TxDOT contract A00186301 bid tabulation

Widen Road - Add Lanes, SL 121 (IH 14 to IH 35). Let by Texas DOT on October 6, 2026, Bell, Waco District. 6 bids received; low bid $22,052,184 by Big Creek Construction, LTD., -11% against the engineer's estimate of $24,664,269.

Owner
Texas DOT
Letting
06 OCT 2026
Pay items
169
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Big Creek Construction, LTD.$22,052,184Low-11%
2Patin Construction LLC$23,137,144+5.0%-6.0%
3James Construction Group, LLC$23,591,027+7.0%-4.0%
4Texas Materials Group, Inc.$23,644,285+7.0%-4.0%
5Jordan Foster Construction, LLC$24,381,341+11%-1.0%
6Joe Bland Construction LLC$25,178,796+14%+2.0%
TxDOT contract A00186301: bids by rank

Engineer's estimate: $24,664,269.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Big Creek Construction, LTD.2. Patin Construction LLC3. James Construction Group, LLC4. Texas Materials Group, Inc.5. Jordan Foster Construction, LLC6. Joe Bland Construction LLC
1Preparing row (100-7002)STA101$2,700.00$550.00$1,800.00$15,708$500.00$10,000$1,250.00
2Removing concrete (pavement) (104-7001)SY3,362$12.00$12.00$25.00$10.50$31.00$17.00$30.00
3Removing concrete (riprap) (104-7006)SY55$16.00$16.00$25.00$27.37$57.00$18.00$30.00
4Removing concrete (medians) (104-7008)SY370$14.50$20.00$25.00$17.54$19.00$7.80$35.00
5Removing concrete (driveways) (104-7011)SY3,753$17.55$15.00$22.00$14.12$25.00$16.00$35.00
6Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY223$22.00$18.00$25.00$25.41$41.00$11.00$40.00
7Removing concrete (curb) (104-7016)LF1,782$7.00$5.00$5.00$2.96$14.00$6.75$8.00
8Removing concrete (curb & gutter) (104-7017)LF341$8.00$8.00$5.00$15.82$18.00$12.30$8.00
9Removing concrete (miscellaneous) (104-7046)SY320$20.00$25.00$25.00$5.86$29.00$21.00$40.00
10Remove (13") TRT/untrt base & asphalt pavement (105-7033)SY4,365$4.40$8.25$7.00$6.45$4.00$9.35$6.00
11Remove (0"-9") TRT/untrt base & asphalt pavement (105-7049)SY51,385$10.00$5.00$7.00$2.14$2.70$4.20$5.00
12Excavation (roadway) (110-7001)CY21,125$12.45$18.00$10.00$18.50$12.00$8.00$12.00
13Embankment (final)(OC)(type C) (132-7005)CY33,581$21.00$18.00$34.00$12.34$15.00$20.00$40.00
14Furn & place topsoil (4") (160-7002)SY53,147$1.50$1.00$2.00$1.23$3.30$2.25$1.00
15Block sodding (162-7002)SY53,147$4.00$4.25$14.00$2.00$3.97$4.20$7.50
16Hydro mulch seed (temporary_warm) (164-7021)SY53,147$0.40$0.40$1.00$0.52$0.37$0.38$0.50
17Hydro mulch seed (temporary_cool) (164-7022)SY53,147$0.70$0.40$1.00$0.52$0.37$0.38$0.50
18Vegetative watering (168-7001)TGL1,294$10.00$25.00$25.00$32.26$38.00$43.00$60.00
19Soil ret BLKT(SL_steep_clay_short) (169-7005)SY1,113$5.00$1.60$3.00$1.10$1.45$2.00$1.50
20FL BS (compacted in place)(type D GR 5)(final pos) (247-7191)CY13,600$61.00$57.00$70.00$60.28$69.20$59.00$84.00
21Lime (com or QK)(slurry) (260-7005)TON1,600$310.00$350.00$380.00$443.05$340.00$350.00$405.00
22Lime TRT (subgrade) (8") (260-7020)SY81,571$6.00$4.30$8.00$5.44$8.00$5.00$14.00
23Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004)GAL97,880$6.15$5.25$2.50$3.01$4.20$4.25$11.00
24Fog seal (CSS-1H) (315-7004)GAL8,161$4.00$5.00$3.00$2.25$8.00$2.35$2.50
25Asphalt (CRS-2P) (316-7012)GAL45,074$5.00$4.00$4.00$3.00$4.30$3.10$3.50
26Aggregate (type-D or L, GR-4) (316-7253)CY559$200.00$120.00$280.00$245.00$221.00$250.00$280.00
27D-GR HMA type-B PG64-22 (341-7001)TON13,060$88.00$90.00$103.00$90.00$132.00$94.00$98.00
28Tack coat (341-7082)GAL7,572$4.00$3.60$5.00$3.75$3.30$3.95$4.25
29SP mixes SP-C sac-A PG70-22 (344-7020)TON8,642$140.00$110.00$130.00$112.00$165.00$115.00$128.00
30Concrete pavement (CRCP) (12") (360-7006)SY831$100.00$140.00$125.00$172.11$132.00$180.00$180.00
31Concrete pavement(transition slab) (12") (360-7035)SY128$225.00$245.00$125.00$210.48$296.00$230.00$190.00
32Cem stabil BKFL (400-7010)CY7,572$180.00$155.00$250.00$154.92$200.00$154.00$168.00
33Cement stab backfill (inlet or MH) (400-7011)CY396$110.00$195.00$250.00$154.92$200.00$195.00$175.00
34Trench excavation protection (402-7001)LF14,187$6.00$10.00$5.00$1.84$1.00$3.40$5.00
35Temporary special shoring (403-7001)SF4,460$22.00$30.00$40.00$19.01$28.00$45.00$20.00
36Drilled shaft (30 in) (416-7005)LF400$300.00$800.00$350.00$726.87$293.00$785.00$385.00
37Riprap (concrete)(4 in) (432-7001)CY1,178$531.00$610.00$500.00$457.62$595.00$735.00$500.00
38Riprap (concrete)(CL B) (432-7005)CY17.50$620.00$830.00$500.00$1,063.06$630.00$800.00$715.00
39Riprap (concrete)(CL B)(5 in) (432-7008)CY120$800.00$630.00$600.00$654.84$630.00$630.00$495.00
40Riprap (stone common)(dry)(18 in) (432-7033)CY10$200.00$250.00$250.00$252.33$350.00$350.00$225.00
41Riprap (stone common)(dry)(24 in) (432-7034)CY198$205.00$165.00$300.00$190.99$227.00$180.00$175.00
42Rail (handrail)(type F) (450-7063)LF1,255$130.00$190.00$185.00$180.31$146.00$185.00$180.00
43Concrete box culvert (5 FT X 4 FT) (462-7008)LF139$602.00$445.00$550.00$529.97$498.00$620.00$740.00
44Concrete box culvert (8 FT X 5 FT) (462-7022)LF20$850.00$885.00$950.00$1,009.10$866.00$1,100.00$1,295.00
45RC pipe (CL III)(18 in) (464-7003)LF2,223$100.00$75.00$70.00$116.58$59.00$92.00$100.00
46RC pipe (CL III)(24 in) (464-7005)LF8,548$100.00$90.00$90.00$138.34$76.00$105.00$120.00
47RC pipe (CL III)(30 in) (464-7007)LF766$140.00$120.00$110.00$153.65$109.00$135.00$150.00
48RC pipe (CL III)(36 in) (464-7009)LF1,625$175.00$165.00$150.00$197.33$162.00$240.00$195.00
49RC pipe (CL III)(42 in) (464-7010)LF826$190.00$222.00$200.00$255.36$228.00$215.00$250.00
50RC pipe (CL III)(48 in) (464-7011)LF403$230.00$254.00$250.00$302.19$289.00$285.00$300.00
51Manh (complete)(PRM)(48IN) (465-7002)EACH7$8,683.00$5,825.00$7,000.00$7,045.24$5,722.00$9,200.00$10,000
52Junction box(complete)(PJB)(3FTX3FT) (465-7005)EACH1$6,493.00$4,500.00$6,000.00$9,453.08$5,056.00$7,800.00$8,500.00
53Inlet (complete)(pco)(5FT)(left) (465-7022)EACH53$12,404$10,510$8,000.00$12,655$7,335.00$9,700.00$7,750.00
54Inlet (complete)(pco)(5FT)(right) (465-7023)EACH41$12,404$10,690$8,000.00$12,867$7,329.00$9,700.00$7,750.00
55Inlet (complete)(pazd)(RC)(3FTX3FT) (465-7152)EACH1$5,793.00$5,750.00$6,000.00$8,579.12$4,012.00$6,300.00$5,750.00
56Inlet (complete)(pazd)(RC)(4FTX4FT) (465-7153)EACH2$7,955.00$6,500.00$6,000.00$9,382.43$3,612.00$7,400.00$8,000.00
57Junction box (complete)(11FT X 6FT) (465-7379)EACH1$40,000$23,500$33,000$36,027$31,562$20,000$35,000
58Headwall (CH - FW - 0) (diameter= 30 in) (466-7007)EACH1$7,000.00$7,825.00$4,500.00$10,791$6,000.00$11,000$7,500.00
59Headwall (CH - FW - 0) (diameter= 48 in) (466-7011)EACH2$12,030$9,830.00$5,500.00$16,695$13,000$17,000$5,750.00
60Headwall (CH - FW - 15) (diameter= 48 in) (466-7026)EACH2$15,500$9,125.00$5,500.00$11,687$11,200$21,000$6,750.00
61Headwall (CH - FW - A - 0) (des= 3) (466-7063)EACH1$850.00$8,575.00$5,500.00$10,935$14,300$16,000$7,750.00
62Headwall (CH - PW - S) (diameter= 30 in) (466-7118)EACH1$13,000$8,750.00$4,500.00$11,246$9,700.00$12,000$7,750.00
63Headwall (CH - PW - S) (diameter= 42 in) (466-7121)EACH2$1,400.00$12,500$5,500.00$19,405$15,000$23,000$9,500.00
64Wingwall (FW - 0) (HW=6 FT) (466-7148)EACH1$14,000$13,400$15,000$11,898$12,900$32,000$12,250
65Wingwall (FW - 0) (HW=7 FT) (466-7149)EACH1$22,113$19,325$17,000$17,746$18,250$37,000$17,750
66Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH5$1,174.00$1,200.00$2,500.00$2,041.44$1,158.00$2,200.00$3,500.00
67Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH1$2,138.00$1,390.00$3,000.00$1,852.82$1,107.00$3,200.00$4,000.00
68Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH1$3,311.00$1,620.00$3,000.00$2,153.23$1,107.00$3,300.00$4,500.00
69Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH11$1,699.00$1,620.00$3,000.00$2,151.55$1,107.00$3,300.00$4,500.00
70Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH2$2,842.00$2,700.00$3,500.00$5,123.35$2,993.00$3,500.00$6,500.00
71Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347)EACH3$4,445.00$3,300.00$3,500.00$5,853.86$3,210.00$3,700.00$7,500.00
72Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH2$3,166.00$2,750.00$3,500.00$6,227.32$3,745.00$3,700.00$7,500.00
73Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365)EACH1$3,940.00$3,350.00$4,000.00$5,644.31$4,100.00$4,700.00$7,500.00
74Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367)EACH1$7,372.00$4,630.00$4,000.00$7,171.96$4,943.00$7,300.00$10,500
75Set (type II) (42 in) (RCP) (6: 1) (C) (467-7379)EACH2$7,000.00$6,200.00$5,000.00$7,500.09$10,800$15,000$13,150
76Set (removing & reinstall) (467-7472)EACH8$390.00$1,000.00$1,500.00$1,512.13$675.00$3,000.00$2,250.00
77Removing & RE - lay pipe (15 in) (472-7003)LF86$100.00$60.00$80.00$70.10$43.00$126.00$150.00
78Removing & RE - lay pipe (18 in) (472-7004)LF210$41.00$60.00$80.00$57.41$50.00$88.00$150.00
79Removing & RE - lay pipe (24 in) (472-7006)LF58$81.00$67.00$80.00$103.93$70.00$125.00$150.00
80Cast-in-place trench drain (474-7021)LF40$213.00$600.00$150.00$446.78$387.00$800.00$750.00
81Adjusting manholes (479-7001)EACH6$1,600.00$2,200.00$500.00$2,152.08$1,800.00$2,300.00$1,250.00
82Removing structure (inlet) (496-7002)EACH2$1,121.65$1,280.00$1,500.00$1,060.29$700.00$940.00$1,625.00
83Removing structure (set) (496-7004)EACH52$457.00$325.00$500.00$903.27$170.00$500.00$1,025.00
84Removing structure (headwall) (496-7006)EACH1$1,126.25$1,500.00$1,500.00$4,224.84$1,000.00$3,900.00$1,625.00
85Removing structure (pipe) (496-7007)LF3,267$12.00$17.50$40.00$24.11$8.00$12.00$50.00
86Mobilization (500-7001)LS1$2,244,429$2,100,000$200,000$2,353,364$2,360,000$2,422,892$1,050,000
87Barricades, signs and traffic handling (502-7001)MO36$12,000$3,100.00$2,500.00$6,635.69$2,500.00$10,000$1,750.00
88Portable changeable message sign (503-7002)EACH2$7,264.00$8,500.00$60,000$16,830$20,000$20,000$8,750.00
89TMA (stationary) (505-7001)DAY50$260.00$200.00$300.00$350.31$170.00$550.00$215.00
90TMA (mobile operation) (505-7002)HR384$60.00$100.00$200.00$175.31$14.00$120.00$145.00
91Rock filter dams (install) (type 2) (506-7002)LF640$51.00$40.00$60.00$38.00$45.00$47.00$40.00
92Rock filter dams (remove) (506-7011)LF640$18.00$6.00$10.00$10.00$20.00$21.00$15.00
93Construction exits (install) (type 2) (506-7021)SY446$30.00$70.00$10.00$45.00$45.00$47.00$115.00
94Construction exits (remove) (506-7024)SY446$10.00$9.00$5.00$20.00$20.00$21.00$30.00
95Temporary sediment control fence (install) (506-7039)LF9,041$3.00$3.30$4.00$3.75$3.59$3.75$5.00
96Temporary sediment control fence (remove) (506-7041)LF9,041$1.00$1.00$1.00$1.00$1.00$1.05$2.00
97Biodegradable erosion control logs (install) (12") (506-7044)LF1,335$4.50$5.50$7.00$5.25$8.50$8.95$8.00
98Biodegradable erosion control logs (remove) (506-7046)LF1,335$1.00$1.00$2.00$1.00$2.00$2.10$2.00
99Constructing detours (508-7001)SY28,268$93.00$58.00$41.00$48.62$65.00$50.00$52.00
100One-way traffic control (port traffic signal) (510-7003)MO3$4,500.00$4,500.00$8,000.00$10,000$9,000.00$5,700.00$7,500.00
101Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021)LF14,460$14.00$10.00$35.00$9.33$16.00$13.65$20.00
102Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022)LF920$20.00$10.00$70.00$13.35$26.00$54.00$10.00
103Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF16,900$7.00$4.00$10.00$6.40$12.50$5.40$15.00
104Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF1,480$7.00$4.00$10.00$7.90$22.00$14.35$15.00
105Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045)LF14,460$11.00$9.25$10.00$6.88$13.50$8.00$20.00
106Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046)LF920$21.00$9.25$10.00$6.88$13.00$13.50$20.00
107Concrete curb & gutter (type II) (529-7009)LF20,150$34.00$27.00$20.00$24.75$32.00$20.85$22.00
108Concrete curb (dowel)(mod) (529-7034)LF17,689$28.00$25.00$25.00$10.69$7.00$35.80$24.00
109Driveways (concrete) (530-7006)SY2,926$105.00$102.00$120.00$102.69$100.00$122.00$130.00
110Driveways (ACP) (530-7010)SY2,892$41.00$50.00$55.00$58.52$75.30$77.00$60.00
111Concrete sidewalks (5") (531-7002)SY15,884$67.00$74.00$74.00$74.73$71.35$78.00$63.00
112Curb ramps (type 1) (531-7005)EACH1$2,800.00$2,550.00$2,500.00$3,192.18$2,200.00$3,300.00$2,000.00
113Curb ramps (type 2) (531-7006)EACH3$2,800.00$2,900.00$2,500.00$3,525.16$2,400.00$3,400.00$2,000.00
114Curb ramps (type 7) (531-7010)EACH8$3,000.00$2,625.00$2,500.00$3,525.16$2,300.00$3,500.00$2,750.00
115Curb ramps (type 10) (531-7011)EACH4$2,800.00$2,300.00$2,500.00$3,525.17$2,100.00$2,300.00$2,750.00
116Curb ramps (type 21) (531-7013)EACH1$3,500.00$500.00$2,500.00$3,525.22$4,300.00$3,500.00$1,750.00
117Curb ramps (type 22) (531-7014)EACH2$5,000.00$500.00$2,500.00$5,842.76$4,800.00$3,500.00$5,500.00
118Concrete median (536-7002)SY55$73.00$140.00$100.00$68.13$92.00$220.00$115.00
119Concrete directional island (12") (536-7007)LF100$95.00$150.00$50.00$98.86$132.00$205.00$300.00
120Relocate existing mailbox (560-7012)EACH8$283.00$240.00$500.00$289.00$350.00$470.00$825.00
121In RD IL (type SA) 40T-12 (250W EQ) LED (610-7128)EACH50$5,360.00$6,200.00$5,500.00$5,656.00$5,020.00$6,100.00$5,900.00
122Conduit (PVC) (schedule 40) (2") (618-7030)LF4,925$13.00$15.00$15.00$13.64$17.50$14.50$14.00
123Conduit (PVC) (schedule 40) (3") (618-7036)LF13,390$15.00$12.00$15.00$10.50$9.65$11.25$15.00
124Conduit (PVC) (schedule 40) (3") (concrete encse) (618-7038)LF3,068$22.00$18.50$20.00$16.75$17.10$18.00$19.00
125Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF2,705$15.00$27.50$35.00$25.00$52.60$27.00$35.00
126Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF6,086$30.00$28.50$60.00$26.00$41.95$28.00$38.00
127ITS multi-duct CND (PVC-40) (619-7001)LF13,290$25.00$19.25$40.00$17.50$20.55$19.00$40.00
128ITS multi-duct CND (PVC-40)(concrete encse) (619-7003)LF3,068$20.00$26.75$50.00$24.25$29.10$26.00$50.00
129ITS multi-duct CND (PVC-80)(bore) (619-7006)LF6,086$47.00$38.50$58.00$35.00$55.50$37.00$58.00
130Fiber optic cable road marker (619-7013)LF35$216.00$46.00$200.00$42.00$172.75$46.00$180.00
131Electrical conductor (no.14) insulated (620-7002)LF11,407$1.00$1.65$2.00$1.50$2.40$1.65$1.50
132Electrical conductor (no.12) bare (620-7003)LF7,760$2.00$1.45$2.00$1.30$2.52$1.40$1.75
133Electrical conductor (no.12) insulated (620-7004)LF15,520$2.00$1.95$2.00$1.75$2.52$2.00$2.00
134ITS GND box(pcast) type 1 (243636)W/aprn (623-7002)EACH33$4,700.00$5,700.00$5,500.00$5,167.00$5,161.00$5,590.00$5,650.00
135ITS GND box(pcast) type 2 (366060)W/aprn (623-7012)EACH2$12,300$8,500.00$8,500.00$7,702.00$8,387.00$8,400.00$8,825.00
136Ground box type A (122311)W/apron (624-7002)EACH31$1,304.00$1,700.00$1,500.00$1,545.00$2,468.00$1,675.00$1,425.00
137Elc SRV type A 120/240 060(NS)SS(E)SP(U) (628-7010)EACH6$9,600.00$8,800.00$10,000$8,004.00$14,510$8,665.00$9,250.00
138Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH32$650.00$715.00$1,000.00$647.00$647.33$680.00$750.00
139Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH2$750.00$825.00$1,000.00$750.00$750.00$800.00$875.00
140Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033)EACH1$1,450.00$935.00$1,100.00$850.00$850.00$900.00$995.00
141Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040)EACH2$1,000.00$950.00$1,100.00$866.00$866.00$915.00$1,015.00
142Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH12$800.00$500.00$700.00$450.00$450.00$475.00$525.00
143Relocate SM RD SN sup&AM type S80 (644-7067)EACH1$700.00$500.00$700.00$450.00$450.00$475.00$525.00
144Remove SM RD SN sup&AM (644-7073)EACH36$110.00$100.00$125.00$90.00$90.00$95.00$105.00
145Relocate lrsa (647-7002)EACH1$5,000.00$6,500.00$10,000$8,200.00$8,200.00$10,500$9,775.00
146Work zone pavement marking removing (reflectorized) type I-C (662-7049)EACH2,267$6.00$5.00$5.00$4.50$3.11$4.75$4.00
147Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH758$5.00$5.00$5.00$4.50$3.03$4.75$3.50
148Work zone pavement marking removing (W)6"(broken) (662-7065)LF333$1.00$1.10$1.00$1.00$0.87$1.05$1.00
149Work zone pavement marking removing (W)6"(solid) (662-7068)LF67,232$1.00$0.55$1.00$0.50$0.60$0.55$1.00
150Work zone pavement marking removing (Y)6"(broken) (662-7098)LF85$1.00$1.10$1.00$1.00$0.77$1.10$1.00
151Work zone pavement marking removing (Y)6"(solid) (662-7100)LF30,176$1.00$0.55$1.00$0.50$0.60$0.52$1.00
152Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF1,944$1.00$1.10$2.00$1.00$1.11$1.05$1.25
153Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF6,285$1.00$0.85$2.00$0.78$0.99$0.85$1.25
154Reflectorized pavement marking type I (W)18"(solid)(100MIL) (666-7033)LF100$6.00$1.65$7.00$1.50$5.75$1.60$6.50
155Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF589$6.00$12.75$10.00$12.00$7.01$12.60$8.25
156Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH13$36.00$60.00$50.00$55.00$35.00$57.00$40.00
157Type I high perf PM (W)6"(broken)(100MIL) (666-7290)LF1,974$0.65$0.75$1.00$0.68$0.80$0.70$1.00
158Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF18,621$1.00$0.75$1.00$0.66$0.71$0.70$1.00
159Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF18,717$1.00$0.75$1.00$0.66$0.73$0.70$1.00
160Prefabricated PM type C (W)(arrow) (668-7091)EACH58$180.00$240.00$500.00$220.00$275.00$230.00$325.00
161Prefabricated PM type C (W)(word) (668-7103)EACH49$230.00$300.00$500.00$275.00$300.00$285.00$350.00
162Reflectorized pavement marker type II-A-A (672-7004)EACH406$5.00$8.50$7.00$8.00$5.67$8.40$6.50
163Reflectorized pavement marker type II-C-R (672-7006)EACH93$4.00$7.00$10.00$6.00$6.11$6.85$7.00
164Full - width mowing (730-7019)CYC6$3,200.00$4,100.00$1,500.00$4,200.00$1,900.00$3,500.00$4,000.00
165Tree trimming / brush removal (752-7001)MI1.95$1,715.00$18,750$10,000$5,000.00$9,000.00$4,000.00$10,250
166System integration (6009-7001)LS1$26,835$12,880$62,000$11,713$83,420$12,600$64,500
167Fiber optic fusion splice (6027-7004)EACH576$67.00$71.00$60.00$65.00$69.45$70.00$60.00
168Fiber optic CBL(single-mode)(144 fiber) (6027-7006)LF25,498$4.00$9.75$6.00$8.90$5.11$9.60$6.00
169Fiber optic patch panel (144 positions) (6027-7008)EACH2$3,000.00$3,000.00$7,500.00$2,748.00$7,240.00$3,400.00$7,750.00
TxDOT contract A00186301: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy