TxDOT contract A00129572 bid tabulation
Construct New Roadway Lanes, SH 5 (NORTH OF COLLIN COUNTY OUTER LOOP to FM 455 w/TRANSITION N OF HACKBERRY DR). Let by Texas DOT on November 4, 2026, Collin, Dallas District. 4 bids received; low bid $35,766,135 by Mario Sinacola & Sons Excavating, Inc., -10% against the engineer's estimate of $39,930,214.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 215
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc. | $35,766,135 | Low | -10% |
| 2 | Ed Bell Construction Company | $36,656,931 | +2.0% | -8.0% |
| 3 | Tiseo Paving Co. | $38,169,956 | +7.0% | -4.0% |
| 4 | Harper Brothers Construction LLC | $40,441,503 | +13% | +1.0% |
Engineer's estimate: $39,930,214.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Mario Sinacola & Sons Excavating, Inc. | 2. Ed Bell Construction Company | 3. Tiseo Paving Co. | 4. Harper Brothers Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 138 | $13,632 | $10,865 | $4,000.00 | $8,190.00 | $6,000.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 36,199 | $12.50 | $10.00 | $10.00 | $15.30 | $6.50 |
| 3 | Removing concrete (pavers) (104-7010) | SY | 33 | $11.00 | $50.00 | $50.00 | $47.00 | $29.50 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 3,477 | $19.10 | $10.00 | $12.00 | $15.50 | $6.00 |
| 5 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 304 | $27.50 | $10.00 | $12.00 | $17.50 | $25.50 |
| 6 | Removing concrete (curb) (104-7016) | LF | 955 | $11.80 | $1.00 | $10.00 | $4.00 | $8.00 |
| 7 | Removing concrete (curb & gutter) (104-7017) | LF | 370 | $22.00 | $1.50 | $12.00 | $18.00 | $10.50 |
| 8 | Removing concrete (miscellaneous) (104-7045) | EACH | 7 | $1,900.00 | $1,000.00 | $1.00 | $1,490.00 | $577.00 |
| 9 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 8,363 | $5.50 | $5.00 | $10.00 | $7.65 | $6.00 |
| 10 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 35,107 | $8.50 | $5.00 | $11.00 | $7.90 | $6.00 |
| 11 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 43,710 | $15.00 | $6.00 | $13.50 | $11.30 | $7.50 |
| 12 | Excavation (roadway) (110-7001) | CY | 42,020 | $16.00 | $20.00 | $10.00 | $28.60 | $12.00 |
| 13 | Embankment (final)(DC)(type C1) (132-7008) | CY | 49,819 | $15.50 | $20.00 | $15.00 | $24.50 | $15.00 |
| 14 | Compost manuf topsoil (4") (161-7002) | SY | 98,042 | $2.35 | $1.00 | $1.10 | $3.75 | $1.50 |
| 15 | Block sodding (162-7002) | SY | 42,500 | $4.18 | $3.81 | $4.20 | $4.05 | $4.00 |
| 16 | Drill seed (permanent_urban_clay) (164-7012) | SY | 55,542 | $0.20 | $0.17 | $0.20 | $0.20 | $0.17 |
| 17 | Drill seed (temporary_warm_cool) (164-7015) | SY | 55,542 | $0.19 | $0.17 | $0.17 | $0.20 | $0.17 |
| 18 | Vegetative watering (168-7001) | TGL | 22,847 | $7.50 | $0.10 | $1.00 | $1.00 | $10.00 |
| 19 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 2,986 | $305.00 | $320.00 | $450.00 | $369.50 | $451.00 |
| 20 | Lime TRT (existing material)(8") (260-7007) | SY | 113,095 | $4.00 | $6.00 | $3.75 | $5.80 | $8.00 |
| 21 | Tack coat (292-7017) | GAL | 424 | $5.00 | $19.00 | $30.00 | $21.00 | $19.00 |
| 22 | SP mixes SP-B PG64-22 (344-7001) | TON | 24,066 | $105.00 | $108.20 | $115.25 | $119.00 | $110.00 |
| 23 | SP mixes SP-C PG64-22 (344-7009) | TON | 1,749 | $150.00 | $151.20 | $161.00 | $165.00 | $155.00 |
| 24 | Concrete pavement (CRCP) (11") (360-7005) | SY | 96,787 | $100.00 | $80.00 | $90.00 | $93.25 | $110.85 |
| 25 | Concrete pavement (CRCP)(hes) (11") (360-7050) | SY | 10,485 | $155.00 | $86.00 | $125.00 | $158.30 | $135.00 |
| 26 | Trench excavation protection (402-7001) | LF | 19,740 | $7.50 | $1.00 | $3.15 | $1.10 | $1.00 |
| 27 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 77 | $400.00 | $285.00 | $372.75 | $369.60 | $575.00 |
| 28 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 78 | $430.00 | $325.00 | $521.30 | $517.00 | $646.00 |
| 29 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 132 | $630.00 | $650.00 | $639.00 | $633.60 | $861.00 |
| 30 | Riprap (concrete)(5 in) (432-7002) | CY | 477 | $560.00 | $775.00 | $600.00 | $674.25 | $500.00 |
| 31 | Rail (type PR11) (450-7044) | LF | 2,468 | $136.00 | $130.00 | $160.00 | $150.00 | $165.00 |
| 32 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 2,638 | $275.00 | $290.00 | $190.00 | $264.00 | $315.00 |
| 33 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 1,249 | $360.00 | $325.00 | $225.00 | $304.00 | $365.00 |
| 34 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 134 | $380.00 | $345.00 | $255.00 | $347.50 | $460.00 |
| 35 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 99 | $555.00 | $720.00 | $390.00 | $500.50 | $700.00 |
| 36 | Concrete box culvert (7 FT X 5 FT) (462-7017) | LF | 144 | $770.00 | $870.00 | $525.00 | $772.00 | $830.00 |
| 37 | Concrete box culvert (8 FT X 5 FT) (462-7022) | LF | 302 | $850.00 | $920.00 | $595.00 | $882.00 | $900.00 |
| 38 | RC pipe (CL III)(18 in) (464-7003) | LF | 748 | $65.00 | $90.00 | $60.00 | $95.00 | $125.00 |
| 39 | RC pipe (CL III)(24 in) (464-7005) | LF | 15,190 | $90.00 | $102.00 | $70.00 | $119.00 | $152.00 |
| 40 | RC pipe (CL III)(30 in) (464-7007) | LF | 2,557 | $130.00 | $147.00 | $95.00 | $150.00 | $165.00 |
| 41 | RC pipe (CL III)(36 in) (464-7009) | LF | 1,458 | $167.00 | $175.00 | $120.00 | $191.00 | $203.00 |
| 42 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 4 | $5,300.00 | $3,500.00 | $7,100.00 | $5,887.00 | $9,983.50 |
| 43 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 3 | $6,300.00 | $7,200.00 | $7,700.00 | $8,026.00 | $10,430 |
| 44 | Inlet (complete)(pco)(3FT)(none) (465-7013) | EACH | 8 | $8,300.00 | $9,300.00 | $10,000 | $8,210.00 | $11,986 |
| 45 | Inlet (complete)(pco)(3FT)(left) (465-7014) | EACH | 34 | $8,500.00 | $11,125 | $11,000 | $9,187.00 | $12,906 |
| 46 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 40 | $8,500.00 | $11,000 | $11,000 | $9,135.00 | $13,087 |
| 47 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 6 | $8,750.00 | $11,750 | $12,000 | $9,715.00 | $13,173 |
| 48 | Inlet (complete)(pco)(4FT)(none) (465-7017) | EACH | 5 | $7,200.00 | $12,375 | $12,000 | $10,560 | $14,795 |
| 49 | Inlet (complete)(pco)(4FT)(left) (465-7018) | EACH | 18 | $7,400.00 | $12,750 | $13,000 | $10,455 | $15,025 |
| 50 | Inlet (complete)(pco)(4FT)(right) (465-7019) | EACH | 5 | $7,400.00 | $12,150 | $13,000 | $9,795.00 | $14,355 |
| 51 | Inlet (complete)(pco)(4FT)(both) (465-7020) | EACH | 5 | $7,500.00 | $15,350 | $14,000 | $11,088 | $16,843 |
| 52 | Inlet (complete)(pco)(6FT)(none) (465-7025) | EACH | 3 | $10,000 | $14,250 | $13,000 | $13,042 | $16,457 |
| 53 | Inlet (complete)(pco)(6FT)(left) (465-7026) | EACH | 2 | $10,300 | $14,800 | $14,000 | $12,567 | $17,115 |
| 54 | Inlet (complete)(pco)(6FT)(right) (465-7027) | EACH | 1 | $10,300 | $14,500 | $14,000 | $12,567 | $17,946 |
| 55 | Inlet (complete)(pcu)(4FT)(right) (465-7035) | EACH | 1 | $8,400.00 | $14,250 | $18,000 | $11,775 | $17,153 |
| 56 | Inlet (complete)(pcu)(4FT)(both) (465-7036) | EACH | 1 | $9,750.00 | $14,500 | $19,000 | $11,564 | $16,393 |
| 57 | Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070) | EACH | 1 | $8,000.00 | $8,000.00 | $8,500.00 | $6,810.00 | $12,181 |
| 58 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 34 | $6,560.00 | $7,600.00 | $8,000.00 | $6,890.00 | $8,560.50 |
| 59 | Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX5FT) (465-7130) | EACH | 5 | $8,000.00 | $9,800.00 | $9,000.00 | $9,135.00 | $12,150 |
| 60 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 2 | $12,000 | $11,500 | $10,000 | $6,573.00 | $12,912 |
| 61 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $15,275 | $14,250 | $12,000 | $9,240.00 | $14,717 |
| 62 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 2 | $21,500 | $19,750 | $16,000 | $14,570 | $20,270 |
| 63 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 5 | $26,000 | $28,000 | $24,000 | $19,900 | $25,872 |
| 64 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $28,000 | $37,500 | $32,000 | $25,715 | $31,352 |
| 65 | Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(P) (467-7043) | EACH | 2 | $4,750.00 | $11,000 | $11,000 | $3,062.00 | $6,000.00 |
| 66 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 6 | $1,700.00 | $4,400.00 | $2,000.00 | $3,800.00 | $4,935.50 |
| 67 | Removing structure (set) (496-7004) | EACH | 25 | $460.00 | $800.00 | $350.00 | $1,950.00 | $655.50 |
| 68 | Removing structure (wingwall) (496-7005) | EACH | 38 | $1,725.00 | $1,500.00 | $2,250.00 | $316.00 | $2,454.00 |
| 69 | Removing structure (headwall) (496-7006) | EACH | 19 | $1,650.00 | $1,500.00 | $1,650.00 | $739.00 | $2,454.00 |
| 70 | Removing structure (pipe) (496-7007) | LF | 1,650 | $20.00 | $35.00 | $40.00 | $12.50 | $19.50 |
| 71 | Removing structure (box culvert) (496-7008) | LF | 403 | $84.00 | $95.00 | $150.00 | $31.50 | $108.00 |
| 72 | Remove STR (rail) (496-7017) | LF | 5,602 | $16.00 | $15.00 | $1.00 | $1.00 | $4.50 |
| 73 | Mobilization (500-7001) | LS | 1 | $3,528,351 | $3,500,000 | $3,350,000 | $741,504 | $2,500,000 |
| 74 | Barricades, signs and traffic handling (502-7001) | MO | 32 | $30,000 | $27,500 | $42,000 | $38,945 | $32,500 |
| 75 | TMA (stationary) (505-7001) | DAY | 1,109 | $175.00 | $56.00 | $75.00 | $210.00 | $192.00 |
| 76 | TMA (mobile operation) (505-7002) | HR | 276 | $80.00 | $200.00 | $75.00 | $100.00 | $334.00 |
| 77 | Rock filter dams (install) (type 1) (506-7001) | LF | 192 | $38.00 | $35.00 | $63.90 | $121.00 | $30.00 |
| 78 | Rock filter dams (install) (type 2) (506-7002) | LF | 776 | $41.00 | $35.00 | $79.88 | $138.50 | $40.00 |
| 79 | Rock filter dams (install) (type 3) (506-7003) | LF | 490 | $61.00 | $40.00 | $133.13 | $105.50 | $65.00 |
| 80 | Rock filter dams (remove) (506-7011) | LF | 1,458 | $11.75 | $5.00 | $42.60 | $47.50 | $25.00 |
| 81 | Construction exits (install) (type 1) (506-7020) | SY | 328 | $30.00 | $31.00 | $42.60 | $31.50 | $24.00 |
| 82 | Construction exits (remove) (506-7024) | SY | 328 | $9.60 | $5.00 | $21.30 | $18.50 | $15.00 |
| 83 | Temporary sediment control fence (install) (506-7039) | LF | 15,722 | $3.80 | $3.15 | $4.26 | $3.15 | $2.00 |
| 84 | Temporary sediment control fence (remove) (506-7041) | LF | 15,722 | $0.95 | $0.10 | $2.13 | $1.50 | $1.00 |
| 85 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,924 | $5.50 | $4.50 | $6.39 | $5.25 | $5.50 |
| 86 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,924 | $1.40 | $0.25 | $3.20 | $2.65 | $1.50 |
| 87 | Constructing detours (508-7001) | SY | 25,823 | $80.00 | $60.00 | $71.00 | $74.00 | $60.00 |
| 88 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 5,650 | $40.00 | $12.00 | $11.00 | $21.00 | $25.00 |
| 89 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 5,150 | $38.00 | $40.00 | $14.00 | $25.00 | $25.00 |
| 90 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 540 | $64.00 | $40.00 | $95.00 | $33.00 | $90.00 |
| 91 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 3,580 | $8.70 | $10.00 | $9.00 | $6.25 | $6.50 |
| 92 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 420 | $13.50 | $10.00 | $28.00 | $13.50 | $12.50 |
| 93 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 5,650 | $15.00 | $5.00 | $11.00 | $14.25 | $12.50 |
| 94 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 5,740 | $14.00 | $5.00 | $14.00 | $16.50 | $13.50 |
| 95 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 500 | $15.00 | $5.00 | $25.00 | $19.30 | $13.00 |
| 96 | Concrete curb (mono) (type II) (529-7007) | LF | 53,199 | $6.60 | $1.50 | $4.00 | $3.00 | $2.00 |
| 97 | Concrete curb (dowel) (529-7014) | LF | 22 | $27.00 | $32.00 | $50.00 | $4.00 | $234.50 |
| 98 | Driveways (concrete) (530-7006) | SY | 2,261 | $95.00 | $89.00 | $85.00 | $104.00 | $104.00 |
| 99 | Driveways (concrete) (hes) (530-7007) | SY | 3,482 | $104.00 | $95.00 | $120.00 | $144.00 | $200.00 |
| 100 | Concrete sidewalks (4") (531-7001) | SY | 13,047 | $63.00 | $68.00 | $65.00 | $60.50 | $55.00 |
| 101 | Curb ramps (type 2) (531-7006) | EACH | 2 | $2,700.00 | $3,400.00 | $2,000.00 | $2,780.00 | $2,964.50 |
| 102 | Curb ramps (type 7) (531-7010) | EACH | 56 | $2,500.00 | $3,300.00 | $2,000.00 | $2,625.00 | $3,064.50 |
| 103 | Concrete median (536-7002) | SY | 1,384 | $80.00 | $69.00 | $105.00 | $147.50 | $67.50 |
| 104 | Concrete median (nose) (536-7005) | SY | 37 | $750.00 | $239.00 | $250.00 | $189.00 | $177.50 |
| 105 | Crash cushion attenuator (remove) (545-7004) | EACH | 18 | $1,100.00 | $1,500.00 | $750.00 | $2,112.00 | $775.00 |
| 106 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 18 | $9,040.00 | $3,200.00 | $9,500.00 | $10,560 | $7,669.00 |
| 107 | Chain link fence (remove) (550-7007) | LF | 946 | $5.00 | $5.00 | $5.25 | $1.00 | $5.00 |
| 108 | Gate (remove) (550-7016) | EACH | 7 | $450.00 | $400.00 | $525.00 | $100.00 | $500.00 |
| 109 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 22 | $607.00 | $685.00 | $2,127.34 | $580.00 | $500.00 |
| 110 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 3 | $331.50 | $235.00 | $1,341.90 | $230.00 | $215.00 |
| 111 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 1 | $352.00 | $275.00 | $410.03 | $250.00 | $230.00 |
| 112 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 405 | $17.90 | $10.00 | $20.50 | $20.25 | $26.50 |
| 113 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 450 | $18.50 | $12.00 | $22.55 | $22.25 | $28.50 |
| 114 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 220 | $30.00 | $15.00 | $27.97 | $27.50 | $31.00 |
| 115 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 1,825 | $41.00 | $27.00 | $47.93 | $47.50 | $53.50 |
| 116 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 225 | $21.00 | $13.00 | $27.57 | $27.25 | $27.50 |
| 117 | Electrical conductor (no.12) insulated (620-7004) | LF | 1,440 | $1.90 | $1.25 | $2.18 | $2.00 | $2.00 |
| 118 | Electrical conductor (no.8) bare (620-7007) | LF | 1,845 | $2.00 | $2.50 | $2.29 | $2.25 | $3.00 |
| 119 | Electrical conductor (no.8) insulated (620-7008) | LF | 4,380 | $2.20 | $2.65 | $2.34 | $2.25 | $3.00 |
| 120 | Electrical conductor (no.6) bare (620-7009) | LF | 245 | $2.35 | $3.00 | $2.81 | $2.75 | $4.00 |
| 121 | Electrical conductor (no.6) insulated (620-7010) | LF | 490 | $2.95 | $3.25 | $3.22 | $3.15 | $4.00 |
| 122 | Ground box type A (122311) (624-7001) | EACH | 5 | $1,170.00 | $1,150.00 | $1,800.38 | $1,785.00 | $1,517.00 |
| 123 | Ground box type C (162911) (624-7005) | EACH | 2 | $1,375.00 | $1,250.00 | $1,642.77 | $1,629.00 | $1,580.00 |
| 124 | Ground box type C (162911)W/apron (624-7006) | EACH | 22 | $1,650.00 | $1,450.00 | $1,981.81 | $1,965.00 | $2,155.00 |
| 125 | Remove electrical services (628-7002) | EACH | 2 | $845.00 | $400.00 | $757.74 | $750.00 | $770.00 |
| 126 | Elc SRV type D 120/240 060(NS)SS(E)TP(O) (628-7150) | EACH | 2 | $9,000.00 | $5,300.00 | $9,052.50 | $8,976.00 | $5,125.00 |
| 127 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 5 | $9,700.00 | $6,500.00 | $9,052.50 | $8,976.00 | $9,225.00 |
| 128 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 49 | $695.00 | $635.00 | $676.28 | $686.00 | $650.00 |
| 129 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 52 | $855.00 | $730.00 | $777.45 | $686.00 | $650.00 |
| 130 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 7 | $1,220.00 | $1,245.00 | $1,325.93 | $1,045.00 | $990.00 |
| 131 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 6 | $1,365.00 | $1,499.00 | $1,596.44 | $1,045.00 | $990.00 |
| 132 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 4 | $610.00 | $635.00 | $676.28 | $528.00 | $500.00 |
| 133 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 10 | $92.00 | $55.00 | $58.58 | $79.00 | $55.00 |
| 134 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 776 | $1.25 | $1.00 | $1.05 | $1.10 | $1.50 |
| 135 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 432 | $1.80 | $1.00 | $1.05 | $1.10 | $2.00 |
| 136 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 46,281 | $0.93 | $0.80 | $1.05 | $1.10 | $1.50 |
| 137 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 6,280 | $1.45 | $1.50 | $1.84 | $1.80 | $2.00 |
| 138 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 184 | $2.50 | $3.00 | $3.41 | $3.45 | $3.50 |
| 139 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 3,523 | $7.50 | $2.50 | $5.88 | $5.90 | $7.00 |
| 140 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 72 | $155.00 | $39.00 | $126.00 | $126.75 | $155.00 |
| 141 | Work zone pavement marking removing (W)(RR crossing) (662-7088) | EACH | 2 | $370.00 | $150.00 | $367.50 | $369.60 | $695.00 |
| 142 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 69 | $250.00 | $39.00 | $143.85 | $144.70 | $175.00 |
| 143 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 72,465 | $0.95 | $0.80 | $1.05 | $1.10 | $1.50 |
| 144 | Work zone pavement marking removing (Y)24"(solid) (662-7105) | LF | 74 | $8.10 | $3.00 | $5.88 | $5.90 | $7.50 |
| 145 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 542 | $1.65 | $0.65 | $1.05 | $1.10 | $2.00 |
| 146 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 13,222 | $0.98 | $0.90 | $1.26 | $1.25 | $0.88 |
| 147 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 3,408 | $3.75 | $2.75 | $3.94 | $3.95 | $3.00 |
| 148 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 3,785 | $7.50 | $6.50 | $8.14 | $8.20 | $6.50 |
| 149 | Pavement sler 6" (666-7347) | LF | 89,504 | $0.17 | $0.16 | $0.24 | $0.25 | $0.19 |
| 150 | Pavement sler 8" (666-7348) | LF | 11,428 | $0.29 | $0.25 | $0.47 | $0.50 | $0.28 |
| 151 | Pavement sler 12" (666-7350) | LF | 3,174 | $1.11 | $0.95 | $1.31 | $1.30 | $0.36 |
| 152 | Pavement sler 24" (666-7352) | LF | 3,785 | $1.60 | $1.20 | $2.10 | $2.10 | $0.72 |
| 153 | Pavement sler (arrow) (666-7353) | EACH | 55 | $32.75 | $15.00 | $57.75 | $58.00 | $10.00 |
| 154 | Pavement sler (word) (666-7354) | EACH | 55 | $49.00 | $15.00 | $63.00 | $63.30 | $10.00 |
| 155 | Pavement sler (LN reduct arrow) (666-7359) | EACH | 2 | $62.50 | $20.00 | $68.25 | $68.60 | $20.00 |
| 156 | Pavement sler (RR crossing) (666-7364) | EACH | 5 | $100.00 | $20.00 | $105.00 | $105.50 | $95.00 |
| 157 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 8,760 | $0.61 | $0.55 | $0.79 | $0.80 | $0.65 |
| 158 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 38,812 | $0.60 | $0.53 | $0.74 | $0.75 | $0.57 |
| 159 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 41,390 | $0.60 | $0.53 | $0.74 | $0.75 | $0.57 |
| 160 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 55 | $215.00 | $190.00 | $262.50 | $264.00 | $195.00 |
| 161 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $450.00 | $400.00 | $336.00 | $338.00 | $955.00 |
| 162 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 55 | $260.00 | $270.00 | $300.30 | $302.00 | $215.00 |
| 163 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 5 | $690.00 | $350.00 | $756.00 | $760.00 | $775.00 |
| 164 | Reflectorized pavement marker type I-C (672-7002) | EACH | 606 | $5.20 | $3.80 | $5.78 | $5.80 | $4.00 |
| 165 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 127 | $5.20 | $3.80 | $5.78 | $5.80 | $4.00 |
| 166 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 444 | $4.60 | $3.80 | $5.78 | $5.80 | $4.00 |
| 167 | Eliminating existing PM & markers (4") (677-7001) | LF | 31,210 | $0.56 | $0.51 | $0.77 | $0.75 | $0.55 |
| 168 | Eliminating existing PM & markers (8") (677-7004) | LF | 3,000 | $1.00 | $0.68 | $0.91 | $0.90 | $0.75 |
| 169 | Eliminating existing PM & markers (12") (677-7006) | LF | 120 | $2.00 | $2.00 | $1.05 | $1.10 | $1.50 |
| 170 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 6 | $58.00 | $45.00 | $57.75 | $58.00 | $65.00 |
| 171 | Eliminating existing PM & markers (word) (677-7015) | EACH | 6 | $67.00 | $46.00 | $63.00 | $63.25 | $65.00 |
| 172 | Pavement surface preparation for marking (6") (678-7002) | LF | 89,504 | $0.13 | $0.18 | $0.21 | $0.25 | $0.06 |
| 173 | Pavement surface preparation for marking (8") (678-7004) | LF | 13,222 | $0.18 | $0.18 | $0.39 | $0.40 | $0.09 |
| 174 | Pavement surface preparation for marking (12") (678-7006) | LF | 3,174 | $0.64 | $0.40 | $1.05 | $1.10 | $0.12 |
| 175 | Pavement surface preparation for marking (24") (678-7008) | LF | 3,047 | $0.75 | $0.45 | $1.26 | $1.30 | $0.24 |
| 176 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 57 | $17.90 | $10.00 | $42.00 | $42.25 | $7.50 |
| 177 | Pavement surface preparation for marking (word) (678-7016) | EACH | 55 | $18.50 | $10.00 | $52.50 | $52.50 | $7.50 |
| 178 | Pavement surface preparation for marking (RR crossing) (678-7020) | EACH | 5 | $62.00 | $25.00 | $78.75 | $79.00 | $55.00 |
| 179 | Install highway traffic signal (isolated) (680-7002) | EACH | 5 | $39,000 | $48,000 | $72,420 | $71,810 | $46,125 |
| 180 | Removing traffic signals (680-7004) | EACH | 5 | $6,590.00 | $8,500.00 | $10,921 | $10,825 | $4,100.00 |
| 181 | Temporary traffic signals (681-7001) | EACH | 5 | $115,000 | $73,000 | $69,119 | $68,535 | $71,750 |
| 182 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 38 | $345.00 | $325.00 | $401.10 | $395.00 | $615.00 |
| 183 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 16 | $350.00 | $325.00 | $401.10 | $395.00 | $615.00 |
| 184 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 38 | $335.00 | $325.00 | $399.36 | $395.00 | $615.00 |
| 185 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 20 | $365.00 | $325.00 | $401.23 | $395.00 | $615.00 |
| 186 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 38 | $335.00 | $325.00 | $399.14 | $395.00 | $615.00 |
| 187 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 20 | $370.00 | $325.00 | $401.27 | $395.00 | $615.00 |
| 188 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 30 | $806.00 | $650.00 | $881.49 | $875.00 | $1,025.00 |
| 189 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 32 | $250.00 | $150.00 | $283.96 | $280.00 | $205.00 |
| 190 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 6 | $280.00 | $205.00 | $356.65 | $350.00 | $215.50 |
| 191 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 10 | $265.00 | $225.00 | $326.03 | $323.00 | $226.00 |
| 192 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 4,223 | $3.00 | $2.75 | $3.75 | $3.75 | $3.00 |
| 193 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 539 | $3.40 | $3.00 | $4.19 | $4.10 | $3.00 |
| 194 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 2,980 | $6.00 | $5.40 | $8.39 | $8.30 | $7.00 |
| 195 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 4,395 | $2.80 | $2.50 | $3.57 | $3.55 | $3.00 |
| 196 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 2 | $12,150 | $11,600 | $13,632 | $13,517 | $14,250 |
| 197 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 3 | $15,600 | $12,200 | $15,970 | $15,835 | $14,660 |
| 198 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 2 | $13,400 | $12,700 | $18,100 | $17,945 | $15,000 |
| 199 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $14,650 | $13,800 | $18,371 | $18,215 | $16,400 |
| 200 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $15,500 | $14,700 | $18,584 | $18,425 | $17,335 |
| 201 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 3 | $16,600 | $14,800 | $20,113 | $19,940 | $17,530 |
| 202 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 2 | $35,800 | $32,000 | $44,725 | $44,345 | $37,105 |
| 203 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 2 | $39,000 | $32,800 | $45,790 | $45,405 | $38,235 |
| 204 | Ins traffic signal PL AM(S)1 arm(65')lum (686-7067) | EACH | 2 | $39,000 | $33,100 | $46,061 | $45,674 | $38,745 |
| 205 | Pedestrian pole assembly (687-7001) | EACH | 14 | $2,970.00 | $2,500.00 | $3,028.66 | $3,003.00 | $5,125.00 |
| 206 | Pedestrian detect push button (APS) (688-7001) | EACH | 30 | $940.00 | $800.00 | $1,248.65 | $1,238.00 | $1,025.00 |
| 207 | Pedestrian detector controller unit (688-7003) | EACH | 4 | $4,100.00 | $3,515.00 | $4,754.34 | $4,715.00 | $6,150.00 |
| 208 | Remove roadway illum assembly (HPS) (690-7163) | EACH | 5 | $410.00 | $350.00 | $1,059.68 | $1,050.00 | $670.00 |
| 209 | Full - width mowing (730-7019) | CYC | 3 | $4,500.00 | $2,000.00 | $10,000 | $15,840 | $6,500.00 |
| 210 | Litter removal (734-7002) | CYC | 3 | $2,000.00 | $750.00 | $3,000.00 | $3,895.00 | $2,078.50 |
| 211 | VIVDS temporary (6006-7006) | EACH | 5 | $37,000 | $43,000 | $7,987.50 | $7,920.00 | $30,750 |
| 212 | Bbu system (external battery cabinet) (6007-7001) | EACH | 5 | $880.00 | $9,500.00 | $10,645 | $10,555 | $8,200.00 |
| 213 | RVDS (presence detection only) (6008-7001) | EACH | 16 | $8,300.00 | $12,150 | $8,786.25 | $8,710.00 | $12,710 |
| 214 | RVDS (advance detection only) (6008-7002) | EACH | 10 | $9,000.00 | $8,200.00 | $10,913 | $10,820 | $12,710 |
| 215 | Portable changeable message sign (6033-7001) | EACH | 2 | $13,500 | $9,500.00 | $10,000 | $22,442 | $13,034 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.