TxDOT contract A00199843 bid tabulation
Rehabilitate Existing Roadway, FM 2448 (SH 17 to IH 10). Let by Texas DOT on August 6, 2026, Reeves, Odessa District. 5 bids received; low bid $8,604,312 by Dan Williams Company, -2.7% against the engineer's estimate of $8,844,235.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 95
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dan Williams Company | $8,604,312 | Low | -3.0% |
| 2 | FNF Construction, Inc. | $9,182,210 | +7.0% | +4.0% |
| 3 | A. L. Helmcamp, Inc. | $9,411,559 | +9.0% | +6.0% |
| 4 | Jones Bros. Dirt & Paving Contractors, Inc. | $10,147,938 | +18% | +15% |
| 5 | Ragle Construction, Inc. | $10,673,571 | +24% | +21% |
Engineer's estimate: $8,844,235.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dan Williams Company | 2. FNF Construction, Inc. | 3. A. L. Helmcamp, Inc. | 4. Jones Bros. Dirt & Paving Contractors, Inc. | 5. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Subgr widen (OC) (112-7001) | STA | 313.30 | $800.00 | $935.00 | $1,000.00 | $225.00 | $1,100.00 | $772.00 |
| 2 | Embankment (final)(OC)(type B) (132-7003) | CY | 3,500 | $25.00 | $11.50 | $10.00 | $50.00 | $46.00 | $32.00 |
| 3 | Backfill (type B) (134-7002) | STA | 313.30 | $400.00 | $75.00 | $135.00 | $150.00 | $221.00 | $432.00 |
| 4 | Blading (150-7002) | HR | 70 | $300.00 | $161.75 | $210.00 | $250.00 | $425.00 | $159.00 |
| 5 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 42,575 | $0.25 | $0.09 | $0.28 | $0.27 | $0.10 | $0.27 |
| 6 | Proof rolling (216-7001) | HR | 70 | $200.00 | $88.25 | $120.00 | $215.00 | $175.00 | $106.50 |
| 7 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 70,866 | $12.00 | $10.50 | $12.00 | $16.00 | $14.50 | $9.50 |
| 8 | Prime coat (MC-30) (310-7004) | GAL | 14,177 | $5.00 | $5.50 | $7.75 | $5.00 | $5.70 | $6.00 |
| 9 | Asphalt (AC-20-5TR) (316-7007) | GAL | 53,857 | $3.00 | $3.75 | $6.00 | $5.00 | $4.31 | $6.00 |
| 10 | Aggregate (type-PB, GR-4)(sac-A) (316-7136) | CY | 1,182 | $135.00 | $163.00 | $120.00 | $250.00 | $174.00 | $160.00 |
| 11 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 2,569 | $110.00 | $210.00 | $160.00 | $215.00 | $224.00 | $200.00 |
| 12 | Tack coat (341-7082) | GAL | 12,366 | $6.00 | $4.50 | $5.00 | $5.00 | $5.35 | $7.44 |
| 13 | Tom-C PG76-22 sac-A (347-7001) | TON | 8,967 | $180.00 | $195.00 | $140.00 | $180.00 | $165.00 | $220.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 1,030 | $300.00 | $295.00 | $250.00 | $330.00 | $247.50 | $133.00 |
| 15 | Drilled shaft (36 in) (416-7006) | LF | 410 | $375.00 | $475.00 | $850.00 | $300.00 | $660.00 | $416.00 |
| 16 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 176 | $460.00 | $285.00 | $300.00 | $290.00 | $440.00 | $275.00 |
| 17 | Class C concrete (abutment)(HPC) (420-7013) | CY | 54.60 | $2,400.00 | $1,400.00 | $2,200.00 | $2,000.00 | $1,601.60 | $946.00 |
| 18 | Class C concrete (cap)(HPC) (420-7023) | CY | 42.40 | $2,500.00 | $2,250.00 | $2,100.00 | $2,500.00 | $1,797.18 | $1,315.00 |
| 19 | Class C concrete (column) (420-7038) | CY | 11.50 | $2,000.00 | $1,950.00 | $1,700.00 | $2,800.00 | $2,045.12 | $2,075.00 |
| 20 | Reinforced concrete slab (HPC) (422-7002) | SF | 8,050 | $35.00 | $41.00 | $40.50 | $40.00 | $32.42 | $30.50 |
| 21 | Approach slab (HPC) (422-7014) | CY | 91.50 | $1,075.00 | $850.00 | $1,000.00 | $1,300.00 | $1,165.78 | $719.00 |
| 22 | Prestressed concrete girder (TX28) (425-7001) | LF | 1,040.90 | $305.00 | $250.00 | $300.00 | $275.00 | $275.00 | $244.00 |
| 23 | Riprap (concrete)(5 in) (432-7002) | CY | 105.70 | $1,200.00 | $725.00 | $650.00 | $850.00 | $577.50 | $750.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 36 | $750.00 | $800.00 | $850.00 | $914.00 | $577.50 | $750.00 |
| 25 | Rail (type SSTR)(HPC) (450-7025) | LF | 398 | $125.00 | $90.00 | $150.00 | $250.00 | $126.50 | $112.00 |
| 26 | Armor joint (sealed) (454-7003) | LF | 87 | $150.00 | $135.00 | $175.00 | $250.00 | $159.50 | $149.00 |
| 27 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 144 | $400.00 | $400.00 | $600.00 | $508.00 | $405.02 | $578.00 |
| 28 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 308 | $425.00 | $415.00 | $850.00 | $575.00 | $478.94 | $561.00 |
| 29 | RC pipe (CL IV)(24 in) (464-7021) | LF | 1,940 | $180.00 | $135.00 | $200.00 | $183.00 | $180.31 | $163.00 |
| 30 | RC pipe (CL IV)(36 in) (464-7024) | LF | 248 | $200.00 | $250.00 | $300.00 | $279.00 | $325.38 | $255.00 |
| 31 | Set (type I)(S= 3 FT)(HW= 2 FT)(6:1)(C) (467-7038) | EACH | 6 | $7,500.00 | $10,000 | $10,000 | $6,350.00 | $8,608.60 | $12,100 |
| 32 | Set (type I)(S= 4 FT)(HW= 2 FT)(6:1)(C) (467-7065) | EACH | 10 | $9,000.00 | $10,000 | $11,000 | $9,350.00 | $8,762.60 | $11,800 |
| 33 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 1 | $2,500.00 | $2,000.87 | $1,500.00 | $1,450.00 | $2,767.38 | $2,900.00 |
| 34 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 8 | $2,500.00 | $1,800.00 | $1,800.00 | $1,800.00 | $3,050.74 | $2,900.00 |
| 35 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 64 | $3,000.00 | $1,800.00 | $2,100.00 | $2,300.00 | $3,495.80 | $2,900.00 |
| 36 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $3,000.00 | $1,900.00 | $2,100.00 | $2,300.00 | $3,495.80 | $2,900.00 |
| 37 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $4,000.00 | $3,090.00 | $5,000.00 | $4,000.00 | $5,132.82 | $4,700.00 |
| 38 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 8 | $4,800.00 | $3,800.00 | $5,200.00 | $5,100.00 | $7,747.74 | $6,800.00 |
| 39 | Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367) | EACH | 4 | $5,300.00 | $4,600.00 | $7,000.00 | $6,600.00 | $9,346.26 | $6,800.00 |
| 40 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 20 | $180.00 | $160.00 | $200.00 | $165.00 | $137.50 | $150.00 |
| 41 | Thermoplastic pipe (PP) (30") (468-7003) | LF | 20 | $190.00 | $175.00 | $250.00 | $185.00 | $137.50 | $245.00 |
| 42 | Clean existing culverts (480-7001) | EACH | 7 | $2,500.00 | $3,000.00 | $3,500.00 | $1,575.00 | $3,850.00 | $2,850.00 |
| 43 | Removing structure (box culvert) (496-7001) | EACH | 2 | $3,000.00 | $2,500.00 | $10,000 | $11,000 | $2,750.00 | $5,000.00 |
| 44 | Removing structure (set) (496-7004) | EACH | 9 | $900.00 | $500.00 | $1,000.00 | $775.00 | $1,320.00 | $1,045.00 |
| 45 | Removing structure (wingwall) (496-7005) | EACH | 18 | $1,200.00 | $1,500.00 | $3,000.00 | $1,550.00 | $990.00 | $2,000.00 |
| 46 | Removing structure (headwall) (496-7006) | EACH | 54 | $1,000.00 | $1,500.00 | $2,000.00 | $1,550.00 | $880.00 | $1,500.00 |
| 47 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $160,000 | $150,000 | $105,000 | $50,000 | $137,500 | $1,000,000 |
| 48 | Mobilization (500-7001) | LS | 1 | $804,021 | $850,000 | $900,000 | $772,000 | $1,081,000 | $1,000,000 |
| 49 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $25,000 | $15,000 | $14,000 | $15,000 | $45,000 | $61,270 |
| 50 | Portable changeable message sign (503-7002) | EACH | 2 | $20,000 | $12,000 | $11,000 | $12,500 | $19,250 | $11,000 |
| 51 | TMA (stationary) (505-7001) | DAY | 172 | $250.00 | $20.00 | $300.00 | $300.00 | $250.00 | $230.00 |
| 52 | TMA (mobile operation) (505-7003) | DAY | 43 | $370.00 | $50.00 | $650.00 | $700.00 | $935.00 | $575.00 |
| 53 | Rock filter dams (install) (type 4) (506-7004) | LF | 54 | $75.00 | $50.65 | $132.00 | $105.00 | $54.51 | $100.00 |
| 54 | Rock filter dams (remove) (506-7011) | LF | 54 | $10.00 | $22.55 | $20.00 | $21.00 | $28.66 | $20.00 |
| 55 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,752 | $10.00 | $9.55 | $15.00 | $11.00 | $8.88 | $9.99 |
| 56 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,752 | $1.50 | $1.70 | $2.20 | $2.75 | $2.06 | $2.50 |
| 57 | Intersections (ACP) (530-7002) | SY | 721 | $75.00 | $70.00 | $90.00 | $100.00 | $110.00 | $70.00 |
| 58 | Driveways (concrete) (530-7006) | SY | 227 | $115.00 | $150.00 | $350.00 | $225.00 | $200.00 | $140.00 |
| 59 | Driveways (ACP) (530-7010) | SY | 2,301 | $80.00 | $75.00 | $90.00 | $100.00 | $90.00 | $90.00 |
| 60 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 61,796 | $0.20 | $0.30 | $0.14 | $0.16 | $0.15 | $0.07 |
| 61 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 12,510 | $0.20 | $0.46 | $0.45 | $0.16 | $0.42 | $0.21 |
| 62 | Metal W-beam guard fence (steel post) (540-7002) | LF | 350 | $40.00 | $40.00 | $50.00 | $50.00 | $50.60 | $45.00 |
| 63 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,700.00 | $2,800.00 | $5,000.00 | $3,950.00 | $4,125.00 | $2,500.00 |
| 64 | Remove metal beam guard fence (542-7001) | LF | 400 | $3.00 | $4.50 | $6.50 | $5.25 | $5.50 | $6.00 |
| 65 | Remove terminal anchor section (542-7002) | EACH | 4 | $1,500.00 | $375.00 | $700.00 | $525.00 | $550.00 | $500.00 |
| 66 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,600.00 | $3,750.00 | $5,000.00 | $4,200.00 | $4,400.00 | $3,700.00 |
| 67 | In RD IL (type SA) 40T-10 (250W EQ) LED (610-7126) | EACH | 22 | $7,000.00 | $5,350.00 | $6,000.00 | $5,775.00 | $7,260.00 | $5,500.00 |
| 68 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 4,186 | $10.00 | $15.25 | $20.00 | $16.00 | $24.20 | $15.00 |
| 69 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 439 | $40.00 | $36.00 | $40.00 | $21.00 | $39.60 | $20.00 |
| 70 | Electrical conductor (no.8) bare (620-7007) | LF | 4,760 | $2.00 | $2.15 | $2.50 | $2.75 | $2.75 | $2.50 |
| 71 | Electrical conductor (no.8) insulated (620-7008) | LF | 9,520 | $3.00 | $2.10 | $2.50 | $3.00 | $3.03 | $2.75 |
| 72 | Ground box type A (122311)W/apron (624-7002) | EACH | 5 | $2,000.00 | $1,000.00 | $1,200.00 | $1,575.00 | $2,530.00 | $1,500.00 |
| 73 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 2 | $13,750 | $8,675.00 | $10,000 | $7,875.00 | $12,650 | $7,500.00 |
| 74 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 25 | $1,000.00 | $775.00 | $900.00 | $825.00 | $939.40 | $854.00 |
| 75 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 28 | $1,000.00 | $850.00 | $1,000.00 | $900.00 | $1,190.20 | $1,082.00 |
| 76 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,200.00 | $990.00 | $1,100.00 | $1,050.00 | $1,486.10 | $1,351.00 |
| 77 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 2 | $1,300.00 | $1,200.00 | $1,500.00 | $1,300.00 | $1,750.10 | $1,591.00 |
| 78 | Remove SM RD SN sup&AM (644-7073) | EACH | 52 | $175.00 | $100.00 | $200.00 | $105.00 | $150.00 | $150.00 |
| 79 | Install delineator assembly (D-SY)SZ 1(BRF)GF1 (658-7034) | EACH | 12 | $35.00 | $45.00 | $40.00 | $50.00 | $49.50 | $13.00 |
| 80 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 54 | $80.00 | $80.00 | $90.00 | $84.00 | $71.50 | $65.00 |
| 81 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 125,727 | $0.25 | $0.17 | $0.18 | $0.18 | $0.19 | $0.17 |
| 82 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 125,727 | $0.25 | $0.17 | $0.18 | $0.18 | $0.19 | $0.17 |
| 83 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 3,000 | $0.50 | $2.29 | $0.73 | $1.14 | $3.01 | $2.00 |
| 84 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 75 | $2.00 | $1.10 | $1.20 | $1.16 | $3.30 | $1.10 |
| 85 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,389 | $1.00 | $1.10 | $1.20 | $1.16 | $0.94 | $1.10 |
| 86 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 62,660 | $0.50 | $0.65 | $0.70 | $0.68 | $0.64 | $0.65 |
| 87 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 7,372 | $0.50 | $0.65 | $0.70 | $0.68 | $0.86 | $0.65 |
| 88 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 6,167 | $0.50 | $0.65 | $0.70 | $0.68 | $0.86 | $0.65 |
| 89 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 48 | $20.00 | $10.00 | $10.50 | $11.00 | $15.40 | $10.00 |
| 90 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 6 | $300.00 | $175.00 | $180.00 | $185.00 | $352.00 | $175.00 |
| 91 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 5 | $350.00 | $200.00 | $205.00 | $210.00 | $418.00 | $200.00 |
| 92 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 8 | $35.00 | $38.00 | $40.00 | $40.00 | $27.50 | $38.00 |
| 93 | Reflectorized pavement marker type I-C (672-7002) | EACH | 126 | $4.00 | $5.00 | $5.50 | $5.25 | $4.95 | $5.00 |
| 94 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 460 | $4.00 | $5.00 | $5.50 | $5.25 | $4.95 | $5.00 |
| 95 | Bonding course (3007-7001) | GAL | 30,908 | $3.00 | $4.00 | $5.00 | $4.50 | $4.91 | $5.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.