TxDOT contract A00189992 bid tabulation
Bridge Replacement, COUNTY ROAD 244 (On CR 244 (F-CR 265) to At Eads Creek). Let by Texas DOT on August 5, 2026, Leon, Bryan District. 8 bids received; low bid $2,572,458 by THK Construction LLC, +24% against the engineer's estimate of $2,078,040.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 60
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $2,572,458 | Low | +24% |
| 2 | Hodges and Son Construction Company, Inc. | $2,579,009 | 0.0% | +24% |
| 3 | Knife River Corporation - South | $2,595,573 | +1.0% | +25% |
| 4 | Pmco Construction LLC | $2,755,532 | +7.0% | +33% |
| 5 | A. L. Helmcamp, Inc. | $2,792,941 | +9.0% | +34% |
| 6 | Larry Young Paving, Inc. | $2,797,371 | +9.0% | +35% |
| 7 | Yoko Excavating, LLC | $2,859,208 | +11% | +38% |
| 8 | Garret Shields Infrastructure | $2,892,386 | +12% | +39% |
Engineer's estimate: $2,078,040.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Hodges and Son Construction Company, Inc. | 3. Knife River Corporation - South | 4. Pmco Construction LLC | 5. A. L. Helmcamp, Inc. | 6. Larry Young Paving, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 17.62 | $1,000.00 | $1,500.00 | $3,400.00 | $2,000.00 | $3,000.00 | $2,200.00 | $1,200.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 556 | $15.00 | $18.00 | $15.00 | $39.00 | $20.00 | $40.00 | $19.00 |
| 3 | Excavation (channel) (110-7002) | CY | 898 | $20.00 | $18.00 | $15.00 | $25.00 | $20.00 | $35.00 | $35.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,501 | $20.00 | $18.00 | $15.00 | $20.00 | $30.00 | $26.00 | $39.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 5,317 | $2.70 | $3.50 | $1.50 | $1.20 | $4.00 | $4.00 | $3.50 |
| 6 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 3,401 | $1.00 | $2.00 | $0.80 | $1.80 | $0.80 | $1.00 | |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,916 | $0.25 | $1.00 | $2.00 | $0.80 | $1.10 | $0.80 | $1.00 |
| 8 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 5,317 | $0.25 | $0.01 | $1.00 | $0.52 | $1.35 | $0.80 | $0.75 |
| 9 | Vegetative watering (168-7001) | TGL | 106.30 | $25.00 | $1.00 | $1.00 | $25.00 | $50.00 | $35.00 | $140.00 |
| 10 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 4,372 | $25.00 | $40.00 | $40.00 | $25.00 | $36.00 | $30.00 | $34.00 |
| 11 | Rework BS metal (type A)(8")(density control) (251-7012) | SY | 2,825 | $10.00 | $20.00 | $2.50 | $5.00 | $15.00 | $8.00 | $8.00 |
| 12 | Asphalt (RC-250) (316-7016) | GAL | 466 | $25.00 | $25.00 | $15.00 | $47.50 | $20.00 | $30.00 | |
| 13 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 14 | $1,500.00 | $1,500.00 | $1,000.00 | $1,950.00 | $1,500.00 | $400.00 | |
| 14 | SP mixes SP-C sac-A PG64-22 (344-7010) | TON | 205 | $225.00 | $300.00 | $300.00 | $400.00 | $450.00 | $260.00 | |
| 15 | Tack coat (344-7077) | GAL | 187 | $15.00 | $6.00 | $3.50 | $4.00 | $9.00 | $11.00 | |
| 16 | Cem stabil BKFL (400-7010) | CY | 304.30 | $190.00 | $275.00 | $280.00 | $280.00 | $250.00 | $230.00 | $130.00 |
| 17 | Temporary special shoring (403-7001) | SF | 1,022 | $35.00 | $35.00 | $40.00 | $40.00 | $40.00 | $70.00 | $35.00 |
| 18 | Drilled shaft (30 in) (416-7005) | LF | 630 | $250.00 | $390.34 | $260.00 | $350.00 | $250.00 | $200.00 | $350.00 |
| 19 | Drilled shaft (36 in) (416-7006) | LF | 210 | $403.00 | $320.00 | $390.00 | $300.00 | $250.00 | $510.00 | |
| 20 | Class C concrete (abutment) (420-7012) | CY | 124.80 | $1,000.00 | $1,000.00 | $1,500.00 | $1,650.00 | $1,400.00 | $1,800.00 | $1,600.00 |
| 21 | Reinforced concrete slab (box beam) (422-7005) | SF | 6,673 | $22.00 | $24.00 | $29.00 | $39.00 | $26.00 | $45.00 | $22.00 |
| 22 | Prestressed concrete box beam (4B20) (425-7026) | LF | 476 | $331.16 | $325.00 | $338.00 | $335.00 | $330.00 | $450.00 | |
| 23 | Prestressed concrete box beam (5B20) (425-7027) | LF | 238 | $335.78 | $325.00 | $338.00 | $410.00 | $330.00 | $470.00 | |
| 24 | Prestressed concrete box beam (4B28) (425-7028) | LF | 535.96 | $330.00 | $290.76 | $375.00 | $350.00 | $325.00 | $330.00 | $450.00 |
| 25 | Prestressed concrete box beam (5B28) (425-7029) | LF | 267.98 | $335.00 | $310.70 | $375.00 | $350.00 | $395.00 | $330.00 | $460.00 |
| 26 | Concrete structure repair (pan girder hole repair) (429-7010) | EACH | 8 | $120.00 | $200.00 | $100.00 | $85.00 | $750.00 | $200.00 | $350.00 |
| 27 | Riprap (mow strip)(4 in) (432-7013) | CY | 69 | $750.00 | $700.00 | $685.00 | $800.00 | $900.00 | $650.00 | |
| 28 | Riprap (stone protection)(18 in) (432-7043) | CY | 973 | $150.00 | $155.00 | $225.00 | $145.00 | $160.00 | $140.00 | $180.00 |
| 29 | Rail (type T223) (450-7008) | LF | 654 | $120.00 | $180.00 | $160.00 | $155.00 | $170.00 | $200.00 | $170.00 |
| 30 | Type A joint (454-7001) | LF | 221 | $50.00 | $20.00 | $50.00 | $65.00 | $95.00 | $110.00 | $65.00 |
| 31 | RC pipe (CL III)(18 in) (464-7003) | LF | 40 | $65.00 | $60.00 | $90.00 | $140.00 | $170.00 | $76.00 | |
| 32 | RC pipe (CL III)(24 in) (464-7005) | LF | 74 | $125.00 | $90.00 | $90.00 | $95.00 | $140.00 | $175.00 | $97.00 |
| 33 | RC pipe (CL III)(30 in) (464-7007) | LF | 95 | $120.00 | $120.00 | $110.00 | $175.00 | $180.00 | $130.00 | |
| 34 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,000.00 | $1,200.00 | $2,500.00 | $1,600.00 | $2,100.00 | $1,400.00 | |
| 35 | Set(type II)(24 in)(RCP)(3:1)(P) (467-7469) | EACH | 2 | $2,500.00 | $1,200.00 | $1,200.00 | $2,750.00 | $1,500.00 | $2,500.00 | $1,200.00 |
| 36 | Set (type II) (30 in)(RCP) (3:1) (P) (467-7481) | EACH | 2 | $2,000.00 | $2,500.00 | $3,250.00 | $2,000.00 | $2,800.00 | $2,300.00 | |
| 37 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 4 | $11,000 | $39,000 | $12,000 | $7,500.00 | $25,000 | $20,000 | $9,900.00 |
| 38 | Mobilization (500-7001) | LS | 1 | $148,500 | $190,000 | $240,000 | $254,000 | $270,000 | $220,000 | $230,000 |
| 39 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $2,000.00 | $1,867.48 | $2,000.00 | $1,400.00 | $3,000.00 | $5,000.00 | $3,600.00 |
| 40 | Portable changeable message sign (503-7001) | DAY | 49 | $75.00 | $100.00 | $75.00 | $200.00 | $100.00 | $250.00 | $60.00 |
| 41 | Rock filter dams (install) (type 2) (506-7002) | LF | 306 | $42.00 | $30.00 | $1.00 | $39.00 | $50.00 | $40.00 | $50.00 |
| 42 | Rock filter dams (remove) (506-7011) | LF | 306 | $10.00 | $1.00 | $1.00 | $10.00 | $10.00 | $10.00 | $13.00 |
| 43 | Construction exits (install) (type 2) (506-7021) | SY | 312 | $45.00 | $1.00 | $1.00 | $12.00 | $50.00 | $40.00 | $50.00 |
| 44 | Construction exits (remove) (506-7024) | SY | 312 | $15.00 | $1.00 | $1.00 | $4.00 | $10.00 | $10.00 | $13.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 2,447 | $5.00 | $3.50 | $1.00 | $6.00 | $4.25 | $3.60 | $4.50 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 2,447 | $1.50 | $1.00 | $1.00 | $1.00 | $1.10 | $1.00 | $1.25 |
| 47 | Constructing detours (508-7001) | SY | 269 | $50.00 | $150.00 | $60.00 | $55.00 | $50.00 | $35.00 | $68.00 |
| 48 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 90 | $46.00 | $100.00 | $50.00 | $67.00 | $100.00 | $75.00 | $20.00 |
| 49 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 90 | $19.00 | $25.00 | $50.00 | $65.00 | $100.00 | $50.00 | $20.00 |
| 50 | Driveways (ACP) (530-7010) | SY | 41 | $75.00 | $120.00 | $55.00 | $75.00 | $190.00 | $66.00 | |
| 51 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,037.50 | $28.00 | $26.21 | $25.00 | $25.00 | $25.30 | $26.00 | $32.00 |
| 52 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 16 | $1,000.00 | $1,207.50 | $1,200.00 | $1,300.00 | $1,215.00 | $1,300.00 | $1,400.00 |
| 53 | Guardrail end treatment (install) (544-7001) | EACH | 16 | $3,100.00 | $3,412.50 | $3,400.00 | $3,100.00 | $3,420.00 | $3,500.00 | $4,200.00 |
| 54 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,100.00 | $840.00 | $1,000.00 | $600.00 | $1,425.00 | $1,300.00 | $1,600.00 |
| 55 | Crash cushion attenuator (install)(S)(N)(TL2) (545-7013) | EACH | 2 | $7,000.00 | $8,373.75 | $10,000 | $7,000.00 | $8,450.00 | $8,500.00 | $10,000 |
| 56 | Remove SM RD SN sup&AM (644-7073) | EACH | 8 | $140.00 | $250.00 | $50.00 | $65.00 | $100.00 | $180.00 | $110.00 |
| 57 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 45 | $30.00 | $20.00 | $30.00 | $27.00 | $25.00 | $30.00 | $34.00 |
| 58 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 8 | $35.00 | $18.90 | $30.00 | $22.00 | $25.00 | $22.00 | $33.00 |
| 59 | Amphibian/reptile exclusion fence inst (5003-7001) | LF | 1,611 | $5.00 | $2.00 | $3.75 | $4.80 | $4.00 | $4.75 | |
| 60 | Amphibian/reptile exclusion fence rem (5003-7002) | LF | 1,611 | $1.00 | $1.00 | $1.00 | $1.50 | $1.10 | $1.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.