TxDOT contract A00186870 bid tabulation

Bridge Replacement, FM 1580 (At Mims Creek to .). Let by Texas DOT on October 8, 2025, Freestone, Bryan District. 7 bids received; low bid $2,573,940 by Pmco Construction LLC, +3.6% against the engineer's estimate of $2,483,796.

Owner
Texas DOT
Letting
08 OCT 2025
Pay items
67
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Pmco Construction LLC$2,573,940Low+4.0%
2Larry Young Paving, Inc.$2,751,365+7.0%+11%
3Knife River Corporation - South$2,763,112+7.0%+11%
4Hodges and Son Construction Company, Inc.$2,796,538+9.0%+13%
5Texas Steel Industrial Placing, LLC$2,856,029+11%+15%
6A. L. Helmcamp, Inc.$2,987,048+16%+20%
7C. E. Barker, LTD.$3,596,808+40%+45%
TxDOT contract A00186870: bids by rank

Engineer's estimate: $2,483,796.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Pmco Construction LLC2. Larry Young Paving, Inc.3. Knife River Corporation - South4. Hodges and Son Construction Company, Inc.5. Texas Steel Industrial Placing, LLC6. A. L. Helmcamp, Inc.
1Preparing row (100-7002)STA15.90$2,000.00$3,000.00$760.00$625.30$2,500.00$5,000.00$4,000.00
2Removing stab base and asphalt pavement(0"-16") (105-7129)SY3,912$10.00$12.00$13.00$9.50$15.00$12.50$10.00
3Excavation (roadway) (110-7001)CY3,214$25.00$20.00$28.00$9.00$15.00$22.00$20.00
4Embankment (final)(DC)(type C) (132-7006)CY1,062$25.00$30.00$28.00$10.75$20.00$25.00$20.00
5Furn & place topsoil (4") (160-7002)SY6,665$3.00$3.00$3.00$4.30$3.50$4.00$5.00
6Hydro mulch seed (permanent_rural_sandy) (164-7017)SY6,665$0.65$0.83$0.75$0.60$1.00$0.46$0.61
7Hydro mulch seed (temporary_warm) (164-7021)SY3,333$0.65$0.73$0.75$0.60$0.50$0.47$0.55
8Hydro mulch seed (temporary_cool) (164-7022)SY3,333$0.63$0.73$0.75$0.60$0.50$0.48$0.55
9Vegetative watering (168-7001)TGL66.70$75.00$50.00$40.00$47.00$1.00$10.00$35.00
10Soil retention blankets (CL 1) (type B) (169-7043)SY257$7.00$6.70$2.75$2.30$3.00$2.00$2.20
11FL BS (compacted in place)(type A GR 1-2) (8") (247-7067)SY2,887$21.00$30.00$31.00$17.50$40.00$25.00$22.50
12FL BS (compacted in place)(type A GR 1-2) (10") (247-7090)SY2,538$34.00$39.00$26.15$45.00$25.00$26.00
13Lime (com or QK)(slurry) or QK(dry) (260-7001)TON32.50$350.00$400.00$470.00$368.60$350.00$375.00$340.00
14Lime TRT (existing material)(8") (260-7007)SY1,562$8.00$12.00$16.00$10.80$20.00$9.00$12.00
15Lime TRT (existing material)(10") (260-7008)SY1,373$12.00$18.00$12.30$25.00$9.00$13.00
16Cement (275-7001)TON32.50$350.00$400.00$240.00$265.60$350.00$300.00$300.00
17Cement TRT (existing material & new base)(10") (275-7008)SY1,373$8.00$9.25$4.15$20.00$9.00$14.00
18Cement TRT (subgrade) (8") (275-7018)SY1,562$8.00$8.00$8.00$3.65$20.00$9.00$12.00
19Prime coat (MC-30) (310-7004)GAL1,085$7.00$16.00$7.75$11.00$10.00$7.00$9.00
20Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068)GAL4,558$10.00$14.00$7.50$6.00$12.00$12.00$5.00
21Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241)CY86$250.00$835.00$285.00$405.15$700.00$1,200.00$500.00
22Cem stabil BKFL (400-7010)CY203$180.00$285.00$130.00$212.00$275.00$185.00$250.00
23Drilled shaft (24 in) (416-7004)LF520$287.67$155.00$310.00$160.50$220.00$390.00$185.00
24Drilled shaft (36 in) (416-7006)LF250$300.00$480.00$339.00$280.00$500.00$365.00
25Class C concrete (abutment) (420-7012)CY77.90$1,300.00$1,275.00$1,500.00$1,384.50$1,600.00$1,200.00$2,850.00
26Class C concrete (cap) (420-7022)CY21.40$1,540.00$2,300.00$2,800.00$2,226.50$1,800.00$1,650.00$2,250.00
27Class C concrete (column) (420-7038)CY11.20$1,500.00$2,300.00$2,700.00$2,300.00$2,000.00$2,000.00$1,850.00
28Reinforced concrete slab (422-7001)SF2,940$32.00$48.00$46.00$26.00$23.00$55.00
29Reinforced concrete slab (slab beam) (422-7007)SF3,780$26.00$25.00$20.00$26.00$22.00$23.00$30.00
30Approach slab (422-7013)CY142.90$935.00$875.00$1,100.00$968.00$900.00$700.00$875.00
31Prestressed concrete girder (TX28) (425-7001)LF347.51$280.00$300.00$346.50$280.00$275.00$275.00
32Prestressed concrete slab beam (4SB12) (425-7016)LF353.92$250.50$215.00$270.00$287.00$240.00$275.00$225.00
33Prestressed concrete slab beam (5SB12) (425-7017)LF442.40$250.00$215.00$270.00$276.00$240.00$275.00$225.00
34Riprap (mow strip)(4 in) (432-7013)CY71$550.00$750.00$700.00$636.40$700.00$650.00$1,000.00
35Riprap (stone protection)(18 in) (432-7043)CY1,634$160.00$160.00$180.00$138.60$200.00$180.00$115.00
36Rail (type T223) (450-7008)LF298$175.00$150.00$150.00$170.20$170.00$160.00$250.00
37Rail (type T223)(mod) (450-7071)LF82$170.00$165.00$178.40$175.00$190.00$350.00
38Type A joint (454-7001)LF168$70.00$50.00$60.00$67.00$100.00$90.00$250.00
39Removing structure (bridge 0 - 99 FT length) (496-7009)EACH2$28,100$30,000$43,000$22,970$50,000$40,000$75,000
40Mobilization (500-7001)LS1$248,000$250,000$230,000$585,086$245,000$285,346$300,000
41Barricades, signs and traffic handling (502-7001)MO9$6,200.00$4,000.00$3,100.00$2,750.00$2,500.00$6,500.00$7,500.00
42Portable changeable message sign (503-7002)EACH7$7,750.00$7,500.00$5,250.00$7,826.00$17,000$16,000$20,000
43TMA (stationary) (505-7001)DAY17$260.00$500.00$260.00$605.00$300.00$300.00$285.00
44TMA (mobile operation) (505-7003)DAY8$260.00$500.00$860.00$970.00$300.00$1.00$300.00
45Rock filter dams (install) (type 2) (506-7002)LF169$51.32$50.00$53.00$43.00$1.00$45.00$42.00
46Rock filter dams (remove) (506-7011)LF169$13.00$17.00$14.00$11.40$1.00$15.00$11.00
47Construction exits (install) (type 1) (506-7020)SY448$44.20$38.00$48.00$39.00$1.00$40.00$38.50
48Construction exits (remove) (506-7024)SY448$15.60$17.00$19.00$16.00$1.00$15.00$15.40
49Temporary sediment control fence (install) (506-7039)LF2,037$5.38$4.50$5.25$4.30$1.00$5.00$4.13
50Temporary sediment control fence (remove) (506-7041)LF2,037$1.56$1.60$1.50$1.15$1.00$1.00$1.10
51Driveways (surface treat) (530-7016)SY111$30.00$70.00$25.00$130.00$60.00$80.00$80.00
52Metal W-beam guard fence (timber post) (540-7001)LF750$30.00$23.50$29.00$24.00$25.00$28.00$23.50
53Metal beam guard fence trans (thrie-beam) (540-7005)EACH7$2,200.00$1,600.00$2,500.00$1,819.00$1,600.00$2,100.00$2,100.00
54Guardrail end treatment (install) (544-7001)EACH7$3,254.65$3,000.00$4,000.00$3,325.00$3,000.00$3,100.00$3,220.00
55Crash cushion attenuator (install)(R)(N)(TL3) (545-7010)EACH1$30,000$10,000$30,985$28,000$28,000$33,825
56Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH6$796.22$905.00$1,000.00$1,080.00$1,500.00$650.00$889.90
57Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH6$940.15$940.00$1,200.00$1,080.00$1,500.00$650.00$929.50
58Remove SM RD SN sup&AM (644-7073)EACH6$153.91$126.00$200.00$170.50$50.00$190.00$149.60
59Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH4$27.00$32.01$29.00$28.50$20.00$35.00$27.50
60Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH23$29.00$32.00$35.00$35.25$25.00$35.00$34.10
61Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH82$1.19$5.01$0.75$1.15$5.00$3.00$0.74
62Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF3,176$1.50$3.70$3.00$5.15$4.00$3.50$3.85
63Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF2,908$1.50$3.70$3.00$5.15$4.00$3.50$3.85
64Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF70$1.50$5.20$1.50$9.00$4.00$3.50$3.85
65Pavement sler 6" (666-7347)LF250$0.27$4.00$1.50$2.30$4.00$3.50$3.85
66Reflectorized pavement marker type II-A-A (672-7004)EACH42$8.60$13.00$12.00$17.00$10.00$10.00$11.00
67Pavement surface preparation for marking (6") (678-7002)LF250$0.64$4.00$0.75$2.30$4.00$3.50$3.85
TxDOT contract A00186870: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way