TxDOT contract A00063983 bid tabulation
Highway Improvement, US 183 (SH 138 to 0.23 MILES N. of CR 254). Let by Texas DOT on November 5, 2025, Williamson, Austin District. 8 bids received; low bid $14,639,581 by Joe Bland Construction LLC, -25% against the engineer's estimate of $19,572,840.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 122
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Joe Bland Construction LLC | $14,639,581 | Low | -25% |
| 2 | Texas Materials Group, Inc. | $14,682,822 | 0.0% | -25% |
| 3 | Hunter Industries, LTD. | $15,140,468 | +3.0% | -23% |
| 4 | Dan Williams Company | $15,440,402 | +5.0% | -21% |
| 5 | Posillico Civil, Inc. | $15,578,367 | +6.0% | -20% |
| 6 | Aaron Concrete Contractors, LLC | $15,679,939 | +7.0% | -20% |
| 7 | Chasco Constructors | $15,689,948 | +7.0% | -20% |
| 8 | Texas Road LLC | $16,484,001 | +13% | -16% |
Engineer's estimate: $19,572,840.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Joe Bland Construction LLC | 2. Texas Materials Group, Inc. | 3. Hunter Industries, LTD. | 4. Dan Williams Company | 5. Posillico Civil, Inc. | 6. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 293 | $3,000.00 | $750.00 | $350.00 | $732.60 | $2,750.00 | $218.00 | $250.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 1,035 | $25.00 | $25.00 | $20.00 | $16.50 | $16.00 | $20.00 | $18.00 |
| 3 | Removing concrete (miscellaneous) (104-7046) | SY | 44 | $20.00 | $30.00 | $31.00 | $29.70 | $45.00 | $142.00 | $21.00 |
| 4 | Remove (16") TRT/untrt base & asphalt pavement (105-7036) | SY | 7,576 | $12.00 | $6.00 | $8.02 | $9.90 | $6.50 | $19.00 | $12.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 28,582 | $14.00 | $15.00 | $11.75 | $14.30 | $15.00 | $7.00 | $4.50 |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 20,449 | $20.00 | $7.00 | $8.50 | $13.20 | $16.00 | $8.00 | $4.50 |
| 7 | Furn & place topsoil (4") (160-7002) | SY | 77,641 | $2.50 | $2.00 | $2.80 | $2.04 | $2.00 | $1.00 | $2.00 |
| 8 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 77,641 | $0.30 | $0.50 | $0.16 | $0.17 | $0.25 | $0.50 | $0.30 |
| 9 | Broadcast seed (temporary_warm) (164-7005) | SY | 38,820.50 | $0.40 | $0.20 | $0.14 | $0.15 | $0.13 | $0.50 | $0.15 |
| 10 | Broadcast seed (temporary_cool) (164-7006) | SY | 38,820.50 | $0.40 | $0.20 | $0.14 | $0.15 | $0.17 | $0.50 | $0.20 |
| 11 | Vegetative watering (168-7001) | TGL | 1,419 | $30.00 | $45.00 | $67.00 | $23.10 | $5.00 | $38.00 | $32.00 |
| 12 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 2,049 | $4.50 | $1.25 | $3.27 | $3.34 | $1.00 | $3.00 | $1.15 |
| 13 | Soil ret BLKT(chan_permanent_4 PSF) (169-7032) | SY | 68,272 | $7.00 | $2.00 | $1.75 | $1.79 | $1.80 | $2.00 | $2.00 |
| 14 | Soil ret BLKT(chan_permanent_8 PSF) (169-7034) | SY | 7,320 | $10.00 | $4.50 | $2.72 | $2.78 | $4.00 | $3.00 | $4.50 |
| 15 | Proof rolling (216-7001) | HR | 100 | $100.00 | $900.00 | $110.00 | $99.00 | $80.00 | $161.00 | $135.00 |
| 16 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 26,046 | $80.00 | $68.00 | $52.00 | $61.86 | $55.00 | $31.00 | $68.00 |
| 17 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 18,030 | $4.50 | $4.00 | $4.20 | $4.95 | $3.30 | $3.00 | $6.00 |
| 18 | D-GR HMA type-B PG64-22 (341-7001) | TON | 18,945 | $110.00 | $80.00 | $83.20 | $95.15 | $74.00 | $75.00 | $88.00 |
| 19 | D-GR HMA type-B PG64-22 (level-UP) (341-7004) | TON | 452 | $130.00 | $92.00 | $180.00 | $102.30 | $90.00 | $89.00 | $220.00 |
| 20 | D-GR HMA type D PG76-22 (341-7056) | TON | 18,969 | $145.00 | $95.00 | $103.70 | $98.45 | $91.00 | $91.00 | $111.00 |
| 21 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 6,611 | $130.00 | $108.00 | $102.00 | $102.85 | $100.00 | $102.00 | $122.00 |
| 22 | Tom-C PG76-22 sac-B (347-7002) | TON | 12,942 | $145.00 | $117.00 | $123.75 | $116.05 | $111.00 | $111.00 | $143.00 |
| 23 | Flexible pavement structure repair(8") (351-7007) | SY | 6,283 | $60.00 | $55.00 | $54.00 | $59.32 | $52.00 | $53.00 | $61.00 |
| 24 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 146,615 | $2.50 | $1.50 | $1.65 | $1.66 | $1.15 | $1.00 | $0.75 |
| 25 | Cut & restoring pavement (400-7006) | SY | 1,035 | $260.00 | $200.00 | $160.00 | $161.48 | $385.00 | $309.00 | $200.00 |
| 26 | Trench excavation protection (402-7001) | LF | 541 | $10.00 | $6.00 | $1.00 | $5.77 | $10.00 | $16.00 | $3.00 |
| 27 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 20 | $300.00 | $435.00 | $400.00 | $478.06 | $450.00 | $437.00 | $490.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 1,581 | $575.00 | $385.00 | $635.00 | $607.00 | $475.00 | $592.00 | $600.00 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 608 | $650.00 | $715.00 | $650.00 | $663.21 | $700.00 | $335.00 | $860.00 |
| 30 | Riprap (stone protection)(18 in) (432-7043) | CY | 300 | $195.00 | $245.00 | $240.00 | $156.45 | $200.00 | $291.00 | $200.00 |
| 31 | Concrete box culvert (5 FT X 4 FT) (462-7008) | LF | 58 | $585.00 | $670.00 | $1,025.00 | $692.71 | $560.00 | $827.00 | $1,000.00 |
| 32 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 71 | $525.00 | $716.00 | $1,025.00 | $750.44 | $650.00 | $852.00 | $975.00 |
| 33 | Concrete box culvert (6 FT X 4 FT) (462-7012) | LF | 132 | $565.00 | $753.00 | $1,125.00 | $785.07 | $700.00 | $938.00 | $2,100.00 |
| 34 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 31 | $780.00 | $934.00 | $1,260.00 | $923.61 | $700.00 | $1,033.00 | $1,400.00 |
| 35 | Concrete box culvert (6 FT X 6 FT) (462-7014) | LF | 96 | $825.00 | $825.00 | $1,375.00 | $946.71 | $725.00 | $1,204.00 | $2,600.00 |
| 36 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,636 | $100.00 | $125.00 | $60.00 | $55.42 | $72.00 | $110.00 | $97.00 |
| 37 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,570 | $115.00 | $150.00 | $72.00 | $69.27 | $82.00 | $134.00 | $130.00 |
| 38 | RC pipe (CL III)(30 in) (464-7007) | LF | 1,090 | $120.00 | $175.00 | $108.00 | $90.05 | $103.00 | $352.00 | $320.00 |
| 39 | RC pipe (CL III)(36 in) (464-7009) | LF | 335 | $210.00 | $265.00 | $170.00 | $144.31 | $140.00 | $473.00 | $430.00 |
| 40 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 8 | $9,750.00 | $6,500.00 | $8,800.00 | $13,854 | $8,500.00 | $14,456 | $13,000 |
| 41 | Headwall (CH - PW - 0) (diameter= 36 in) (466-7105) | EACH | 4 | $14,000 | $8,500.00 | $13,650 | $15,586 | $9,000.00 | $14,768 | $17,000 |
| 42 | Headwall (CH - PW - S) (diameter= 30 in) (466-7118) | EACH | 1 | $15,000 | $9,000.00 | $10,000 | $16,163 | $10,500 | $14,456 | $13,000 |
| 43 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 3 | $15,000 | $18,000 | $13,500 | $17,318 | $17,000 | $14,456 | $13,000 |
| 44 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 2 | $22,000 | $19,500 | $17,600 | $19,627 | $18,000 | $19,760 | $19,000 |
| 45 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 5 | $30,000 | $22,500 | $25,500 | $21,936 | $24,000 | $17,160 | $21,000 |
| 46 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 3 | $35,500 | $30,500 | $32,800 | $35,790 | $28,000 | $29,120 | $27,000 |
| 47 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 1 | $38,000 | $36,250 | $40,000 | $40,408 | $30,000 | $26,000 | $32,000 |
| 48 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 54 | $1,600.00 | $2,250.00 | $1,120.00 | $2,078.13 | $2,200.00 | $6,276.00 | $1,300.00 |
| 49 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 48 | $2,100.00 | $2,750.00 | $1,385.00 | $2,309.04 | $2,300.00 | $6,604.00 | $1,600.00 |
| 50 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 2 | $3,200.00 | $6,000.00 | $1,423.00 | $3,117.20 | $2,800.00 | $8,695.00 | $2,100.00 |
| 51 | Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347) | EACH | 4 | $3,500.00 | $6,250.00 | $2,300.00 | $3,463.56 | $3,000.00 | $10,403 | $2,100.00 |
| 52 | Removing structure (set) (496-7004) | EACH | 57 | $600.00 | $750.00 | $200.00 | $692.71 | $300.00 | $867.00 | $600.00 |
| 53 | Removing structure (wingwall) (496-7005) | EACH | 14 | $2,000.00 | $1,000.00 | $1,200.00 | $2,309.04 | $2,000.00 | $4,087.00 | $2,800.00 |
| 54 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,000.00 | $1,425.00 | $1,500.00 | $1,731.78 | $2,000.00 | $4,087.00 | $2,800.00 |
| 55 | Removing structure (pipe) (496-7007) | LF | 2,177 | $35.00 | $15.00 | $11.00 | $23.09 | $25.00 | $48.00 | $38.00 |
| 56 | Removing structure (box culvert) (496-7008) | LF | 58 | $55.00 | $100.00 | $100.00 | $115.45 | $130.00 | $281.00 | $590.00 |
| 57 | Removing structure (ret wall) (496-7019) | LF | 7 | $350.00 | $150.00 | $500.00 | $232.31 | $225.00 | $100.00 | $760.00 |
| 58 | Mobilization (500-7001) | LS | 1 | $1,444,900 | $425,000 | $1,025,000 | $1,060,250 | $1,500,000 | $1,500,000 | $250,000 |
| 59 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $14,000 | $2,820.00 | $13,553 | $25,000 | $57,429 | $2,700.00 |
| 60 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $23,750 | $4,900.00 | $5,151.23 | $15,000 | $9,743.00 | $10,000 |
| 61 | TMA (stationary) (505-7001) | DAY | 62 | $275.00 | $205.00 | $355.00 | $154.54 | $185.00 | $465.00 | $300.00 |
| 62 | TMA (mobile operation) (505-7002) | HR | 512 | $125.00 | $100.00 | $106.00 | $77.27 | $60.00 | $167.00 | $150.00 |
| 63 | Rock filter dams (install) (type 4) (506-7004) | LF | 162 | $65.00 | $75.00 | $56.06 | $59.02 | $65.00 | $56.00 | $74.00 |
| 64 | Rock filter dams (remove) (506-7011) | LF | 162 | $12.00 | $25.00 | $15.55 | $16.37 | $23.00 | $16.00 | $26.00 |
| 65 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,569 | $8.25 | $6.00 | $7.26 | $7.64 | $5.00 | $7.00 | $5.50 |
| 66 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,569 | $1.70 | $2.00 | $0.97 | $1.02 | $1.25 | $1.00 | $1.40 |
| 67 | Driveways (concrete) (530-7006) | SY | 721 | $120.00 | $170.00 | $167.00 | $122.52 | $100.00 | $288.00 | $128.00 |
| 68 | Driveways (ACP) (530-7010) | SY | 2,412 | $80.00 | $95.00 | $102.00 | $48.40 | $90.00 | $70.00 | $89.00 |
| 69 | Turnouts (ACP) (530-7018) | SY | 392 | $85.00 | $145.00 | $39.00 | $52.80 | $65.00 | $39.00 | $92.00 |
| 70 | Metal W-beam guard fence (timber post) (540-7001) | LF | 9,537.50 | $27.00 | $25.00 | $22.67 | $23.00 | $25.00 | $23.00 | $30.00 |
| 71 | Short radius (28") (540-7013) | LF | 325 | $50.00 | $50.00 | $48.26 | $48.00 | $50.00 | $48.00 | $58.00 |
| 72 | Downstream anchor terminal section (540-7015) | EACH | 24 | $1,500.00 | $1,425.00 | $1,220.30 | $1,250.00 | $1,450.00 | $1,220.00 | $1,700.00 |
| 73 | Metal beam guard fence (long span system) (540-7027) | EACH | 27 | $1,180.00 | $1,315.00 | $1,318.56 | $1,350.00 | $1,500.00 | $1,319.00 | $1,500.00 |
| 74 | Remove metal beam guard fence (542-7001) | LF | 1,975 | $2.50 | $3.00 | $6.00 | $2.50 | $3.00 | $6.00 | $2.60 |
| 75 | Guardrail end treatment (install) (544-7001) | EACH | 21 | $3,200.00 | $3,600.00 | $3,361.96 | $3,100.00 | $3,500.00 | $3,362.00 | $4,300.00 |
| 76 | Guardrail end treatment (remove) (544-7003) | EACH | 14 | $240.00 | $190.00 | $404.37 | $250.00 | $300.00 | $404.00 | $230.00 |
| 77 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 18 | $310.00 | $325.00 | $275.00 | $275.00 | $300.00 | $275.00 | $305.00 |
| 78 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 3 | $330.00 | $385.00 | $300.00 | $300.00 | $325.00 | $300.00 | $333.00 |
| 79 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 5 | $700.00 | $715.00 | $600.00 | $600.00 | $625.00 | $600.00 | $667.00 |
| 80 | Relocate RD IL asm (shoe-base) (610-7002) | EACH | 2 | $3,000.00 | $1,525.00 | $1,400.00 | $1,549.39 | $1,450.00 | $2,939.00 | $1,722.00 |
| 81 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 234 | $12.50 | $19.00 | $18.00 | $19.92 | $18.00 | $15.00 | $22.00 |
| 82 | Electrical conductor (no.8) bare (620-7007) | LF | 244 | $2.00 | $5.00 | $4.00 | $4.43 | $4.00 | $3.00 | $5.00 |
| 83 | Electrical conductor (no.8) insulated (620-7008) | LF | 488 | $2.10 | $6.00 | $5.00 | $5.53 | $5.00 | $3.00 | $6.00 |
| 84 | Ground box type A (122311)W/apron (624-7002) | EACH | 2 | $1,300.00 | $2,725.00 | $2,500.00 | $2,766.77 | $3,000.00 | $1,396.00 | $3,100.00 |
| 85 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 47 | $710.00 | $925.00 | $615.00 | $615.00 | $615.00 | $615.00 | $684.00 |
| 86 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $880.00 | $1,095.00 | $755.00 | $755.00 | $755.00 | $755.00 | $840.00 |
| 87 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $875.00 | $1,250.00 | $805.00 | $805.00 | $805.00 | $805.00 | $900.00 |
| 88 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 6 | $825.00 | $925.00 | $658.00 | $658.00 | $658.00 | $658.00 | $730.00 |
| 89 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 2 | $1,000.00 | $1,075.00 | $795.00 | $795.00 | $795.00 | $795.00 | $880.00 |
| 90 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 1 | $1,250.00 | $1,350.00 | $1,040.00 | $1,040.00 | $1,040.00 | $1,040.00 | $1,100.00 |
| 91 | Install small roadside sign support and assembly TYS80(1)SB(U-BM) (644-7045) | EACH | 1 | $2,040.00 | $1,350.00 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 | $1,150.00 |
| 92 | Remove SM RD SN sup&AM (644-7073) | EACH | 40 | $110.00 | $135.00 | $100.00 | $100.00 | $150.00 | $35.00 | $111.00 |
| 93 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 155 | $45.00 | $45.00 | $45.51 | $35.00 | $40.00 | $35.00 | $38.00 |
| 94 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 58,559 | $0.35 | $0.25 | $0.14 | $0.15 | $0.14 | $0.25 | $0.28 |
| 95 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 14,550 | $0.40 | $0.25 | $0.18 | $0.19 | $0.18 | $0.25 | $0.29 |
| 96 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 58,057 | $0.40 | $0.25 | $0.18 | $0.19 | $0.18 | $0.25 | $0.28 |
| 97 | Work zone pavement marking non-removing (W)8"(DOT) (662-7010) | LF | 54 | $0.75 | $0.25 | $0.22 | $0.23 | $0.22 | $1.00 | $1.17 |
| 98 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,749 | $0.48 | $0.25 | $0.22 | $0.23 | $0.22 | $1.00 | $0.61 |
| 99 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 12 | $4.55 | $6.50 | $6.00 | $6.32 | $6.00 | $6.00 | $5.83 |
| 100 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 40 | $82.33 | $38.00 | $35.00 | $36.86 | $35.00 | $35.00 | $58.30 |
| 101 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 16 | $95.92 | $45.00 | $40.00 | $42.12 | $40.00 | $40.00 | $58.30 |
| 102 | Work zone pavement marking non-removing (Y)4"(broken) (662-7033) | LF | 14,630 | $0.15 | $0.25 | $0.14 | $0.15 | $0.14 | $0.25 | $0.29 |
| 103 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 58,559 | $0.35 | $0.25 | $0.14 | $0.15 | $0.14 | $0.25 | $0.29 |
| 104 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 12,720 | $0.50 | $0.25 | $0.18 | $0.19 | $0.18 | $1.00 | $0.29 |
| 105 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 58,334 | $0.40 | $0.25 | $0.18 | $0.19 | $0.18 | $0.25 | $0.29 |
| 106 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 180 | $2.80 | $3.00 | $2.50 | $2.63 | $2.50 | $3.00 | $4.66 |
| 107 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 374 | $2.00 | $1.25 | $1.00 | $6.73 | $2.50 | $1.00 | $1.51 |
| 108 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 2,749 | $0.94 | $1.00 | $0.70 | $0.74 | $0.70 | $1.00 | $1.03 |
| 109 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 12 | $8.98 | $16.00 | $15.00 | $15.80 | $15.00 | $15.00 | $16.32 |
| 110 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 40 | $168.13 | $205.00 | $185.00 | $194.81 | $185.00 | $185.00 | $174.91 |
| 111 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 16 | $192.38 | $220.00 | $200.00 | $210.61 | $200.00 | $200.00 | $174.91 |
| 112 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 58,057 | $1.10 | $0.75 | $0.72 | $0.76 | $0.72 | $0.75 | $0.85 |
| 113 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 58,334 | $1.10 | $0.75 | $0.72 | $0.76 | $0.72 | $0.75 | $0.85 |
| 114 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 12,720 | $1.20 | $1.00 | $0.72 | $0.76 | $0.72 | $0.75 | $0.86 |
| 115 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 14,550 | $0.52 | $0.75 | $0.51 | $0.54 | $0.51 | $0.50 | $0.64 |
| 116 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 11,614 | $5.50 | $4.00 | $3.10 | $3.26 | $3.10 | $3.00 | $2.33 |
| 117 | Reflectorized pavement marker type I-C (672-7002) | EACH | 874 | $6.00 | $5.00 | $4.00 | $4.21 | $4.00 | $4.00 | $4.52 |
| 118 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,654 | $4.50 | $5.00 | $4.00 | $4.21 | $4.00 | $4.00 | $4.41 |
| 119 | Eliminating existing PM & markers (4") (677-7001) | LF | 9,744 | $0.60 | $1.00 | $0.44 | $0.46 | $0.44 | $0.50 | $0.82 |
| 120 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $70.00 | $105.00 | $95.00 | $100.04 | $95.00 | $95.00 | $69.96 |
| 121 | Bonding course (3007-7001) | GAL | 41,389 | $4.00 | $3.25 | $4.50 | $3.52 | $4.00 | $4.00 | $4.83 |
| 122 | Subsurface util locate (non-paved area) (5061-7001) | EACH | 10 | $1,805.00 | $2,000.00 | $975.00 | $4,000.00 | $750.00 | $3,619.00 | $580.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.