TxDOT contract A00068611 bid tabulation
Widen Road - Add Lanes, UA 90 (FM 359 to W of SH 99). Let by Texas DOT on August 5, 2026, Fort Bend, Houston District. 7 bids received; low bid $48,831,301 by Ser Construction Partners, LLC, -7.0% against the engineer's estimate of $52,496,966.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 223
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ser Construction Partners, LLC | $48,831,301 | Low | -7.0% |
| 2 | James Construction Group, LLC | $49,016,785 | 0.0% | -7.0% |
| 3 | Zachry Construction Corporation | $49,951,826 | +2.0% | -5.0% |
| 4 | Harper Brothers Construction LLC | $50,296,882 | +3.0% | -4.0% |
| 5 | R Construction Civil, LLC | $51,891,161 | +6.0% | -1.0% |
| 6 | Granite Construction Company | $52,433,678 | +7.0% | 0.0% |
| 7 | Pulice Construction, Inc. | $62,267,803 | +28% | +19% |
Engineer's estimate: $52,496,966.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ser Construction Partners, LLC | 2. James Construction Group, LLC | 3. Zachry Construction Corporation | 4. Harper Brothers Construction LLC | 5. R Construction Civil, LLC | 6. Granite Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 142.67 | $6,500.00 | $2,600.00 | $12,492 | $33,644 | $5,000.00 | $2,100.00 | $30,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 77,674 | $12.50 | $6.60 | $4.29 | $5.12 | $5.00 | $11.00 | $7.00 |
| 3 | Removing concrete (medians) (104-7008) | SY | 47 | $18.00 | $20.60 | $3.57 | $13.91 | $5.00 | $33.00 | $20.00 |
| 4 | Removing concrete (curb) (104-7016) | LF | 1,323 | $10.00 | $2.60 | $2.71 | $14.89 | $2.00 | $6.75 | $8.00 |
| 5 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 38,023 | $8.50 | $6.70 | $7.00 | $2.80 | $8.50 | $6.50 | $3.00 |
| 6 | Remove (27") TRT/untrt base & asphalt pavement (105-7131) | SY | 129,281 | $8.00 | $15.20 | $13.00 | $6.30 | $8.50 | $14.50 | $6.50 |
| 7 | Excavation (roadway) (110-7001) | CY | 10,593 | $13.00 | $6.30 | $5.00 | $7.24 | $12.00 | $18.50 | $10.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 100,855 | $10.00 | $16.50 | $18.00 | $5.21 | $12.00 | $24.00 | $15.00 |
| 9 | Block sodding (162-7002) | SY | 63,757 | $3.50 | $4.60 | $1.15 | $3.53 | $3.35 | $3.75 | $1.15 |
| 10 | Straw or hay mulch (162-7003) | SY | 63,757 | $0.30 | $0.30 | $0.30 | $0.11 | $0.10 | $0.50 | $0.30 |
| 11 | Drill seed (temporary_warm_cool) (164-7015) | SY | 63,757 | $0.20 | $0.20 | $0.24 | $0.20 | $0.19 | $0.10 | $0.24 |
| 12 | Fertilizer (166-7001) | ACRE | 26.34 | $800.00 | $927.00 | $730.00 | $657.93 | $625.00 | $590.00 | $730.00 |
| 13 | Vegetative watering (168-7001) | TGL | 3,161.50 | $9.00 | $36.10 | $20.00 | $35.79 | $90.00 | $34.00 | $9.00 |
| 14 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 2,902 | $340.00 | $340.40 | $328.10 | $338.39 | $316.00 | $370.00 | $330.00 |
| 15 | Lime TRT (existing material)(8") (260-7007) | SY | 161,098 | $2.00 | $3.70 | $3.33 | $2.59 | $3.05 | $3.00 | $4.00 |
| 16 | Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343) | SY | 176,935 | $17.00 | $9.50 | $9.23 | $10.40 | $16.00 | $19.00 | $17.00 |
| 17 | Asphalt TRT base (GR 4)(PG 64) (292-7014) | TON | 9,730 | $80.00 | $134.20 | $137.34 | $135.80 | $125.00 | $132.00 | $128.00 |
| 18 | Concrete pavement (CRCP) (9") (360-7003) | SY | 148,862 | $83.00 | $70.80 | $68.00 | $68.95 | $78.00 | $90.00 | $72.00 |
| 19 | Concrete pavement (CRCP)(fast TRK) (12") (360-7076) | SY | 29,194 | $110.00 | $111.00 | $119.00 | $95.50 | $100.00 | $108.00 | $105.00 |
| 20 | Cut & restore asphalt paving (400-7008) | SY | 88 | $180.00 | $331.70 | $207.20 | $233.56 | $210.00 | $475.00 | $500.00 |
| 21 | Cem stabil BKFL (400-7010) | CY | 10,726 | $75.00 | $63.90 | $52.73 | $66.05 | $57.00 | $84.00 | $56.00 |
| 22 | Cement stab backfill (inlet or MH) (400-7011) | CY | 370 | $70.00 | $63.90 | $52.73 | $66.10 | $57.00 | $88.00 | $56.00 |
| 23 | Trench excavation protection (402-7001) | LF | 12,674.50 | $3.00 | $0.10 | $1.04 | $7.27 | $5.00 | $5.00 | $1.00 |
| 24 | Temporary special shoring (403-7001) | SF | 7,488 | $28.00 | $32.70 | $26.40 | $30.00 | $12.50 | $47.00 | $4.00 |
| 25 | Drilled shaft (30 in) (416-7005) | LF | 8,214 | $200.00 | $199.80 | $202.22 | $194.43 | $150.00 | $185.93 | $195.00 |
| 26 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 13 | $400.00 | $273.20 | $355.00 | $373.71 | $355.00 | $385.00 | $358.59 |
| 27 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 132 | $600.00 | $471.10 | $510.00 | $536.88 | $510.00 | $575.00 | $515.15 |
| 28 | Sound wall (419-7001) | SF | 48,720 | $55.00 | $42.30 | $44.05 | $52.49 | $45.00 | $44.00 | $46.00 |
| 29 | Class C concrete (rail foundation) (420-7052) | CY | 7 | $550.00 | $938.90 | $919.66 | $1,020.17 | $2,600.00 | $600.00 | $700.00 |
| 30 | Riprap (concrete)(5 in) (432-7002) | CY | 353 | $600.00 | $598.60 | $535.31 | $551.06 | $425.00 | $375.00 | $400.00 |
| 31 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 196 | $800.00 | $610.40 | $463.22 | $647.83 | $540.00 | $840.00 | $810.00 |
| 32 | Riprap (mow strip)(4 in) (432-7013) | CY | 99 | $620.00 | $731.70 | $671.48 | $600.00 | $950.00 | $765.00 | $725.00 |
| 33 | Rail (type SSTR) (450-7024) | LF | 335 | $55.00 | $59.00 | $75.85 | $124.69 | $132.00 | $180.00 | $148.00 |
| 34 | Rail (type PR11) (450-7044) | LF | 1,133 | $130.00 | $105.80 | $94.44 | $128.30 | $50.00 | $190.00 | $123.11 |
| 35 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 840.50 | $350.00 | $257.60 | $278.36 | $269.43 | $400.00 | $300.00 | $325.00 |
| 36 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 30 | $350.00 | $301.80 | $361.43 | $408.46 | $550.00 | $515.00 | $375.00 |
| 37 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 150 | $350.00 | $359.80 | $430.18 | $317.45 | $700.00 | $430.00 | $400.00 |
| 38 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 456 | $420.00 | $392.40 | $415.17 | $339.16 | $600.00 | $348.00 | $425.00 |
| 39 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 746 | $500.00 | $473.70 | $509.17 | $406.49 | $725.00 | $434.00 | $520.00 |
| 40 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 304 | $650.00 | $544.30 | $570.98 | $471.57 | $750.00 | $499.00 | $625.00 |
| 41 | Concrete box culvert (7 FT X 4 FT) (462-7016) | LF | 296 | $725.00 | $612.40 | $658.11 | $552.89 | $850.00 | $558.00 | $700.00 |
| 42 | Concrete box culvert (7 FT X 5 FT) (462-7017) | LF | 600 | $1,000.00 | $646.00 | $697.42 | $579.76 | $950.00 | $610.00 | $725.00 |
| 43 | Concrete box culvert (8 FT X 5 FT) (462-7022) | LF | 302 | $1,200.00 | $777.10 | $834.90 | $682.63 | $1,100.00 | $646.00 | $800.00 |
| 44 | RC pipe (CL III)(24 in) (464-7005) | LF | 17,473 | $90.00 | $75.90 | $73.37 | $72.49 | $130.00 | $67.00 | $85.00 |
| 45 | RC pipe (CL III)(42 in) (464-7010) | LF | 114 | $200.00 | $173.90 | $172.28 | $166.29 | $350.00 | $174.00 | $200.00 |
| 46 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 1 | $6,800.00 | $3,050.90 | $3,917.22 | $6,000.00 | $4,000.00 | $4,700.00 | $5,000.00 |
| 47 | Junction box(complete)(PJB)(6FTX6FT) (465-7011) | EACH | 1 | $10,000 | $6,996.90 | $7,429.43 | $8,217.46 | $8,000.00 | $6,300.00 | $8,000.00 |
| 48 | Junction box(complete)(PJB)(8FTX8FT) (465-7012) | EACH | 1 | $20,500 | $13,630 | $12,078 | $14,820 | $12,000 | $9,600.00 | $14,000 |
| 49 | Inlet (complete)(pco)(3FT)(none) (465-7013) | EACH | 6 | $6,500.00 | $4,671.00 | $5,488.60 | $6,266.34 | $8,000.00 | $4,800.00 | $6,000.00 |
| 50 | Inlet (complete)(pco)(3FT)(left) (465-7014) | EACH | 3 | $6,500.00 | $7,357.90 | $5,821.61 | $6,603.22 | $8,000.00 | $5,500.00 | $7,000.00 |
| 51 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 1 | $6,400.00 | $9,822.00 | $5,790.40 | $6,571.64 | $8,000.00 | $5,200.00 | $7,000.00 |
| 52 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 21 | $6,500.00 | $7,287.00 | $6,295.11 | $7,082.19 | $8,000.00 | $6,360.00 | $7,000.00 |
| 53 | Inlet (complete)(pco)(6FT)(both) (465-7028) | EACH | 4 | $11,000 | $9,293.90 | $10,348 | $11,225 | $11,000 | $7,800.00 | $11,000 |
| 54 | Inlet (complete)(pcu)(3FT)(none) (465-7029) | EACH | 5 | $7,000.00 | $4,929.20 | $5,503.69 | $7,000.00 | $6,500.00 | $4,850.00 | $6,000.00 |
| 55 | Inlet (complete)(pcu)(3FT)(both) (465-7032) | EACH | 6 | $7,500.00 | $9,719.70 | $6,690.04 | $7,524.34 | $7,500.00 | $6,550.00 | $7,500.00 |
| 56 | Inlet (complete)(pcu)(6FT)(none) (465-7041) | EACH | 1 | $10,000 | $7,151.90 | $8,917.04 | $9,777.12 | $10,500 | $6,730.00 | $10,000 |
| 57 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 5 | $6,800.00 | $4,292.10 | $5,810.69 | $6,622.61 | $7,000.00 | $2,970.00 | $7,000.00 |
| 58 | Inlet (complete)(PSL)(FG)(6FTX6FT-3FTX3FT) (465-7140) | EACH | 11 | $12,000 | $8,371.20 | $7,947.85 | $8,780.65 | $7,000.00 | $4,730.00 | $9,000.00 |
| 59 | JCT box (complete)(special) (465-7332) | EACH | 1 | $27,000 | $52,703 | $61,532 | $40,742 | $65,000 | $43,500 | $95,000 |
| 60 | JCT box (complete)(cip)(19FT X 10 FT) (465-7415) | EACH | 1 | $20,000 | $48,031 | $40,323 | $54,253 | $60,000 | $22,600 | $60,000 |
| 61 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 2 | $14,000 | $17,991 | $15,946 | $21,482 | $35,000 | $6,250.00 | $16,671 |
| 62 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 2 | $23,000 | $29,321 | $18,009 | $22,679 | $38,000 | $8,350.00 | $13,338 |
| 63 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 3 | $22,000 | $34,748 | $18,339 | $39,858 | $42,000 | $12,800 | $24,449 |
| 64 | Wingwall (PW - 2) (HW=7 FT) (466-7191) | EACH | 3 | $28,000 | $40,649 | $19,148 | $39,347 | $48,000 | $16,000 | $24,449 |
| 65 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 2 | $32,000 | $64,298 | $22,500 | $65,678 | $55,000 | $23,200 | $26,671 |
| 66 | Set (type I)(S= 6 FT)(HW= 4 FT)(4:1)(C) (467-7129) | EACH | 3 | $13,800 | $11,668 | $9,649.55 | $8,987.30 | $9,000.00 | $29,900 | $21,000 |
| 67 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 41 | $2,200.00 | $2,813.70 | $2,817.98 | $4,983.65 | $3,100.00 | $2,600.00 | $3,500.00 |
| 68 | Set (type II) (42 in) (RCP) (6: 1) (P) (467-7380) | EACH | 1 | $7,500.00 | $11,374 | $11,643 | $15,681 | $12,000 | $11,240 | $11,000 |
| 69 | Pipe (PVC) (schedule 40) (12 in) (481-7016) | LF | 39 | $80.00 | $66.20 | $106.29 | $34.70 | $100.00 | $107.00 | $75.00 |
| 70 | Removing structure (inlet) (496-7002) | EACH | 5 | $500.00 | $517.10 | $518.11 | $3,162.66 | $700.00 | $940.00 | $1,000.00 |
| 71 | Removing structure (manhole) (496-7003) | EACH | 1 | $1,300.00 | $911.00 | $958.16 | $1,067.28 | $475.00 | $940.00 | $1,000.00 |
| 72 | Removing structure (set) (496-7004) | EACH | 88 | $450.00 | $646.50 | $195.60 | $1,165.07 | $450.00 | $600.00 | $900.00 |
| 73 | Removing structure (wingwall) (496-7005) | EACH | 1 | $1,900.00 | $2,685.10 | $2,730.29 | $2,828.55 | $600.00 | $4,700.00 | $2,000.00 |
| 74 | Removing structure (headwall) (496-7006) | EACH | 6 | $1,700.00 | $2,685.10 | $1,482.21 | $2,635.56 | $1,300.00 | $2,350.00 | $3,000.00 |
| 75 | Removing structure (pipe) (496-7007) | LF | 2,601 | $20.00 | $26.10 | $11.80 | $38.18 | $15.00 | $24.00 | $30.00 |
| 76 | Removing structure (box culvert) (496-7008) | LF | 2,314 | $40.00 | $47.90 | $47.58 | $89.45 | $60.00 | $50.00 | $40.00 |
| 77 | Removing structure (small) (496-7036) | EACH | 1 | $500.00 | $911.00 | $479.09 | $10,527 | $500.00 | $2,870.00 | $1,000.00 |
| 78 | Mobilization (500-7001) | LS | 1 | $4,758,646 | $4,500,000 | $4,700,000 | $4,800,000 | $4,600,000 | $2,400,000 | $4,500,000 |
| 79 | Barricades, signs and traffic handling (502-7001) | MO | 38 | $8,000.00 | $3,891.00 | $12,229 | $5,239.70 | $3,286.50 | $7,800.00 | $12,000 |
| 80 | Portable changeable message sign (503-7002) | EACH | 2 | $2,000.00 | $8,240.00 | $14,569 | $19,942 | $22,000 | $19,500 | $12,473 |
| 81 | TMA (stationary) (505-7001) | DAY | 576 | $250.00 | $206.00 | $192.57 | $183.90 | $60.00 | $230.00 | $200.00 |
| 82 | TMA (mobile operation) (505-7002) | HR | 160 | $50.00 | $82.30 | $570.75 | $65.71 | $70.00 | $170.00 | $95.00 |
| 83 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,024 | $50.00 | $82.40 | $40.53 | $31.58 | $30.00 | $47.00 | $40.53 |
| 84 | Rock filter dams (install) (type 3) (506-7003) | LF | 180 | $100.00 | $103.00 | $53.80 | $68.42 | $65.00 | $120.00 | $53.80 |
| 85 | Rock filter dams (remove) (506-7011) | LF | 1,204 | $16.00 | $20.60 | $12.00 | $18.95 | $18.00 | $15.00 | $12.00 |
| 86 | Construction exits (install) (type 1) (506-7020) | SY | 382 | $30.00 | $28.80 | $27.00 | $33.69 | $32.00 | $46.00 | $27.00 |
| 87 | Construction exits (remove) (506-7024) | SY | 382 | $8.00 | $10.30 | $15.40 | $18.95 | $18.00 | $13.00 | $15.40 |
| 88 | Temporary sediment control fence (install) (506-7039) | LF | 28,409 | $2.50 | $1.90 | $2.71 | $3.00 | $2.85 | $3.48 | $2.71 |
| 89 | Temporary sediment control fence (remove) (506-7041) | LF | 28,409 | $1.00 | $0.60 | $0.99 | $1.05 | $1.00 | $1.00 | $0.99 |
| 90 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 920 | $4.00 | $6.20 | $5.00 | $6.84 | $6.50 | $6.00 | $5.00 |
| 91 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 325 | $7.00 | $7.20 | $6.80 | $8.95 | $8.50 | $7.50 | $6.80 |
| 92 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,245 | $1.40 | $2.10 | $1.00 | $2.11 | $2.00 | $1.50 | $1.00 |
| 93 | Constructing detours (type 1) (508-7003) | SY | 39,006 | $80.00 | $90.00 | $99.88 | $87.04 | $90.00 | $89.00 | $98.00 |
| 94 | Constructing detours (type 2) (508-7004) | SY | 1,489 | $80.00 | $48.00 | $47.61 | $35.68 | $60.00 | $33.00 | $50.00 |
| 95 | Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021) | LF | 29,900 | $18.00 | $9.70 | $8.31 | $5.73 | $8.00 | $7.50 | $8.00 |
| 96 | Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022) | LF | 520 | $26.00 | $9.70 | $8.31 | $8.03 | $10.00 | $7.46 | $31.00 |
| 97 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 29,880 | $10.00 | $8.60 | $4.50 | $1.99 | $4.00 | $7.00 | $5.00 |
| 98 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 740 | $14.00 | $8.60 | $5.27 | $6.01 | $4.00 | $11.00 | $9.00 |
| 99 | Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045) | LF | 29,900 | $10.00 | $9.40 | $7.95 | $5.73 | $8.00 | $7.50 | $9.00 |
| 100 | Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046) | LF | 520 | $10.00 | $9.40 | $7.95 | $8.03 | $10.00 | $7.50 | $23.00 |
| 101 | Portable concrete traffic barrier (connection hardware) (512-7070) | EACH | 1,441 | $20.00 | $98.90 | $99.90 | $101.06 | $75.00 | $174.00 | $101.00 |
| 102 | Concrete curb (mono) (type I) (529-7006) | LF | 363 | $15.00 | $4.30 | $4.44 | $2.81 | $6.50 | $8.00 | $6.00 |
| 103 | Concrete curb (mono) (type II) (529-7007) | LF | 15,206 | $8.00 | $4.00 | $4.44 | $5.06 | $4.50 | $8.00 | $5.00 |
| 104 | Concrete curb (slotted) (529-7013) | LF | 1,359 | $18.00 | $4.60 | $5.45 | $6.64 | $4.50 | $15.60 | $10.00 |
| 105 | Driveways (concrete) (hes) (530-7007) | SY | 2,672 | $125.00 | $84.10 | $74.59 | $113.06 | $150.00 | $87.00 | $125.00 |
| 106 | Driveways (ACP) (530-7010) | SY | 319 | $60.00 | $68.70 | $79.85 | $47.38 | $75.00 | $60.00 | $75.00 |
| 107 | Concrete sidewalks (6") (531-7003) | SY | 15,534 | $69.00 | $80.50 | $66.86 | $68.17 | $68.00 | $82.00 | $78.00 |
| 108 | Curb ramps (type 1) (531-7005) | EACH | 1 | $2,500.00 | $1,211.20 | $2,312.93 | $2,991.01 | $8,550.00 | $2,350.00 | $1,500.00 |
| 109 | Curb ramps (type 3) (531-7007) | EACH | 2 | $2,600.00 | $2,189.20 | $2,312.95 | $3,368.65 | $8,550.00 | $2,350.00 | $1,850.00 |
| 110 | Curb ramps (type 7) (531-7010) | EACH | 6 | $2,400.00 | $4,616.80 | $2,806.36 | $4,033.63 | $8,300.00 | $2,350.00 | $2,450.00 |
| 111 | Curb ramps (type 10) (531-7011) | EACH | 1 | $2,000.00 | $2,609.10 | $2,777.98 | $3,684.46 | $9,000.00 | $3,250.00 | $2,450.00 |
| 112 | Curb ramps (type 21) (531-7013) | EACH | 2 | $3,200.00 | $1,968.30 | $2,537.18 | $3,751.32 | $10,882 | $2,350.00 | $1,700.00 |
| 113 | Fill milled asphalt rumble strips (shoulder) (533-7005) | LF | 10,600 | $5.00 | $3.60 | $5.00 | $2.37 | $10.00 | $8.25 | $5.00 |
| 114 | Concrete median (536-7002) | SY | 11,490 | $110.00 | $52.50 | $72.46 | $66.19 | $55.00 | $67.00 | $48.00 |
| 115 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,050 | $28.00 | $31.50 | $26.50 | $32.26 | $26.50 | $28.00 | $25.09 |
| 116 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $1,800.00 | $2,157.90 | $2,100.00 | $2,254.19 | $2,100.00 | $3,300.00 | $1,656.20 |
| 117 | Downstream anchor terminal section (540-7015) | EACH | 5 | $1,100.00 | $1,225.70 | $1,585.00 | $1,466.22 | $1,585.00 | $1,650.00 | $1,355.07 |
| 118 | Metal beam guard fence (long span system) (540-7027) | EACH | 4 | $1,000.00 | $1,179.40 | $1,350.00 | $1,567.49 | $1,350.00 | $1,400.00 | $1,179.42 |
| 119 | Remove metal beam guard fence (542-7001) | LF | 1,001 | $3.00 | $2.10 | $3.00 | $6.32 | $3.00 | $3.00 | $3.01 |
| 120 | Remove terminal anchor section (542-7002) | EACH | 6 | $210.00 | $226.60 | $250.00 | $726.24 | $250.00 | $260.00 | $200.75 |
| 121 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,000.00 | $3,682.30 | $3,285.00 | $4,271.76 | $3,285.00 | $3,450.00 | $3,362.59 |
| 122 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $250.00 | $339.90 | $200.00 | $564.29 | $200.00 | $208.80 | $200.75 |
| 123 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 1 | $23,000 | $28,634 | $25,850 | $32,344 | $25,850 | $27,000 | $25,250 |
| 124 | Conduit (PVC) (schedule 40) (3") (concrete encse) (618-7038) | LF | 16,100 | $13.00 | $14.60 | $12.05 | $12.69 | $12.05 | $14.00 | $12.17 |
| 125 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 555 | $10.00 | $10.70 | $12.75 | $13.42 | $12.75 | $8.25 | $12.88 |
| 126 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 12,620 | $37.00 | $31.10 | $13.25 | $13.95 | $13.25 | $13.00 | $13.38 |
| 127 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 40 | $25.00 | $19.70 | $29.50 | $31.06 | $29.50 | $12.00 | $29.80 |
| 128 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 1,520 | $35.00 | $22.80 | $13.75 | $14.48 | $13.75 | $20.00 | $13.89 |
| 129 | ITS multi-duct CND (PVC-40)(concrete encse) (619-7003) | LF | 16,100 | $20.00 | $24.90 | $19.05 | $20.06 | $19.05 | $25.00 | $19.24 |
| 130 | ITS multi-duct CND (PVC-80)(bore) (619-7006) | LF | 12,620 | $40.00 | $43.10 | $24.75 | $26.06 | $24.75 | $23.00 | $25.00 |
| 131 | Electrical conductor (no.14) insulated (620-7002) | LF | 14,360 | $0.80 | $1.10 | $1.55 | $1.63 | $1.55 | $0.85 | $1.57 |
| 132 | Electrical conductor (no.8) bare (620-7007) | LF | 2,115 | $2.00 | $1.90 | $2.15 | $2.26 | $2.15 | $1.60 | $2.17 |
| 133 | Electrical conductor (no.4) insulated (620-7012) | LF | 220 | $3.50 | $3.30 | $2.85 | $3.00 | $2.85 | $2.30 | $2.88 |
| 134 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 1,550 | $4.00 | $3.30 | $3.90 | $4.11 | $3.90 | $2.88 | $3.94 |
| 135 | ITS GND box(pcast) type 1 (243636) (623-7001) | EACH | 3 | $4,000.00 | $4,718.40 | $4,275.00 | $4,500.31 | $4,275.00 | $4,900.00 | $4,318.18 |
| 136 | ITS GND box(pcast) type 1 (243636)W/aprn (623-7002) | EACH | 33 | $4,250.00 | $5,022.30 | $4,775.00 | $5,026.66 | $4,775.00 | $5,250.00 | $4,823.23 |
| 137 | ITS GND box(pcast) type 2 (366036)W/aprn (623-7008) | EACH | 2 | $7,400.00 | $7,895.00 | $7,075.00 | $7,447.89 | $7,075.00 | $7,100.00 | $7,146.47 |
| 138 | Ground box type D (162922)W/apron (624-7008) | EACH | 9 | $1,500.00 | $1,097.00 | $1,300.00 | $1,368.51 | $1,300.00 | $1,550.00 | $1,313.13 |
| 139 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 2 | $10,000 | $7,575.70 | $6,925.00 | $7,289.98 | $6,925.00 | $7,450.00 | $6,994.95 |
| 140 | Aluminum signs (type A) (636-7001) | SF | 45.75 | $40.00 | $39.10 | $123.25 | $33.18 | $123.25 | $31.00 | $30.00 |
| 141 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 23 | $600.00 | $700.40 | $535.00 | $754.63 | $535.00 | $560.00 | $583.00 |
| 142 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 3 | $850.00 | $916.70 | $685.00 | $1,024.88 | $685.00 | $720.00 | $785.00 |
| 143 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 40 | $770.00 | $885.80 | $655.00 | $910.74 | $655.00 | $720.00 | $733.00 |
| 144 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 3 | $850.00 | $978.50 | $785.00 | $1,111.27 | $785.00 | $825.00 | $960.00 |
| 145 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $990.00 | $1,277.20 | $995.00 | $1,370.92 | $995.00 | $1,050.00 | $1,114.03 |
| 146 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,200.00 | $1,339.00 | $1,300.00 | $1,812.54 | $1,300.00 | $1,350.00 | $1,586.00 |
| 147 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 6 | $1,300.00 | $1,323.60 | $1,285.00 | $1,064.54 | $1,285.00 | $130.00 | $1,299.00 |
| 148 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 27 | $25.00 | $25.80 | $25.00 | $32.36 | $25.00 | $26.00 | $95.00 |
| 149 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 8 | $120.00 | $92.70 | $90.00 | $196.99 | $90.00 | $94.00 | $95.00 |
| 150 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 22,300 | $1.00 | $2.80 | $2.75 | $2.90 | $2.75 | $2.85 | $2.78 |
| 151 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 240 | $2.00 | $3.80 | $3.66 | $3.85 | $3.66 | $3.85 | $3.70 |
| 152 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 94,277 | $0.75 | $1.30 | $1.25 | $1.32 | $1.25 | $1.30 | $1.26 |
| 153 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 7,069 | $2.00 | $2.70 | $2.60 | $2.74 | $2.60 | $2.70 | $2.63 |
| 154 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 785 | $9.00 | $6.80 | $6.60 | $6.95 | $6.60 | $6.60 | $6.67 |
| 155 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 93,617 | $0.75 | $1.30 | $1.25 | $1.32 | $1.25 | $1.25 | $1.26 |
| 156 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 14,680 | $0.30 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 | $0.10 |
| 157 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 367 | $0.90 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 | $0.10 |
| 158 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 29,482 | $0.30 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 | $0.10 |
| 159 | Reflectorized pavement marking type II (W) 8" (DOT) (666-7177) | LF | 629 | $1.20 | $0.10 | $0.12 | $0.13 | $0.12 | $0.13 | $0.12 |
| 160 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 11,702 | $0.70 | $0.10 | $0.12 | $0.13 | $0.12 | $0.13 | $0.12 |
| 161 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 564 | $3.50 | $0.40 | $0.36 | $0.38 | $0.36 | $0.35 | $0.36 |
| 162 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 27,673 | $0.30 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 | $0.10 |
| 163 | Reflectorized pavement marking type II (BLK)(6")(shadow) (666-7229) | LF | 14,680 | $0.70 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 | $0.10 |
| 164 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 29,482 | $0.80 | $0.90 | $0.90 | $0.95 | $0.90 | $0.95 | $0.91 |
| 165 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 14,680 | $0.80 | $0.90 | $0.90 | $0.95 | $0.90 | $0.94 | $0.91 |
| 166 | Reflectorized pavement marking type III (W)(6")(DOT) (666-7238) | LF | 367 | $2.00 | $0.90 | $0.90 | $0.95 | $0.90 | $0.94 | $0.91 |
| 167 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 11,702 | $1.60 | $2.20 | $2.12 | $2.23 | $2.12 | $2.20 | $2.14 |
| 168 | Reflectorized pavement marking type III (W)(8")(DOT) (666-7241) | LF | 629 | $2.00 | $2.20 | $2.12 | $2.23 | $2.12 | $2.20 | $2.14 |
| 169 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 564 | $8.00 | $10.80 | $10.50 | $11.05 | $10.50 | $11.00 | $10.61 |
| 170 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 27,673 | $1.20 | $0.90 | $0.90 | $0.95 | $0.90 | $0.95 | $0.91 |
| 171 | Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262) | LF | 14,680 | $0.90 | $0.90 | $0.90 | $0.95 | $0.90 | $0.95 | $0.91 |
| 172 | Prefabricated PM type C (W)(24")(solid)contrast (668-7090) | LF | 531 | $50.00 | $34.10 | $33.06 | $34.81 | $33.06 | $35.00 | $33.39 |
| 173 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 29 | $220.00 | $316.40 | $307.19 | $323.39 | $307.19 | $320.00 | $310.29 |
| 174 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 1 | $325.00 | $429.20 | $416.69 | $438.66 | $416.69 | $430.00 | $420.90 |
| 175 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 14 | $320.00 | $443.00 | $430.08 | $452.74 | $430.08 | $440.00 | $434.42 |
| 176 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $550.00 | $536.60 | $520.95 | $548.41 | $520.95 | $540.00 | $526.21 |
| 177 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 43 | $285.00 | $376.80 | $365.84 | $385.12 | $365.84 | $380.00 | $369.54 |
| 178 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 6 | $600.00 | $677.30 | $657.62 | $692.28 | $657.62 | $685.00 | $664.26 |
| 179 | Reflectorized pavement marker type I-C (672-7002) | EACH | 108 | $6.00 | $6.20 | $6.00 | $6.32 | $6.00 | $6.25 | $6.06 |
| 180 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,259 | $5.00 | $6.20 | $6.00 | $6.32 | $6.00 | $6.25 | $6.06 |
| 181 | Eliminating existing PM & markers (4") (677-7001) | LF | 35,777 | $0.30 | $0.40 | $0.39 | $0.41 | $0.39 | $0.40 | $0.39 |
| 182 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,866 | $0.60 | $0.80 | $0.78 | $0.82 | $0.78 | $0.80 | $0.79 |
| 183 | Eliminating existing PM & markers (24") (677-7008) | LF | 153 | $3.00 | $2.70 | $2.65 | $2.79 | $2.65 | $2.75 | $2.68 |
| 184 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 5 | $50.00 | $72.10 | $70.00 | $73.69 | $70.00 | $70.00 | $70.71 |
| 185 | Eliminating existing PM & markers (word) (677-7015) | EACH | 5 | $50.00 | $77.30 | $75.00 | $78.95 | $75.00 | $75.00 | $75.76 |
| 186 | Pavement surface preparation for marking (6") (678-7002) | LF | 86,882 | $0.10 | $0.40 | $0.42 | $0.44 | $0.42 | $0.42 | $0.42 |
| 187 | Pavement surface preparation for marking (8") (678-7004) | LF | 12,331 | $0.10 | $0.90 | $0.84 | $0.88 | $0.84 | $0.85 | $0.85 |
| 188 | Pavement surface preparation for marking (24") (678-7008) | LF | 531 | $0.70 | $6.20 | $6.00 | $6.32 | $6.00 | $6.25 | $6.06 |
| 189 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 31 | $16.00 | $87.60 | $85.00 | $89.48 | $85.00 | $88.00 | $85.86 |
| 190 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 1 | $20.00 | $123.60 | $120.00 | $126.29 | $120.00 | $125.00 | $121.21 |
| 191 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 14 | $21.00 | $123.60 | $120.00 | $126.32 | $120.00 | $125.00 | $121.21 |
| 192 | Pavement surface preparation for marking (word) (678-7016) | EACH | 43 | $15.00 | $123.60 | $120.00 | $126.32 | $120.00 | $125.00 | $121.21 |
| 193 | Pavement surface preparation for marking (RR crossing) (678-7020) | EACH | 6 | $10.00 | $309.00 | $300.00 | $315.82 | $300.00 | $300.00 | $303.03 |
| 194 | Install highway traffic signal (system) (680-7003) | EACH | 2 | $40,000 | $43,896 | $32,475 | $34,187 | $32,475 | $28,500 | $32,803 |
| 195 | Removing traffic signals (680-7004) | EACH | 2 | $5,100.00 | $5,150.00 | $3,184.75 | $3,352.60 | $3,184.08 | $8,500.00 | $3,216.92 |
| 196 | Temporary traffic signals (681-7001) | EACH | 2 | $45,000 | $66,254 | $88,188 | $92,835 | $88,188 | $85,000 | $89,078 |
| 197 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 19 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 198 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 6 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 199 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 19 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 200 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 6 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 201 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 19 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 202 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 12 | $270.00 | $350.20 | $305.00 | $321.08 | $305.00 | $270.00 | $308.08 |
| 203 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 4 | $650.00 | $788.00 | $935.00 | $984.27 | $935.00 | $635.00 | $944.45 |
| 204 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 6 | $225.00 | $187.50 | $275.00 | $289.50 | $275.00 | $200.00 | $277.78 |
| 205 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 19 | $180.00 | $138.00 | $220.00 | $231.60 | $220.00 | $170.00 | $222.22 |
| 206 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 615 | $2.00 | $2.10 | $2.25 | $2.37 | $2.25 | $1.50 | $2.27 |
| 207 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 635 | $2.00 | $3.10 | $2.75 | $2.90 | $2.75 | $2.00 | $2.78 |
| 208 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 4,697 | $4.00 | $4.70 | $3.90 | $4.11 | $3.90 | $3.00 | $3.94 |
| 209 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $15,000 | $16,063 | $22,050 | $23,212 | $22,050 | $17,500 | $22,273 |
| 210 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 1 | $36,000 | $36,029 | $35,775 | $37,661 | $35,775 | $45,500 | $36,136 |
| 211 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 1 | $39,000 | $37,335 | $37,200 | $39,161 | $37,200 | $46,000 | $37,576 |
| 212 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 2 | $38,500 | $37,871 | $38,275 | $40,292 | $38,275 | $47,000 | $38,662 |
| 213 | Ins traffic signal PL AM(S)1 arm(65')lum (686-7067) | EACH | 2 | $42,000 | $38,322 | $39,205 | $41,271 | $39,205 | $47,500 | $39,601 |
| 214 | Pedestrian pole assembly (687-7001) | EACH | 3 | $2,600.00 | $2,621.40 | $2,835.00 | $2,984.42 | $2,835.00 | $2,900.00 | $2,863.64 |
| 215 | Pedestrian detect push button (standard) (688-7002) | EACH | 4 | $310.00 | $773.50 | $1,085.00 | $1,142.19 | $1,085.00 | $1,000.00 | $1,095.96 |
| 216 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $3,600.00 | $4,084.00 | $4,250.00 | $4,473.99 | $4,250.00 | $5,100.00 | $4,292.93 |
| 217 | Full - width mowing (730-7019) | CYC | 6 | $6,000.00 | $3,914.00 | $4,518.70 | $12,106 | $16,000 | $1,300.00 | $5,417.15 |
| 218 | Litter removal (734-7002) | CYC | 6 | $2,900.00 | $1,751.00 | $820.70 | $2,903.76 | $3,500.00 | $2,400.00 | $1,066.75 |
| 219 | Debris removal (CNTR medians/mainlanes) (735-7014) | CYC | 24 | $1,800.00 | $2,266.00 | $845.12 | $2,903.76 | $2,000.00 | $2,400.00 | $975.00 |
| 220 | Cleaning / sweeping (center median) (738-7004) | CYC | 24 | $3,000.00 | $2,678.00 | $1,000.00 | $909.20 | $1,600.00 | $1,400.00 | $1,575.00 |
| 221 | Bbu system (external battery cabinet) (6007-7001) | EACH | 2 | $9,000.00 | $9,527.50 | $8,975.00 | $9,448.02 | $8,975.00 | $8,900.00 | $9,065.66 |
| 222 | RVDS (presence detection only) (6008-7001) | EACH | 7 | $6,500.00 | $10,028 | $6,975.00 | $7,342.61 | $6,975.00 | $6,500.00 | $7,045.45 |
| 223 | RVDS (advance detection only) (6008-7002) | EACH | 4 | $6,500.00 | $8,242.60 | $6,975.00 | $7,342.62 | $6,975.00 | $6,500.00 | $7,045.46 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.