TxDOT contract A00123454 bid tabulation

Rehabilitate Existing Roadway, FM 1575 (FM 510 to SH 100). Let by Texas DOT on September 3, 2026, Cameron, Pharr District. 5 bids received; low bid $9,595,502 by Reim Construction, Inc., -15% against the engineer's estimate of $11,236,734.

Owner
Texas DOT
Letting
03 SEP 2026
Pay items
132
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Reim Construction, Inc.$9,595,502Low-15%
2Texas Cordia Construction, LLC$10,509,310+10%-6.0%
3Ioc Company LLC$11,172,180+16%-1.0%
4Foremost Paving, Inc.$11,423,679+19%+2.0%
5Go Underground, Limited Liability Company$11,594,684+21%+3.0%
TxDOT contract A00123454: bids by rank

Engineer's estimate: $11,236,734.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Reim Construction, Inc.2. Texas Cordia Construction, LLC3. Ioc Company LLC4. Foremost Paving, Inc.5. Go Underground, Limited Liability Company
1Preparing row (100-7002)STA211.50$2,500.00$685.00$2,700.00$2,750.00$2,500.00$1,000.00
2Removing concrete (riprap) (104-7006)SY92$20.00$13.00$14.00$50.00$127.08$12.00
3Removing concrete (driveways) (104-7011)SY1,807$20.00$12.15$10.00$15.00$27.76$12.00
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY1,004$15.00$10.85$15.00$15.00$13.07$12.00
5Removing concrete (curb & gutter) (104-7017)LF2,015$8.00$3.15$5.00$10.00$7.09$12.00
6Removing concrete (gutter) (104-7019)LF85$15.00$10.30$11.00$35.00$9.90$12.00
7Excavation (roadway) (110-7001)CY27,945$10.00$5.00$8.00$10.00$15.84$12.00
8Embankment (final)(DC)(type C) (132-7006)CY1,956$12.00$10.05$4.00$7.00$29.26$33.00
9Backfill (type A) (134-7001)STA211.50$280.00$175.00$350.00$150.00$256.48$150.00
10Furn & place topsoil (vehicle) (160-7007)CY50$75.00$24.00$50.00$10.00$30.01$93.00
11Hydro mulch seed (permanent_rural_clay) (164-7018)SY75,299$0.50$0.40$0.40$0.36$0.33$0.44
12Hydro mulch seed (temporary_warm) (164-7021)SY75,299$0.40$0.24$0.25$0.23$0.20$0.42
13Vegetative watering (168-7001)TGL1,266$20.00$31.80$2.00$28.00$42.51$34.63
14Sprinkling (dust control) (204-7001)TGL846$10.00$31.80$19.00$1.00$1.00$2.00
15FL BS (roadway del)(type E GR 4)(final pos) (247-7277)CY17,447$40.00$54.60$63.00$55.00$47.23$32.62
16Geogrid base reinforcement (type 2) (250-7002)SY97,708$1.50$1.50$3.00$1.50$1.56$1.00
17Rework BS metal (type B)(8")(DC)(org pos) (251-7036)CY22,522$5.00$7.65$3.00$8.50$6.85$5.00
18Lime (com or QK)(slurry) (260-7005)TON1,603$260.00$315.00$250.00$300.00$272.17$360.00
19Lime TRT (existing material)(12") (260-7009)SY107,835$3.00$2.05$3.00$1.00$4.85$4.00
20Cement (275-7001)TON1,350$190.00$190.00$226.00$175.00$186.51$140.00
21Cement TRT (existing material & new base)(14") (275-7027)SY102,749$2.50$2.80$2.00$1.00$5.83$3.00
22Salvage,haul & stockpile reclaimed asphalt PV (0 to 3") (305-7023)SY101,343$3.00$1.95$3.00$1.00$1.55$4.17
23Prime coat (MC-30) (310-7004)GAL19,543$6.00$6.20$5.00$5.75$6.73$10.00
24Asphalt (tier II) (316-7266)GAL29,314$6.00$4.30$5.00$4.50$6.98$7.00
25Aggregate (type-D GR-4P) (sac B) (316-7280)CY784$80.00$88.50$210.00$100.00$73.42$90.00
26SP mixes SP-D sac-A PG76-22 (344-7064)TON16,714$125.00$122.00$125.00$145.00$125.00$151.40
27Struct excavation (special) (400-7005)CY42$95.00$91.90$112.00$125.00$110.55$97.00
28Cut & restore asphalt paving (400-7008)SY262$100.00$81.75$95.00$130.00$105.53$90.00
29Cem stabil BKFL (400-7010)CY96$100.00$82.90$73.00$100.00$110.55$55.00
30Trench excavation protection (402-7001)LF192$10.00$2.55$12.00$0.10$1.01$2.00
31Riprap (concrete)(4 in) (432-7001)CY92$600.00$500.00$695.00$555.00$804.00$480.00
32RC pipe (CL III)(18 in) (464-7003)LF9,974$100.00$74.05$71.00$107.00$99.80$94.15
33RC pipe (CL III)(24 in) (464-7005)LF32$100.00$86.80$103.00$110.00$211.05$105.50
34RC pipe (CL IV)(18 in) (464-7019)LF288$125.00$79.35$128.00$105.00$216.08$99.82
35Inlet (stage II)(pco)(5FT)(none) (465-7340)EACH8$5,000.00$2,730.00$3,130.00$4,000.00$5,025.00$3,450.00
36Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH420$1,200.00$1,120.00$944.00$1,000.00$1,115.55$1,450.00
37Set (type II)(18 in)(RCP)(3:1)(P) (467-7467)EACH12$1,800.00$894.00$780.00$1,500.00$1,105.50$1,350.00
38Clean existing culverts (480-7001)EACH13$2,500.00$2,840.00$1,080.00$1,500.00$11,055$5,000.00
39Removing structure (inlet) (496-7002)EACH8$1,000.00$709.00$700.00$750.00$1,809.00$500.00
40Removing structure (set) (496-7004)EACH461$400.00$284.00$292.00$250.00$246.23$150.00
41Removing structure (pipe) (496-7007)LF8,535$15.00$13.10$6.00$15.00$20.10$4.00
42Mobilization (500-7001)LS1$1,021,521$700,000$849,725$1,000,000$628,000$732,000
43Barricades, signs and traffic handling (502-7001)MO22$5,000.00$4,650.00$800.00$3,500.00$4,000.00$3,200.00
44Portable changeable message sign (503-7002)EACH5$5,000.00$6,420.00$67.00$10,000$2,500.00$8,000.00
45TMA (stationary) (505-7001)DAY660$180.00$29.75$32.00$100.00$25.00$225.00
46TMA (mobile operation) (505-7003)DAY28$200.00$387.00$70.00$750.00$0.01$500.00
47Rock filter dams (install) (type 4) (506-7004)LF80$70.00$67.05$126.00$100.00$95.48$23.25
48Rock filter dams (remove) (506-7011)LF80$20.00$23.95$99.00$45.00$40.20$1.00
49Construction exits (install) (type 2) (506-7021)SY936$40.00$16.55$21.00$35.00$25.61$22.00
50Construction exits (remove) (506-7024)SY936$10.00$9.05$6.00$1.00$14.42$1.00
51Temporary sediment control fence (install) (506-7039)LF773$4.50$2.70$5.00$5.00$3.77$9.00
52Temporary sediment control fence (remove) (506-7041)LF773$1.20$1.10$1.00$3.00$2.17$1.00
53Biodegradable erosion control logs (install) (12") (506-7044)LF14,040$5.00$2.65$5.00$3.00$5.48$9.00
54Biodegradable erosion control logs (remove) (506-7046)LF14,040$1.00$1.00$1.00$0.10$0.91$1.00
55Concrete C&G (valley gutter) (529-7019)LF85$80.00$54.15$107.00$175.00$71.66$120.00
56Concrete curb & gutter (type A) (barrier) (529-7025)LF2,015$25.00$18.75$20.00$25.00$13.33$60.00
57Driveways (concrete) (530-7006)SY2,108$100.00$73.20$103.00$86.00$78.59$97.00
58Driveways (ACP) (530-7010)SY11,345$55.00$35.90$35.00$70.00$56.56$65.00
59Concrete sidewalks (4") (531-7001)SY924$60.00$44.10$66.00$85.00$51.55$85.00
60Curb ramps (type 1) (531-7005)EACH4$2,900.00$1,690.00$2,100.00$2,500.00$1,680.20$3,500.00
61Curb ramps (type 5) (531-7008)EACH4$3,500.00$2,080.00$2,340.00$2,500.00$1,680.20$3,500.00
62Curb ramps (type 10) (531-7011)EACH11$2,000.00$1,970.00$2,080.00$2,200.00$1,680.20$3,500.00
63Mailbox install-S (TWW-post) type 4 (560-7008)EACH169$320.00$328.00$519.00$300.00$301.50$332.31
64Mailbox install-D (TWW-post) type 4 (560-7009)EACH3$300.00$382.00$599.00$450.00$452.25$378.00
65Mailbox install-M (TWW-post) type 4 (560-7010)EACH7$1,000.00$628.00$978.00$550.00$552.75$621.00
66Conduit (PVC) (schedule 40) (1") (618-7021)LF30$15.00$18.60$20.00$19.75$17.09$19.44
67Conduit (PVC) (schedule 40) (2") (618-7030)LF255$10.00$34.95$13.00$13.17$32.16$12.96
68Conduit (PVC) (schedule 40) (4") (618-7040)LF450$20.00$38.25$22.00$21.94$35.18$21.60
69Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF340$40.00$49.15$42.00$41.69$45.23$41.04
70Electrical conductor (no.8) bare (620-7007)LF1,255$2.00$2.25$2.00$2.19$2.07$2.16
71Electrical conductor (no.6) bare (620-7009)LF130$2.00$2.45$3.00$2.74$2.27$2.70
72Electrical conductor (no.6) insulated (620-7010)LF260$2.00$2.80$3.00$3.07$2.57$3.02
73Tray cable (4 conductor) (12 AWG) (621-7006)LF2,563$3.00$3.70$4.00$3.84$3.42$3.78
74Ground box type A (122311)W/apron (624-7002)EACH7$1,000.00$1,530.00$1,090.00$1,091.69$1,407.00$1,074.60
75Ground box type D (162922)W/apron (624-7008)EACH1$1,500.00$1,970.00$2,030.00$2,029.78$1,809.00$1,998.00
76Zinc-coat steel wire strand (3/16") (625-7001)LF1,805$2.50$1.70$2.00$1.97$1.56$1.94
77Zinc-coat steel wire strand (5/16") (625-7003)LF4,915$4.00$1.95$2.00$2.41$1.81$2.38
78Aluminum signs (type A) (636-7001)SF54$35.00$38.25$18.00$45.00$38.19$37.80
79Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH50$750.00$819.00$856.00$850.00$854.25$810.00
80Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH11$1,000.00$929.00$973.00$1,100.00$1,105.50$918.00
81Relocate SM RD SN sup&AM type S80 (644-7067)EACH3$600.00$266.00$1,590.00$650.00$653.25$486.00
82Remove SM RD SN sup&AM (644-7073)EACH64$150.00$109.00$213.00$70.00$136.46$108.00
83Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH8$100.00$104.00$248.00$125.00$125.63$102.60
84Work zone pavement marking removing (W)6"(solid) (662-7068)LF46,960$0.75$0.86$0.34$0.34$0.35$1.16
85Work zone pavement marking removing (W)8"(solid) (662-7072)LF1,440$1.50$1.40$2.00$2.20$2.22$1.37
86Work zone pavement marking removing (W)24"(solid) (662-7077)LF182$8.00$13.10$7.00$6.50$6.54$12.96
87Work zone pavement marking removing (Y)6"(broken) (662-7098)LF630$1.50$1.30$1.00$1.10$1.11$1.26
88Work zone pavement marking removing (Y)6"(solid) (662-7100)LF49,879$0.75$0.86$0.35$0.34$0.35$0.84
89Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH2,126$1.00$1.45$6.00$1.70$1.31$0.41
90Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,046$1.00$1.50$6.00$1.80$1.31$0.42
91Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF299$1.00$1.00$2.00$2.20$2.22$0.96
92Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,046$5.00$8.20$6.00$5.50$5.53$8.10
93Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF460$0.55$0.85$1.00$1.10$1.11$0.83
94Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF38,905$0.45$0.75$1.00$0.66$0.67$0.72
95Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF4,520$0.55$0.85$1.00$0.88$0.89$0.83
96Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF13,792$0.45$0.75$1.00$0.76$0.77$0.72
97Prefabricated PM type C (W)(arrow) (668-7091)EACH3$200.00$328.00$175.00$175.00$175.88$324.00
98Prefabricated PM type C (W)(word) (668-7103)EACH3$200.00$54.65$275.00$275.00$276.38$378.00
99Reflectorized pavement marker type I-C (672-7002)EACH38$5.00$5.20$25.00$25.00$25.13$5.12
100Reflectorized pavement marker type II-A-A (672-7004)EACH569$5.00$5.20$8.00$7.50$7.54$5.13
101Traffic button type Y (672-7008)EACH2,187$3.00$4.25$3.00$2.50$2.52$4.18
102Traffic button type B (672-7009)EACH5,869$2.50$4.25$3.00$2.50$2.52$4.18
103Eliminating existing PM & markers (4") (677-7001)LF41,679$0.30$0.50$0.35$0.35$0.36$0.51
104Eliminating existing PM & markers (8") (677-7004)LF600$0.75$0.55$0.45$0.45$0.46$0.51
105Eliminating existing PM & markers (24") (677-7008)LF411$3.00$6.55$3.00$3.00$3.02$6.48
106Eliminating existing PM & markers (arrow) (677-7009)EACH3$50.00$219.00$50.00$50.00$50.25$216.00
107Eliminating existing PM & markers (word) (677-7015)EACH3$50.00$219.00$50.00$50.00$50.25$216.00
108Install highway traffic signal (flash beacon) (680-7001)EACH5$10,000$2,400.00$1,480.00$1,481.19$2,211.00$1,458.00
109Install highway traffic signal (isolated) (680-7002)EACH2$25,000$4,150.00$6,030.00$6,034.49$3,819.00$5,940.00
110Removing traffic signals (680-7004)EACH7$5,000.00$1,640.00$2,470.00$2,468.65$1,507.50$2,430.00
111Temporary traffic signals (681-7001)EACH2$10,000$5,350.00$4,660.00$4,663.01$4,924.50$4,590.00
112Vehicle signal section (12")LED(green) (682-7001)EACH16$325.00$382.00$371.00$370.85$351.75$365.04
113Vehicle signal section (12")LED(green arrow) (682-7002)EACH6$325.00$393.00$371.00$370.85$361.80$365.04
114Vehicle signal section (12")LED(yel) (682-7003)EACH36$325.00$382.00$371.00$370.85$351.75$365.04
115Vehicle signal section (12")LED(yel arrow) (682-7004)EACH12$325.00$393.00$371.00$370.85$361.80$365.04
116Vehicle signal section (12")LED(red) (682-7005)EACH34$325.00$382.00$371.00$370.85$351.75$365.04
117Vehicle signal section (12")LED(red arrow) (682-7006)EACH6$325.00$393.00$371.00$370.85$361.80$365.04
118Pedestrian signal section (LED)(countdown) (682-7018)EACH16$700.00$940.00$603.00$603.45$864.30$594.00
119Backplate W/reflectorized border(4 sec) (682-7037)EACH6$225.00$153.00$137.00$137.15$140.70$135.00
120Backplate W/reflectorized border(3 sec) (682-7054)EACH16$200.00$131.00$126.00$126.18$120.60$124.20
121Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF2,625$2.00$2.45$2.00$1.92$2.22$1.89
122Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF4,941$3.00$3.80$3.00$3.13$3.52$3.08
123Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF1,276$3.50$4.95$4.00$4.00$4.58$3.94
124Pedestrian pole assembly (687-7001)EACH9$2,000.00$3,170.00$3,020.00$3,017.24$2,914.50$2,970.00
125Pedestrian detect push button (APS) (688-7001)EACH16$1,000.00$1,090.00$1,030.00$1,031.35$1,005.00$1,015.20
126Pedestrian detector controller unit (688-7003)EACH2$4,000.00$4,480.00$3,570.00$3,565.84$4,120.50$3,510.00
127Removal of conduit (690-7001)LF1,420$4.00$3.90$4.00$4.39$3.57$4.32
128Removal of ground boxes (690-7006)EACH13$245.00$98.35$340.00$340.13$90.45$334.80
129Bonding course (3007-7001)GAL6,840$3.50$4.95$5.00$1.00$2.72$14.00
130HVDS W/FXD LNS (6017-7007)EACH8$6,900.00$8,190.00$10,040$10,039$7,537.50$9,882.00
131Video imaging and radar set-UP sys (6017-7016)EACH2$750.00$2,730.00$384.00$384.02$2,512.50$378.00
132Vid image and radar det processor sys (6017-7018)EACH2$15,000$10,300$16,290$16,293$9,447.00$16,038
TxDOT contract A00123454: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy