625.00 | $625.00 | $825.00 | $650.00 | $750.00 | $730.00 |
| 62 | Remove SM RD SN sup&AM (644-7073) | EACH | 41 | $100.00 | $100.00 | $100.00 | $135.00 | $110.00 | $135.00 | $116.00 |
| 63 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 24,000 | $0.40 | $0.25 | $0.25 | $0.25 | $0.26 | $0.69 | $0.70 |
| 64 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 24 | $10.00 | $12.00 | $12.00 | $13.25 | $12.50 | $3.39 | $3.40 |
| 65 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 22,800 | $0.40 | $0.25 | $0.25 | $0.25 | $0.26 | $0.69 | $0.70 |
| 66 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 200 | $0.90 | $2.10 | $2.15 | $2.50 | $2.25 | $0.89 | $0.90 |
| 67 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,200 | $2.00 | $5.00 | $1.63 | $1.25 | $3.10 | $2.50 | $1.25 |
| 68 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 24,000 | $0.40 | $0.30 | $0.30 | $0.50 | $0.35 | $0.37 | $0.40 |
| 69 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 48 | $10.00 | $12.00 | $12.00 | $14.00 | $12.50 | $0.67 | $0.70 |
| 70 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 22,800 | $0.40 | $0.32 | $0.32 | $0.50 | $0.35 | $0.26 | $0.30 |
| 71 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 24,000 | $1.25 | $0.87 | $0.87 | $1.00 | $0.90 | $0.69 | $0.70 |
| 72 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 24,000 | $1.25 | $0.87 | $0.87 | $1.00 | $0.90 | $0.69 | $0.70 |
| 73 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 2,400 | $5.00 | $3.10 | $3.15 | $3.50 | $3.30 | $1.25 | $1.25 |
| 74 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 4,800 | $5.00 | $3.10 | $3.15 | $3.50 | $3.30 | $1.25 | $1.25 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 600 | $5.00 | $6.00 | $6.00 | $4.00 | $6.50 | $6.24 | $6.25 |
| 76 | Eliminating existing PM & markers (4") (677-7001) | LF | 24,000 | $0.60 | $0.20 | $0.20 | $0.25 | $0.25 | $0.25 | $0.25 |
| 77 | Bonding course (3007-7001) | GAL | 1,937 | $5.00 | $3.35 | $3.08 | $4.00 | $3.50 | $4.00 | $4.00 |
| 78 | Temporary solar RD IL (furnish and install) (6145-7001) | EACH | 6 | $10,000 | $24,350 | $24,350 | $25,000 | $26,000 | $28,470 | $30,285 |
| 79 | Temporary solar RD IL (move) (6145-7002) | EACH | 6 | $2,000.00 | $2,650.00 | $2,650.00 | $3,000.00 | $3,000.00 | $30,100 | $3,296.00 |
| 80 | Temporary solar RD IL (remove) (6145-7003) | EACH | 6 | $1,000.00 | $1,000.00 | $1,000.00 | $1,100.00 | $1,050.00 | $1,170.00 | $1,244.00 |
| 81 | Subsurface util locate (outside rdbed) (7019-7001) | EACH | 10 | $1,200.00 | $3,000.00 | $1,499.52 | $1,800.00 | $2,550.00 | $1,550.00 | $885.00 |
| 82 | Subsurface util locate (within rdbed) (7019-7002) | EACH | 2 | $2,700.00 | $1,500.00 | $1,499.52 | $3,000.00 | $4,100.00 | $2,500.00 | $2,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.