| 1 | Preparing row (100-7002) | STA | 289 | $2,500.00 | $500.00 | $930.60 | $1,000.00 |
| 2 | Removing concrete (mowstrip) (104-7003) | SY | 340 | $13.00 | $10.00 | $9.90 | $25.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 928 | $22.00 | $20.00 | $16.50 | $25.00 |
| 4 | Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010) | SY | 50,932 | $11.00 | $4.00 | $6.53 | $5.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 48,832 | $25.00 | $15.00 | $18.70 | $24.00 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 32,075 | $30.00 | $12.00 | $18.70 | $50.00 |
| 7 | Blading (150-7002) | HR | 40 | $150.00 | $150.00 | $99.00 | $225.00 |
| 8 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 5,000 | $2.00 | $0.15 | $0.25 | $0.20 |
| 9 | Drill seed (permanent_rural_clay) (164-7010) | SY | 692,953 | $0.20 | $0.10 | $0.13 | $0.20 |
| 10 | Drill seed (temporary_warm) (164-7013) | SY | 173,241 | $0.25 | $0.05 | $0.05 | $0.20 |
| 11 | Drill seed (temporary_cool) (164-7014) | SY | 173,241 | $0.25 | $0.05 | $0.05 | $0.20 |
| 12 | Vegetative watering (168-7001) | TGL | 5,884.20 | $35.00 | $15.00 | $23.10 | $20.00 |
| 13 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 54,553 | $100.00 | $95.00 | $85.05 | $75.00 |
| 14 | Rework BS metal (type C)(12")(ord comp) (251-7055) | SY | 4,000 | $8.00 | $2.50 | $4.40 | $4.00 |
| 15 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 3,152 | $255.00 | $315.00 | $363.00 | $380.00 |
| 16 | Lime TRT (subgrade) (8") (260-7020) | SY | 197,418 | $12.00 | $2.45 | $3.30 | $14.00 |
| 17 | Asphalt (RC-250) (316-7016) | GAL | 38,374 | $7.00 | $5.00 | $5.17 | $5.50 |
| 18 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 1,382 | $215.00 | $120.00 | $96.22 | $138.00 |
| 19 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 1,491 | $195.00 | $130.00 | $142.94 | $150.00 |
| 20 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 65,224 | $4.50 | $3.50 | $4.35 | $4.50 |
| 21 | D-GR HMA type-B PG64-22 (341-7001) | TON | 31,545 | $98.00 | $85.00 | $96.80 | $121.00 |
| 22 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 44,677 | $130.00 | $90.00 | $107.80 | $144.00 |
| 23 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 10,807 | $130.00 | $100.00 | $107.80 | $150.00 |
| 24 | Tack coat (341-7082) | GAL | 45,598 | $3.00 | $4.00 | $3.30 | $4.50 |
| 25 | Flexible pavement structure repair(10") (351-7009) | SY | 500 | $95.00 | $100.00 | $105.27 | $172.00 |
| 26 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 2,428 | $2.00 | $4.00 | $3.30 | $7.00 |
| 27 | Cut & restoring pavement (400-7006) | SY | 452 | $90.00 | $50.00 | $230.00 | $65.00 |
| 28 | Cem stabil BKFL (400-7010) | CY | 1,153 | $200.00 | $123.00 | $200.00 | $165.00 |
| 29 | Temporary special shoring (403-7001) | SF | 3,796 | $50.00 | $25.00 | $15.00 | $30.00 |
| 30 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 180 | $360.00 | $250.00 | $235.00 | $350.00 |
| 31 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 18 | $500.00 | $225.00 | $220.00 | $400.00 |
| 32 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 108 | $360.00 | $300.00 | $280.00 | $585.00 |
| 33 | Riprap (concrete)(5 in) (432-7002) | CY | 38 | $600.00 | $700.00 | $630.00 | $605.00 |
| 34 | Riprap (stone protection)(12 in) (432-7041) | CY | 430 | $250.00 | $200.00 | $200.00 | $285.00 |
| 35 | Rail (type T631) (450-7020) | LF | 260 | $80.00 | $115.00 | $100.00 | $115.00 |
| 36 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 924 | $460.00 | $550.00 | $365.00 | $1,000.00 |
| 37 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 318 | $470.00 | $475.00 | $420.00 | $1,025.00 |
| 38 | Concrete box culvert (7 FT X 3 FT) (462-7015) | LF | 569 | $780.00 | $850.00 | $600.00 | $1,600.00 |
| 39 | RC pipe (CL III)(18 in) (464-7003) | LF | 4,672 | $100.00 | $75.00 | $65.00 | $200.00 |
| 40 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,778 | $120.00 | $95.00 | $90.00 | $240.00 |
| 41 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 1 | $40,000 | $10,000 | $5,200.00 | $7,500.00 |
| 42 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $40,000 | $38,000 | $24,000 | $27,500 |
| 43 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $55,000 | $40,000 | $27,000 | $30,250 |
| 44 | Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(C) (467-7097) | EACH | 21 | $10,500 | $5,500.00 | $5,400.00 | $1,500.00 |
| 45 | Set (type I)(S= 5 FT)(HW= 4 FT)(6:1)(C) (467-7101) | EACH | 6 | $10,300 | $8,000.00 | $8,500.00 | $5,000.00 |
| 46 | Set (type I)(S= 7 FT)(HW= 4 FT)(6:1)(C) (467-7155) | EACH | 4 | $13,000 | $10,000 | $11,000 | $6,250.00 |
| 47 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 244 | $2,000.00 | $1,800.00 | $2,400.00 | $3,500.00 |
| 48 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 6 | $2,800.00 | $2,800.00 | $3,800.00 | $3,750.00 |
| 49 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 82 | $2,300.00 | $2,000.00 | $3,900.00 | $3,750.00 |
| 50 | Removing structure (box culvert) (496-7001) | EACH | 2 | $17,000 | $5,000.00 | $17,500 | $4,500.00 |
| 51 | Removing structure (small) (496-7036) | EACH | 97 | $1,600.00 | $500.00 | $500.00 | $1,000.00 |
| 52 | Mobilization (500-7001) | LS | 1 | $3,000,000 | $2,450,000 | $2,223,897 | $1,000,000 |
| 53 | Barricades, signs and traffic handling (502-7001) | MO | 29 | $3,500.00 | $5,000.00 | $7,696.47 | $5,000.00 |
| 54 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $15,000 | $5,000.00 | $20,500 |
| 55 | TMA (stationary) (505-7001) | DAY | 435 | $250.00 | $250.00 | $250.00 | $215.00 |
| 56 | TMA (mobile operation) (505-7003) | DAY | 60 | $250.00 | $25.00 | $350.00 | $675.00 |
| 57 | Rock filter dams (install) (type 1) (506-7001) | LF | 1,540 | $45.00 | $30.00 | $44.53 | $80.00 |
| 58 | Rock filter dams (remove) (506-7011) | LF | 1,540 | $13.00 | $10.00 | $40.90 | $20.00 |
| 59 | Sandbags for erosion control (506-7035) | EACH | 100 | $15.00 | $10.00 | $22.04 | $35.00 |
| 60 | Temporary sediment control fence (install) (506-7039) | LF | 8,590 | $3.00 | $3.50 | $3.32 | $10.00 |
| 61 | Temporary sediment control fence (remove) (506-7041) | LF | 8,590 | $1.50 | $1.00 | $0.85 | $2.00 |
| 62 | Constructing detours (508-7001) | SY | 2,245 | $125.00 | $7.00 | $13.20 | $15.00 |
| 63 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 360 | $75.00 | $75.00 | $45.00 | $120.00 |
| 64 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 150 | $50.00 | $75.00 | $64.00 | $10.00 |
| 65 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 360 | $30.00 | $50.00 | $25.00 | $30.00 |
| 66 | Colored textured concrete (6") (527-7003) | SY | 548 | $225.00 | $130.00 | $90.00 | $105.00 |
| 67 | Concrete curb (type II) (529-7002) | LF | 730 | $25.00 | $25.00 | $30.00 | $25.00 |
| 68 | Driveways (concrete) (530-7006) | SY | 1,033 | $100.00 | $95.00 | $96.00 | $120.00 |
| 69 | Driveways (ACP) (530-7010) | SY | 346 | $200.00 | $75.00 | $35.20 | $90.00 |
| 70 | Driveways (surface treat) (530-7016) | SY | 7,115 | $40.00 | $45.00 | $35.20 | $25.00 |
| 71 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 58,220 | $0.50 | $0.20 | $0.18 | $0.20 |
| 72 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 52,768 | $0.50 | $0.20 | $0.18 | $0.25 |
| 73 | Metal W-beam guard fence (timber post) (540-7001) | LF | 340 | $30.00 | $30.00 | $28.99 | $32.00 |
| 74 | Remove metal beam guard fence (542-7001) | LF | 400 | $5.00 | $3.25 | $3.10 | $2.00 |
| 75 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $4,000.00 | $3,679.00 | $4,375.00 |
| 76 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $250.00 | $375.00 | $375.00 | $175.00 |
| 77 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 16 | $2,000.00 | $900.00 | $1,450.00 | $1,750.00 |
| 78 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $800.00 | $900.00 | $1,300.00 | $1,125.00 |
| 79 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 4 | $8,500.00 | $10,000 | $8,800.00 | $8,800.00 |
| 80 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 13 | $450.00 | $500.00 | $500.00 | $550.00 |
| 81 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 45 | $250.00 | $175.00 | $175.00 | $275.00 |
| 82 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 7 | $300.00 | $185.00 | $185.00 | $300.00 |
| 83 | In RD IL (type SA) 50T-8 (400W EQ) LED (610-7196) | EACH | 18 | $3,500.00 | $5,200.00 | $5,112.00 | $7,000.00 |
| 84 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 4,585 | $22.00 | $10.25 | $10.26 | $25.00 |
| 85 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 1,715 | $15.00 | $14.50 | $14.26 | $30.00 |
| 86 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 140 | $13.50 | $16.50 | $16.40 | $30.00 |
| 87 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 530 | $35.00 | $15.00 | $14.98 | $30.00 |
| 88 | Electrical conductor (no.8) bare (620-7007) | LF | 3,450 | $2.00 | $2.25 | $2.16 | $4.00 |
| 89 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,950 | $2.40 | $2.50 | $2.38 | $4.00 |
| 90 | Electrical conductor (no.6) bare (620-7009) | LF | 3,555 | $2.40 | $2.75 | $2.74 | $4.00 |
| 91 | Electrical conductor (no.6) insulated (620-7010) | LF | 7,510 | $2.60 | $3.25 | $3.07 | $4.00 |
| 92 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 4,071 | $4.00 | $3.25 | $3.25 | $4.00 |
| 93 | Ground box type A (122311)W/apron (624-7002) | EACH | 18 | $1,350.00 | $1,000.00 | $985.00 | $1,525.00 |
| 94 | Ground box type D (162922)W/apron (624-7008) | EACH | 16 | $1,250.00 | $1,150.00 | $1,125.00 | $2,150.00 |
| 95 | Remove ground box (624-7013) | EACH | 3 | $550.00 | $50.00 | $50.00 | $350.00 |
| 96 | Remove electrical services (628-7002) | EACH | 2 | $1,000.00 | $100.00 | $100.00 | $600.00 |
| 97 | Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009) | EACH | 2 | $10,000 | $8,500.00 | $8,350.00 | $11,250 |
| 98 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $8,600.00 | $8,000.00 | $7,975.00 | $11,250 |
| 99 | Elc SRV type T 120/240 000(NS)GS(N)SP(O) (628-7326) | EACH | 3 | $8,600.00 | $6,500.00 | $6,490.00 | $7,500.00 |
| 100 | Aluminum signs (type A) (636-7001) | SF | 57 | $30.00 | $34.00 | $27.50 | $35.00 |
| 101 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 4 | $650.00 | $750.00 | $750.00 | $925.00 |
| 102 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 13 | $800.00 | $725.00 | $725.00 | $935.00 |
| 103 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $950.00 | $1,000.00 | $1,000.00 | $1,025.00 |
| 104 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 1 | $1,000.00 | $1,200.00 | $1,200.00 | $1,450.00 |
| 105 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 25 | $450.00 | $475.00 | $465.00 | $500.00 |
| 106 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 9 | $500.00 | $525.00 | $520.00 | $575.00 |
| 107 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 3 | $750.00 | $450.00 | $400.00 | $550.00 |
| 108 | Relocate SM RD SN sup&AM type TWT (644-7068) | EACH | 2 | $200.00 | $300.00 | $300.00 | $550.00 |
| 109 | Relocate SM RD SN sup&AM(sign only) (644-7072) | EACH | 4 | $270.00 | $100.00 | $100.00 | $120.00 |
| 110 | Remove SM RD SN sup&AM (644-7073) | EACH | 61 | $100.00 | $100.00 | $100.00 | $120.00 |
| 111 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 12 | $30.00 | $25.00 | $25.00 | $30.00 |
| 112 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 22 | $60.00 | $80.00 | $76.00 | $120.00 |
| 113 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 117,350 | $1.00 | $0.30 | $0.30 | $1.00 |
| 114 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 120 | $12.00 | $25.00 | $25.00 | $12.00 |
| 115 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 8,700 | $1.60 | $1.00 | $0.88 | $1.50 |
| 116 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 160,780 | $1.00 | $0.30 | $0.30 | $1.00 |
| 117 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,890 | $2.00 | $1.00 | $1.53 | $1.25 |
| 118 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,890 | $2.00 | $1.00 | $1.53 | $1.25 |
| 119 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,880 | $2.00 | $1.20 | $1.20 | $1.00 |
| 120 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 13,926 | $1.20 | $0.90 | $0.88 | $1.00 |
| 121 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 58,220 | $1.10 | $0.75 | $0.72 | $1.00 |
| 122 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 12,792 | $1.20 | $0.90 | $0.88 | $1.00 |
| 123 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 59,818 | $1.10 | $0.75 | $0.72 | $1.00 |
| 124 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 32 | $15.00 | $50.00 | $50.00 | $16.00 |
| 125 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 68 | $250.00 | $125.00 | $125.00 | $295.00 |
| 126 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 8 | $400.00 | $275.00 | $275.00 | $350.00 |
| 127 | Reflectorized pavement marker type I-C (672-7002) | EACH | 794 | $11.00 | $7.50 | $7.50 | $5.00 |
| 128 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,672 | $11.00 | $7.50 | $7.50 | $5.00 |
| 129 | Eliminating existing PM & markers (4") (677-7001) | LF | 63,584 | $0.50 | $3.00 | $0.37 | $0.50 |
| 130 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $20,000 | $17,000 | $16,548 | $18,750 |
| 131 | Removing traffic signals (680-7004) | EACH | 1 | $8,000.00 | $5,000.00 | $5,000.00 | $11,250 |
| 132 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 16 | $300.00 | $350.00 | $340.00 | $450.00 |
| 133 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 6 | $300.00 | $350.00 | $340.00 | $450.00 |
| 134 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 16 | $300.00 | $350.00 | $340.00 | $450.00 |
| 135 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 6 | $300.00 | $340.00 | $340.00 | $450.00 |
| 136 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 16 | $300.00 | $340.00 | $340.00 | $450.00 |
| 137 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 6 | $300.00 | $340.00 | $340.00 | $450.00 |
| 138 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 22 | $180.00 | $180.00 | $180.00 | $200.00 |
| 139 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 5,214 | $3.40 | $4.75 | $4.64 | $6.00 |
| 140 | Install RDSD flash beacon assembly (685-7001) | EACH | 3 | $5,300.00 | $6,500.00 | $6,355.00 | $10,000 |
| 141 | Remove RDSD flash beacon assembly (685-7003) | EACH | 1 | $1,000.00 | $150.00 | $150.00 | $1,000.00 |
| 142 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 3 | $13,000 | $14,125 | $14,125 | $21,150 |
| 143 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 3 | $13,500 | $15,500 | $15,106 | $21,150 |
| 144 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 1 | $15,000 | $15,500 | $15,440 | $21,150 |
| 145 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $15,000 | $16,000 | $15,832 | $21,150 |
| 146 | Install radar vehicle detection system (690-7134) | EACH | 14 | $3,500.00 | $10,000 | $9,132.18 | $11,750 |
| 147 | Full - width mowing (730-7022) | ACRE | 143.20 | $40.00 | $80.00 | $70.00 | $900.00 |
| 148 | TMSP radar speed control monitor (6025-7001) | EACH | 2 | $12,000 | $5,000.00 | $7,500.00 | $17,500 |