TxDOT contract A00209149 bid tabulation
Bridge Replacement, MANGANA-HEIN RD (MANGANA HEIN RD to .). Let by Texas DOT on November 4, 2026, Webb, Laredo District. 7 bids received; low bid $2,866,785 by STX Civil, +12% against the engineer's estimate of $2,562,657.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $2,866,785 | Low | +12% |
| 2 | Delgado'S Contractors, LLC | $2,950,000 | +3.0% | +15% |
| 3 | Acee Construction LLC. | $3,033,273 | +6.0% | +18% |
| 4 | James Construction Group, LLC | $3,261,472 | +14% | +27% |
| 5 | E-Z Bel Construction, LLC | $3,270,969 | +14% | +28% |
| 6 | Lucania Contractors LLC | $3,466,015 | +21% | +35% |
| 7 | Foremost Paving, Inc. | $5,083,300 | +77% | +98% |
Engineer's estimate: $2,562,657.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Delgado'S Contractors, LLC | 3. Acee Construction LLC. | 4. James Construction Group, LLC | 5. E-Z Bel Construction, LLC | 6. Lucania Contractors LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 11 | $2,500.00 | $1,994.88 | $1,000.00 | $2,700.00 | $10,000 | $7,200.00 | $3,900.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 134 | $21.37 | $8.00 | $5.70 | $32.87 | $17.00 | $22.00 | |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 349 | $7.74 | $10.00 | $2.55 | $4.38 | $14.00 | $18.00 | |
| 4 | Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014) | SY | 1,954 | $20.00 | $13.84 | $8.00 | $5.80 | $10.13 | $15.00 | $30.00 |
| 5 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 572 | $13.84 | $15.00 | $2.45 | $7.11 | $9.25 | $30.00 | |
| 6 | Excavation (roadway) (110-7001) | CY | 350 | $11.00 | $20.80 | $25.00 | $20.00 | $68.90 | $19.00 | $20.00 |
| 7 | Excavation (channel) (110-7002) | CY | 1,540 | $20.00 | $18.96 | $25.00 | $20.00 | $25.67 | $25.00 | $15.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 719 | $12.50 | $22.00 | $50.00 | $37.50 | $20.53 | $25.00 | $40.00 |
| 9 | Proof rolling (216-7001) | HR | 24 | $150.00 | $131.66 | $25.00 | $56.70 | $165.07 | $110.00 | $1.00 |
| 10 | FL BS (compacted in place)(type A GR 1-2) (6") (247-7044) | SY | 1,051 | $39.18 | $30.00 | $37.50 | $34.14 | $35.00 | $30.00 | |
| 11 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 1,724 | $21.50 | $49.99 | $30.00 | $45.00 | $40.43 | $45.00 | $32.00 |
| 12 | Prime coat (MC-30) (310-7004) | GAL | 529 | $5.00 | $13.67 | $5.00 | $9.10 | $5.50 | $20.00 | $10.00 |
| 13 | Lra pavement type-I GR-CC (330-7005) | TON | 97 | $207.97 | $175.00 | $215.00 | $150.00 | $205.00 | $200.00 | |
| 14 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 274 | $115.00 | $165.39 | $175.00 | $201.50 | $120.00 | $180.00 | $280.00 |
| 15 | D-GR HMA type-C sac-A PG76-22 (341-7031) | TON | 169 | $113.00 | $225.16 | $175.00 | $244.80 | $140.00 | $218.00 | $330.00 |
| 16 | Cem stabil BKFL (400-7010) | CY | 282 | $150.00 | $175.85 | $210.00 | $145.00 | $279.51 | $265.00 | $100.00 |
| 17 | Flowable backfill (401-7001) | CY | 185 | $235.45 | $210.00 | $175.00 | $258.30 | $250.00 | $200.00 | |
| 18 | Temporary special shoring (403-7001) | SF | 2,775 | $15.00 | $8.68 | $35.00 | $21.00 | $42.66 | $24.00 | $30.00 |
| 19 | Drilled shaft (18 in) (416-7002) | LF | 136 | $190.22 | $180.00 | $195.00 | $114.65 | $142.00 | $500.00 | |
| 20 | Drilled shaft (36 in) (416-7006) | LF | 537 | $275.00 | $667.42 | $500.00 | $546.40 | $401.04 | $470.00 | $610.00 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 83.40 | $1,500.00 | $1,039.46 | $1,750.00 | $1,222.05 | $1,297.16 | $1,345.00 | $2,300.00 |
| 22 | Class C concrete (cap) (420-7022) | CY | 43.20 | $1,450.00 | $1,219.49 | $1,750.00 | $1,232.00 | $1,480.04 | $1,425.00 | $2,500.00 |
| 23 | Class C concrete (column) (420-7038) | CY | 15.80 | $1,500.00 | $1,450.55 | $1,750.00 | $1,112.30 | $2,765.79 | $1,125.00 | $2,000.00 |
| 24 | CL E concrete (seal slab) (420-7069) | CY | 79 | $423.78 | $450.00 | $338.00 | $350.00 | $205.00 | $400.00 | |
| 25 | Class A concrete (channel lining) (420-7150) | CY | 12 | $879.41 | $750.00 | $675.00 | $990.58 | $640.00 | $1,000.00 | |
| 26 | Class C concrete (culvert) (420-7152) | CY | 148 | $864.64 | $1,500.00 | $1,250.00 | $1,116.58 | $1,950.00 | $1,350.00 | |
| 27 | Reinforced concrete slab (422-7001) | SF | 8,100 | $25.00 | $24.40 | $28.50 | $24.00 | $42.14 | $30.00 | $32.00 |
| 28 | Approach slab (422-7013) | CY | 108 | $900.00 | $901.17 | $950.00 | $905.00 | $841.37 | $725.00 | $650.00 |
| 29 | Prestressed concrete girder (TX28) (425-7001) | LF | 1,337.26 | $180.00 | $358.79 | $245.00 | $248.75 | $276.94 | $325.00 | $320.00 |
| 30 | Riprap (concrete)(4 in) (432-7001) | CY | 12 | $801.77 | $650.00 | $620.70 | $546.67 | $530.00 | $600.00 | |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 44 | $695.00 | $623.05 | $650.00 | $603.85 | $602.34 | $700.00 | $450.00 |
| 32 | Riprap (stone protection)(12 in) (432-7041) | CY | 1,052 | $170.00 | $142.96 | $200.00 | $245.00 | $275.95 | $205.00 | $180.00 |
| 33 | Rail (type T223) (450-7008) | LF | 702 | $110.00 | $166.45 | $175.00 | $177.75 | $113.89 | $250.00 | $200.00 |
| 34 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 129 | $220.00 | $247.10 | $200.00 | $265.70 | $281.99 | $325.00 | $350.00 |
| 35 | Wingwall (FW - 0) (HW=7 FT) (466-7149) | EACH | 4 | $10,076 | $11,000 | $4,750.00 | $18,658 | $500.00 | $14,000 | |
| 36 | Removing structure (wingwall) (496-7005) | EACH | 4 | $2,440.54 | $1,500.00 | $179.40 | $811.77 | $1,500.00 | $2,000.00 | |
| 37 | Removing structure (box culvert) (496-7008) | LF | 86 | $139.93 | $200.00 | $50.00 | $99.06 | $80.00 | $250.00 | |
| 38 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $21,000 | $9,809.07 | $20,000 | $32,500 | $34,501 | $28,000 | $35,000 |
| 39 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $18,646 | $35,000 | $95,000 | $73,430 | $34,000 | $75,000 | |
| 40 | Mobilization (500-7001) | LS | 1 | $244,900 | $172,438 | $177,500 | $300,000 | $241,538 | $304,000 | $324,000 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $2,000.00 | $3,028.27 | $2,500.00 | $5,500.00 | $5,980.67 | $4,200.00 | $1,500.00 |
| 42 | Rock filter dams (install) (type 2) (506-7002) | LF | 210 | $49.00 | $42.14 | $30.00 | $94.25 | $62.00 | $62.00 | $60.00 |
| 43 | Rock filter dams (remove) (506-7011) | LF | 210 | $17.00 | $3.47 | $5.00 | $19.70 | $32.00 | $32.00 | $30.00 |
| 44 | Temporary sediment control fence (install) (506-7039) | LF | 1,350 | $4.00 | $3.50 | $5.00 | $7.90 | $3.95 | $4.00 | $5.00 |
| 45 | Temporary sediment control fence (remove) (506-7041) | LF | 1,350 | $1.20 | $1.25 | $1.00 | $1.60 | $2.25 | $2.50 | $2.00 |
| 46 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 210 | $60.00 | $73.84 | $125.00 | $27.00 | $26.93 | $62.00 | $100.00 |
| 47 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 390 | $6.00 | $22.51 | $25.00 | $11.50 | $9.98 | $5.00 | $6.00 |
| 48 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 210 | $10.00 | $3.50 | $35.00 | $12.50 | $16.00 | $62.00 | $35.00 |
| 49 | Concrete curb & gutter (type I) (529-7008) | LF | 31 | $22.07 | $35.00 | $24.50 | $108.63 | $73.00 | $30.00 | |
| 50 | Concrete curb & gutter (type II) (529-7009) | LF | 294 | $15.80 | $35.00 | $39.35 | $58.96 | $61.00 | $30.00 | |
| 51 | Driveways (ACP) (530-7010) | SY | 92 | $96.54 | $60.00 | $75.00 | $136.48 | $105.00 | $60.00 | |
| 52 | Metal W-beam guard fence (timber post) (540-7001) | LF | 600 | $27.00 | $36.03 | $30.00 | $24.10 | $29.80 | $35.00 | $30.00 |
| 53 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,350.00 | $1,916.29 | $1,400.00 | $1,500.00 | $1,585.00 | $1,400.00 | $1,500.00 |
| 54 | Downstream anchor terminal section (540-7015) | EACH | 4 | $1,600.00 | $1,450.82 | $1,700.00 | $1,505.00 | $1,200.00 | $1,800.00 | $1,200.00 |
| 55 | Remove metal beam guard fence (542-7001) | LF | 728 | $3.50 | $3.63 | $2.00 | $5.00 | $3.00 | $5.00 | $3.00 |
| 56 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,350.00 | $4,298.06 | $4,000.00 | $3,400.00 | $3,555.00 | $4,200.00 | $3,600.00 |
| 57 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 8 | $1,500.00 | $1,834.67 | $2,000.00 | $750.00 | $1,517.49 | $1,350.00 | $1,000.00 |
| 58 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $900.00 | $979.31 | $2,000.00 | $850.00 | $810.00 | $1,400.00 | $1,500.00 |
| 59 | Cca (install)(N)(TL2)(work zone) (545-7017) | EACH | 2 | $8,000.00 | $9,980.43 | $8,000.00 | $4,250.00 | $8,255.00 | $4,400.00 | $27,000 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $800.00 | $3,022.55 | $2,534.15 | $2,625.00 | $850.00 | $2,825.00 | $1,100.00 |
| 61 | Remove SM RD SN sup&AM (644-7073) | EACH | 7 | $130.00 | $102.77 | $100.00 | $89.25 | $110.00 | $85.00 | $100.00 |
| 62 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 12 | $211.58 | $180.00 | $183.75 | $79.00 | $175.00 | $100.00 | |
| 63 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 12 | $134.00 | $211.58 | $180.00 | $183.75 | $80.00 | $175.00 | $100.00 |
| 64 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $100.00 | $151.13 | $130.00 | $131.25 | $45.00 | $125.00 | $100.00 |
| 65 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 6 | $151.13 | $130.00 | $131.25 | $45.00 | $125.00 | $100.00 | |
| 66 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 8 | $80.00 | $181.35 | $160.00 | $157.50 | $65.00 | $150.00 | $100.00 |
| 67 | Install object marker assembly (OM-3L)(WFLX)GNDLL (658-7268) | EACH | 2 | $1,148.56 | $1,050.00 | $997.50 | $492.00 | $950.00 | $700.00 | |
| 68 | Install object marker assembly (OM-3R)(WFLX)GNDLL (658-7276) | EACH | 2 | $1,148.56 | $1,050.00 | $997.50 | $492.00 | $950.00 | $700.00 | |
| 69 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 56 | $3.90 | $29.02 | $26.00 | $25.20 | $24.00 | $24.00 | $29.00 |
| 70 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 760 | $0.78 | $3.32 | $4.00 | $2.90 | $2.75 | $2.75 | $3.30 |
| 71 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 960 | $0.78 | $3.32 | $4.00 | $2.90 | $2.75 | $2.75 | $3.30 |
| 72 | Reflectorized pavement marking type II (W)6"(solid)(020 mil) (666-7533) | LF | 1,609 | $0.65 | $2.12 | $2.00 | $1.85 | $1.75 | $2.00 | $2.00 |
| 73 | Reflectorized pavement marking type II (Y)6"(solid)(020 mil) (666-7537) | LF | 466 | $0.75 | $2.72 | $3.00 | $2.40 | $2.25 | $2.25 | $2.75 |
| 74 | Reflectorized pavement marker type I-C (672-7002) | EACH | 28 | $5.50 | $60.45 | $52.00 | $52.50 | $50.00 | $50.00 | $60.00 |
| 75 | Pavement surface preparation for marking (6") (678-7002) | LF | 20 | $0.09 | $42.32 | $40.00 | $36.75 | $35.00 | $35.00 | $42.00 |
| 76 | Temporary traffic signals (681-7001) | EACH | 6 | $15,000 | $11,486 | $9,000.00 | $12,500 | $5,000.00 | $4,010.00 | $1.00 |
| 77 | Bonding course (3007-7001) | GAL | 315 | $5.00 | $12.94 | $6.00 | $5.45 | $5.00 | $20.00 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.