TxDOT contract A00193114 bid tabulation
Hazard Elimination & Safety, FM 491 (0.77 Miles North of FM 2629 to West Uncle Peter's Rd.). Let by Texas DOT on June 2, 2026, Hidalgo, Pharr District. 7 bids received; low bid $7,675,891 by Foremost Paving, Inc., -11% against the engineer's estimate of $8,600,027.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 126
- Data through
- 19 NOV 2026
6 of the 7 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foremost Paving, Inc. | $7,675,891 | Low | -11% |
| 3 | Texas Cordia Construction, LLC | $8,458,004 | +10% | -2.0% |
| 4 | Reim Construction, Inc. | $8,635,762 | +13% | 0.0% |
| 5 | CK Newberry, LLC | $9,244,602 | +20% | +7.0% |
| 6 | Earthworks Enterprise | $9,286,974 | +21% | +8.0% |
| 7 | 3LW Civil LLC | $9,743,826 | +27% | +13% |
Engineer's estimate: $8,600,027.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foremost Paving, Inc. | 2. Texas Cordia Construction, LLC | 3. Reim Construction, Inc. | 4. CK Newberry, LLC | 5. Earthworks Enterprise | 6. 3LW Civil LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 160 | $1,500.00 | $2,000.00 | $2,000.00 | $3,250.00 | $300.00 | $425.00 | $1,766.61 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 38 | $23.47 | $30.00 | $23.15 | $100.00 | $13.50 | $23.16 | |
| 3 | Remove (4") TRT/untrt base & asphalt pavement (105-7024) | SY | 37,354 | $12.00 | $0.32 | $4.00 | $3.10 | $2.25 | $3.75 | $1.07 |
| 4 | Obliterating abandoned road (106-7002) | SY | 5,167 | $4.00 | $2.15 | $2.00 | $4.30 | $2.25 | $5.50 | $4.68 |
| 5 | Excavation (roadway) (110-7001) | CY | 5,257 | $7.00 | $18.72 | $2.00 | $8.65 | $12.00 | $14.00 | $12.00 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 30,703 | $5.92 | $18.20 | $12.00 | $15.50 | $22.00 | $18.00 | $26.83 |
| 7 | Backfill (type A) (134-7001) | STA | 160 | $328.16 | $152.56 | $180.00 | $262.00 | $125.00 | $156.00 | $61.03 |
| 8 | Furn & place topsoil (vehicle) (160-7007) | CY | 50 | $32.50 | $28.29 | $50.00 | $43.25 | $55.00 | $35.00 | $110.43 |
| 9 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 69,321 | $0.45 | $0.45 | $0.50 | $0.50 | $0.55 | $0.75 | $0.67 |
| 10 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 69,321 | $0.40 | $0.28 | $0.50 | $0.31 | $0.50 | $0.75 | $0.65 |
| 11 | Vegetative watering (168-7001) | TGL | 1,509 | $30.31 | $59.59 | $25.00 | $31.60 | $25.00 | $9.00 | $83.30 |
| 12 | Sprinkling (dust control) (204-7001) | TGL | 637 | $10.19 | $1.00 | $30.00 | $31.60 | $30.00 | $9.00 | $51.37 |
| 13 | Proof rolling (216-7001) | HR | 12.81 | $40.25 | $89.22 | $50.00 | $59.70 | $80.00 | $93.00 | $49.22 |
| 14 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 17,182 | $55.00 | $31.48 | $55.00 | $38.65 | $42.00 | $53.00 | $53.69 |
| 15 | Lime (com or QK)(slurry) (260-7005) | TON | 1,288 | $215.50 | $250.71 | $300.00 | $337.00 | $350.00 | $386.00 | $341.02 |
| 16 | Lime TRT (existing material)(12") (260-7009) | SY | 65,053 | $3.25 | $3.26 | $3.00 | $2.00 | $3.50 | $4.25 | $3.52 |
| 17 | Cement (275-7001) | TON | 578 | $190.00 | $177.21 | $200.00 | $206.00 | $200.00 | $213.00 | $231.47 |
| 18 | Cement TRT (new base)(10") (275-7012) | SY | 61,851 | $2.50 | $3.79 | $3.00 | $1.90 | $2.00 | $3.00 | $3.18 |
| 19 | Salvage,haul & stockpile reclaimed asphalt PV (1 to 3") (305-7034) | SY | 34,905 | $3.50 | $1.34 | $5.00 | $3.35 | $1.50 | $2.75 | $5.66 |
| 20 | Prime coat (MC-30) (310-7004) | GAL | 12,081 | $6.26 | $6.38 | $8.00 | $7.00 | $6.50 | $7.15 | $9.52 |
| 21 | Asphalt (tier II) (316-7266) | GAL | 17,595 | $5.29 | $6.82 | $7.00 | $4.30 | $4.75 | $6.00 | $9.69 |
| 22 | Aggregate (type-D GR-4P) (sac B) (316-7280) | CY | 467 | $186.10 | $74.99 | $170.00 | $87.75 | $175.00 | $159.25 | $211.74 |
| 23 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 10,310 | $124.10 | $113.86 | $130.00 | $140.00 | $145.00 | $152.25 | $140.84 |
| 24 | Plane & text asphalt concrete pavement(1.5") (354-7018) | SY | 2,909 | $4.31 | $4.11 | $5.00 | $2.25 | $5.00 | $1.75 | $2.76 |
| 25 | Struct excavation (special) (400-7005) | CY | 152 | $86.25 | $95.95 | $90.00 | $84.30 | $150.00 | $106.75 | $103.41 |
| 26 | Cut & restore asphalt paving (400-7008) | SY | 152 | $70.42 | $101.00 | $120.00 | $70.00 | $55.00 | $38.00 | $122.04 |
| 27 | Cem stabil BKFL (400-7010) | CY | 309 | $68.91 | $80.80 | $300.00 | $76.45 | $200.00 | $81.25 | $191.35 |
| 28 | Trench excavation protection (402-7001) | LF | 409 | $4.25 | $1.01 | $20.00 | $3.75 | $15.00 | $2.50 | $5.95 |
| 29 | Temporary special shoring (403-7001) | SF | 3,750 | $10.00 | $0.01 | $30.00 | $68.30 | $30.00 | $98.00 | $7.51 |
| 30 | Sheet piling (PZ - 27) (407-7002) | SF | 6,556 | $71.95 | $52.00 | $70.00 | $83.00 | $85.00 | $111.25 | $81.43 |
| 31 | Drilled shaft (24 in) (416-7004) | LF | 1,360 | $259.65 | $404.00 | $330.00 | $493.00 | $375.00 | $408.25 | $462.37 |
| 32 | Class C concrete (abutment) (420-7012) | CY | 22.60 | $1,743.60 | $2,828.00 | $1,190.00 | $1,300.00 | $1,500.00 | $2,136.00 | $1,409.46 |
| 33 | Class C concrete (cap) (420-7022) | CY | 34.40 | $2,139.50 | $4,646.00 | $2,300.00 | $1,860.00 | $3,000.00 | $4,786.00 | $1,425.91 |
| 34 | Class C concrete (column) (420-7038) | CY | 13.90 | $1,459.45 | $5,050.00 | $2,010.00 | $3,260.00 | $5,000.00 | $2,121.00 | $1,320.72 |
| 35 | Reinforced concrete slab (slab beam) (422-7007) | SF | 5,851 | $56.00 | $23.23 | $50.00 | $27.10 | $25.00 | $32.75 | $21.54 |
| 36 | Prestressed concrete slab beam (4SB12) (425-7016) | LF | 1,005 | $350.00 | $272.70 | $330.00 | $236.00 | $275.00 | $280.25 | $199.60 |
| 37 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 335 | $245.76 | $272.70 | $340.00 | $236.00 | $300.00 | $284.75 | $230.78 |
| 38 | Riprap (concrete)(4 in) (432-7001) | CY | 164 | $550.00 | $409.05 | $650.00 | $462.00 | $675.00 | $391.00 | $566.55 |
| 39 | Riprap (mow strip)(4 in) (432-7013) | CY | 69 | $735.03 | $419.15 | $760.00 | $671.00 | $650.00 | $391.00 | $654.01 |
| 40 | Riprap (stone protection)(15 in) (432-7042) | CY | 32 | $190.92 | $328.25 | $280.00 | $303.00 | $450.00 | $194.50 | $328.93 |
| 41 | Elastomeric bearing (plain) (434-7001) | EACH | 120 | $1,400.00 | $1.01 | $470.00 | $276.00 | $35.00 | $100.00 | $0.01 |
| 42 | Rail (type T223) (450-7008) | LF | 364 | $146.15 | $191.90 | $500.00 | $176.00 | $200.00 | $202.00 | $142.91 |
| 43 | Armor joint (sealed) (454-7003) | LF | 67 | $154.32 | $303.00 | $140.00 | $173.00 | $175.00 | $195.00 | $198.12 |
| 44 | RC pipe (CL III)(18 in) (464-7003) | LF | 0 | $100.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 45 | RC pipe (CL III)(24 in) (464-7005) | LF | 0 | $160.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 46 | RC pipe (CL III)(36 in) (464-7009) | LF | 36 | $212.45 | $363.60 | $220.00 | $199.00 | $220.00 | $211.00 | $294.73 |
| 47 | RC pipe (CL IV)(18 in) (464-7019) | LF | 342 | $150.00 | $212.10 | $90.00 | $83.10 | $105.00 | $85.50 | $164.35 |
| 48 | RC pipe (CL IV)(24 in) (464-7021) | LF | 208 | $170.00 | $242.40 | $130.00 | $119.00 | $150.00 | $119.75 | $163.08 |
| 49 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 18 | $1,500.00 | $909.00 | $1,230.00 | $934.00 | $2,200.00 | $1,008.00 | $1,005.23 |
| 50 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 31 | $1,000.00 | $1,111.00 | $1,360.00 | $1,200.00 | $2,200.00 | $1,123.00 | $1,148.89 |
| 51 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 5 | $1,500.00 | $1,161.50 | $1,560.00 | $1,220.00 | $2,500.00 | $1,295.00 | $1,222.17 |
| 52 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 5 | $2,000.00 | $1,191.80 | $1,560.00 | $1,220.00 | $2,500.00 | $1,295.00 | $1,275.30 |
| 53 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 10 | $1,849.24 | $1,616.00 | $1,760.00 | $1,390.00 | $2,800.00 | $1,467.00 | $1,624.69 |
| 54 | Set (type II) (18") (RCP) (4:1) (P) (467-7474) | EACH | 1 | $1,350.00 | $1,010.00 | $1,230.00 | $867.00 | $3,400.00 | $1,008.00 | $2,582.99 |
| 55 | Removing structure (set) (496-7004) | EACH | 40 | $437.54 | $404.00 | $360.00 | $246.00 | $500.00 | $167.75 | $290.42 |
| 56 | Removing structure (pipe) (496-7007) | LF | 960 | $13.80 | $30.30 | $10.00 | $11.85 | $15.00 | $12.25 | $19.32 |
| 57 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $90,000 | $118,170 | $99,460 | $125,000 | $325,000 | $123,000 | $227,237 |
| 58 | Mobilization (500-7001) | LS | 1 | $778,645 | $500,000 | $361,500 | $750,000 | $925,000 | $450,000 | $883,530 |
| 59 | Barricades, signs and traffic handling (502-7001) | MO | 17 | $2,350.00 | $7,300.00 | $500.00 | $2,940.00 | $12,000 | $3,255.00 | $2,833.99 |
| 60 | Portable changeable message sign (503-7002) | EACH | 4 | $10,000 | $8,145.87 | $70.00 | $5,750.00 | $15,000 | $31,206 | $4,760.00 |
| 61 | TMA (stationary) (505-7001) | DAY | 253 | $109.83 | $35.89 | $70.00 | $28.70 | $250.00 | $207.00 | $260.47 |
| 62 | TMA (mobile operation) (505-7003) | DAY | 253 | $196.64 | $0.01 | $70.00 | $115.00 | $25.00 | $303.00 | $416.67 |
| 63 | Rock filter dams (install) (type 2) (506-7002) | LF | 56 | $52.02 | $90.90 | $120.00 | $65.10 | $100.00 | $97.50 | $119.00 |
| 64 | Rock filter dams (remove) (506-7011) | LF | 56 | $20.29 | $48.23 | $90.00 | $22.25 | $50.00 | $46.00 | $53.55 |
| 65 | Construction exits (install) (type 2) (506-7021) | SY | 468 | $27.44 | $22.18 | $20.00 | $15.00 | $25.00 | $7.75 | $65.45 |
| 66 | Construction exits (remove) (506-7024) | SY | 468 | $2.85 | $13.76 | $9.00 | $7.75 | $10.00 | $2.25 | $23.80 |
| 67 | FRNT end loader work (ersn & sedm cont) (506-7031) | HR | 24 | $150.00 | $95.86 | $200.00 | $63.00 | $125.00 | $91.50 | $79.73 |
| 68 | Temporary sediment control fence (install) (506-7039) | LF | 678 | $6.28 | $3.29 | $4.00 | $3.85 | $5.00 | $5.00 | $7.14 |
| 69 | Temporary sediment control fence (remove) (506-7041) | LF | 678 | $2.59 | $2.38 | $1.00 | $1.00 | $2.00 | $1.50 | $3.57 |
| 70 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,181 | $5.50 | $5.61 | $6.00 | $3.20 | $8.00 | $7.25 | $9.52 |
| 71 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,181 | $1.29 | $1.17 | $1.00 | $1.00 | $2.00 | $1.50 | $2.38 |
| 72 | Driveways (concrete) (530-7006) | SY | 249 | $94.86 | $110.00 | $69.80 | $150.00 | $69.00 | $81.49 | |
| 73 | Driveways (ACP) (530-7010) | SY | 1,232 | $63.96 | $51.10 | $40.00 | $46.90 | $60.00 | $27.50 | $74.06 |
| 74 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 31,738 | $0.19 | $0.14 | $0.25 | $0.18 | $0.15 | $0.25 | $0.18 |
| 75 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 15,319 | $0.23 | $0.20 | $0.25 | $0.24 | $0.25 | $0.25 | $0.25 |
| 76 | Metal W-beam guard fence (timber post) (540-7001) | LF | 576 | $32.17 | $29.40 | $30.00 | $34.00 | $33.00 | $34.50 | $31.92 |
| 77 | Remove metal beam guard fence (542-7001) | LF | 633 | $6.79 | $3.03 | $4.00 | $3.00 | $3.00 | $3.50 | $4.78 |
| 78 | RM metal beam guard fence trans (T101) (542-7005) | EACH | 4 | $206.05 | $4.04 | $920.00 | $210.00 | $625.00 | $688.50 | $366.69 |
| 79 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $4,590.91 | $3,509.75 | $3,880.00 | $3,920.00 | $4,000.00 | $4,449.75 | $3,132.77 |
| 80 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $1,475.00 | $333.30 | $580.00 | $265.00 | $325.00 | $344.25 | $733.39 |
| 81 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 4 | $34,250 | $30,441 | $25,630 | $25,500 | $25,000 | $33,275 | $25,378 |
| 82 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 5 | $210.00 | $237.35 | $910.00 | $307.00 | $275.00 | $401.75 | $327.25 |
| 83 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 19 | $796.93 | $813.05 | $870.00 | $801.00 | $725.00 | $975.50 | $862.75 |
| 84 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 9 | $847.73 | $883.75 | $1,020.00 | $1,080.00 | $975.00 | $1,091.00 | $1,160.25 |
| 85 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 8 | $962.58 | $979.70 | $1,090.00 | $1,160.00 | $1,050.00 | $1,205.00 | $1,249.50 |
| 86 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $1,162.50 | $1,222.10 | $1,310.00 | $1,490.00 | $1,350.00 | $1,435.00 | $1,606.50 |
| 87 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 1 | $1,275.00 | $1,555.40 | $1,770.00 | $1,840.00 | $1,600.00 | $1,547.45 | $1,904.00 |
| 88 | Remove SM RD SN sup&AM (644-7073) | EACH | 26 | $75.00 | $132.12 | $280.00 | $71.75 | $100.00 | $229.50 | $77.35 |
| 89 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 27 | $32.50 | $30.30 | $220.00 | $71.75 | $75.00 | $28.75 | $77.35 |
| 90 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 12 | $20.00 | $24.24 | $210.00 | $49.70 | $50.00 | $17.25 | $53.55 |
| 91 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 14 | $85.00 | $64.64 | $240.00 | $105.00 | $100.00 | $86.25 | $113.05 |
| 92 | Remove delin & object marker assms (658-7078) | EACH | 30 | $20.00 | $18.69 | $100.00 | $11.05 | $10.00 | $11.50 | $11.90 |
| 93 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 9 | $28.64 | $35.35 | $640.00 | $39.00 | $35.00 | $17.25 | $41.65 |
| 94 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 22,019 | $0.54 | $0.49 | $0.50 | $0.52 | $0.50 | $0.75 | $0.86 |
| 95 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 400 | $2.00 | $1.52 | $2.00 | $1.65 | $1.50 | $1.75 | $1.43 |
| 96 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 45 | $10.20 | $16.16 | $20.00 | $17.65 | $17.00 | $12.75 | $9.52 |
| 97 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 1,128 | $0.32 | $0.79 | $1.00 | $0.87 | $1.00 | $1.00 | $0.86 |
| 98 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 16,892 | $0.54 | $0.49 | $0.50 | $0.54 | $0.50 | $0.75 | $0.86 |
| 99 | Work zone pavement marking non-removing (Y)12"(solid) (662-7040) | LF | 260 | $1.78 | $2.02 | $2.00 | $2.20 | $2.00 | $3.50 | $4.76 |
| 100 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 20 | $4.15 | $3.54 | $4.00 | $3.85 | $5.00 | $5.50 | $6.55 |
| 101 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 244 | $4.20 | $3.54 | $4.00 | $3.85 | $5.00 | $5.50 | $6.55 |
| 102 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 11,370 | $0.73 | $0.39 | $0.40 | $0.43 | $0.40 | $0.75 | $1.19 |
| 103 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 11,370 | $0.72 | $0.39 | $0.40 | $0.43 | $0.40 | $0.75 | $1.19 |
| 104 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 30 | $1.00 | $1.25 | $5.00 | $1.40 | $2.00 | $0.75 | $29.75 |
| 105 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 1,220 | $1.90 | $1.25 | $5.00 | $2.20 | $2.00 | $0.75 | $4.17 |
| 106 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 400 | $1.06 | $2.02 | $2.00 | $2.20 | $2.00 | $3.00 | $1.49 |
| 107 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 100 | $7.62 | $16.16 | $20.00 | $17.65 | $16.00 | $11.25 | $16.66 |
| 108 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 335 | $3.51 | $3.54 | $4.00 | $3.85 | $3.50 | $4.75 | $8.33 |
| 109 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 340 | $1.03 | $15.15 | $20.00 | $16.55 | $15.00 | $4.50 | $11.90 |
| 110 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 170 | $1.10 | $20.20 | $20.00 | $22.10 | $20.00 | $4.50 | $11.90 |
| 111 | Reflectorized pavement marking type III (Y)(6")(broken) (666-7249) | LF | 40 | $1.82 | $25.25 | $30.00 | $27.60 | $25.00 | $4.50 | $11.90 |
| 112 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 33,146 | $0.60 | $0.67 | $1.00 | $0.75 | $0.75 | $0.75 | $0.86 |
| 113 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 3,410 | $0.69 | $1.12 | $1.00 | $1.20 | $1.20 | $1.00 | $0.86 |
| 114 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 12,954 | $0.65 | $0.85 | $1.00 | $0.95 | $1.00 | $1.00 | $0.86 |
| 115 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $283.53 | $151.50 | $150.00 | $166.00 | $150.00 | $276.00 | $416.50 |
| 116 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $309.80 | $277.75 | $280.00 | $304.00 | $275.00 | $276.00 | $476.00 |
| 117 | Reflectorized pavement marker type I-C (672-7002) | EACH | 20 | $3.91 | $35.35 | $40.00 | $39.00 | $35.00 | $8.25 | $6.55 |
| 118 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 463 | $3.57 | $7.58 | $8.00 | $8.30 | $8.00 | $5.00 | $6.55 |
| 119 | Eliminating existing PM & markers (6") (677-7002) | LF | 14,080 | $0.50 | $0.36 | $0.35 | $0.41 | $0.35 | $0.75 | $0.65 |
| 120 | PRSSR irrig PVC pipe (18") (1000-7001) | LF | 60 | $128.97 | $454.50 | $210.00 | $111.00 | $225.00 | $132.00 | $142.87 |
| 121 | PRSSR irrig PVC pipe (30") (1000-7003) | LF | 60 | $235.00 | $909.00 | $850.00 | $448.00 | $260.00 | $264.00 | $224.15 |
| 122 | Bonding course (3007-7001) | GAL | 4,335 | $6.72 | $2.57 | $7.00 | $2.80 | $4.50 | $5.00 | $10.71 |
| 123 | Bird exclusion method (5029-7001) | SF | 5,858 | $8.43 | $10.10 | $4.00 | $1.05 | $7.00 | $4.25 | $3.25 |
| 124 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 620 | $100.00 | $33.33 | $40.00 | $49.15 | $65.00 | $49.00 | $77.35 |
| 125 | RC pipe (CL III)(24 in) (464-7005) | LF | 36 | $160.00 | $212.10 | $100.00 | $95.35 | $125.00 | $92.50 | $160.30 |
| 126 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 296 | $160.00 | $58.58 | $60.00 | $64.65 | $85.00 | $72.00 | $74.97 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.