TxDOT contract A00135345 bid tabulation

Reconstruct Existing Roadway, FM 487 (COLLEGE AVENUE to SH 195 BYPASS). Let by Texas DOT on February 5, 2026, Williamson, Austin District. 10 bids received; low bid $3,649,316 by Rucoba & Maya Construction, LLC, -14% against the engineer's estimate of $4,222,092.

Owner
Texas DOT
Letting
05 FEB 2026
Pay items
155
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Rucoba & Maya Construction, LLC$3,649,316Low-14%
2Posillico Civil, Inc.$3,790,532+4.0%-10%
3STX Civil$3,832,408+5.0%-9.0%
4Dan Williams Company$3,854,723+6.0%-9.0%
5Lone Star Sitework, LLC$3,915,770+7.0%-7.0%
6Patin Construction LLC$3,983,935+9.0%-6.0%
7Aaron Concrete Contractors, LLC$4,092,443+12%-3.0%
8Chasco Constructors$4,379,339+20%+4.0%
9C. E. Barker, LTD.$4,769,760+31%+13%
10Hunter Industries, LTD.$4,998,063+37%+18%
TxDOT contract A00135345: bids by rank

Engineer's estimate: $4,222,092.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Rucoba & Maya Construction, LLC2. Posillico Civil, Inc.3. STX Civil4. Dan Williams Company5. Lone Star Sitework, LLC6. Patin Construction LLC
1Preparing row (100-7002)STA20.10$2,000.00$1,000.00$7,500.00$650.00$7,250.00$2,200.00$4,000.00
2Removing concrete (driveways) (104-7011)SY505$25.00$24.00$10.00$25.00$14.00$6.10$25.00
3Removing concrete (curb) (104-7016)LF86$6.00$8.00$10.00$7.00$5.00$20.00
4Removing concrete (flume) (104-7041)SY256$24.00$10.00$20.00$14.00$6.00$20.00
5Remove (17") TRT/untrt base & asphalt pavement (105-7037)SY6,219$12.00$12.50$4.00$7.00$8.50$36.00$20.00
6Excavation (roadway) (110-7001)CY5,146$14.00$12.10$10.00$10.00$20.00$39.00$20.00
7Embankment (final)(OC)(type B) (132-7003)CY1,003$14.00$12.00$15.00$20.00$30.00$78.00$5.00
8Embankment (final)(OC)(type C) (132-7005)CY422$27.50$28.50$17.00$25.00$35.00$95.00$35.00
9Furn & place topsoil (4") (160-7002)SY3,542$4.50$6.50$2.00$4.50$2.50$36.00$4.00
10Roll sodding (162-7008)SY3,542$8.50$9.00$5.00$8.00$9.25$9.25$15.00
11Vegetative watering (168-7001)TGL59.60$60.00$25.00$150.00$100.00$15.00$135.00$50.00
12FL BS (compacted in place)(type A GR 5)(final pos) (247-7179)CY3,041$54.00$59.00$65.00$70.00$54.00$95.00$78.00
13Prime coat(MC-30 or AE-P) (310-7013)GAL1,825$5.00$3.21$3.00$3.50$3.10$3.40$5.00
14D-GR HMA type-C PG76-22 (exempt) (341-7040)TON864$105.00$113.85$110.00$113.00$115.00$121.00$135.00
15D-GR HMA type D PG 76-22 (exempt) (341-7065)TON724$110.00$116.96$113.00$116.00$118.00$124.00$140.00
16Tom-C PG76-22 sac-B (347-7002)TON497$120.00$155.25$150.00$153.00$155.00$165.00$200.00
17Flexible pavement structure repair(4") (351-7003)SY200$30.00$59.00$125.00$60.00$57.00$81.00$75.00
18Planing asphalt concrete pavement (2.5") (354-7082)SY948$3.50$6.73$3.00$6.85$6.50$8.20$10.00
19Cut & restore asphalt paving (400-7008)SY597$200.00$90.00$110.00$115.00$300.00$15.00$150.00
20Flowable backfill (401-7001)CY5$350.00$207.00$175.00$160.00$325.00$145.00$700.00
21Trench excavation protection (402-7001)LF2,920$17.50$10.35$5.00$15.00$1.50$5.50$5.00
22Temporary special shoring (403-7001)SF3,752$30.00$15.00$30.00$40.00$4.50$62.50$15.00
23Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF8$300.00$210.00$500.00$414.09$450.00$468.00$410.00
24Retaining wall (spread footing) (423-7015)SF1,581$114.00$120.00$145.00$110.00$97.00$124.00
25Riprap (concrete)(5 in) (432-7002)CY90$600.00$523.33$600.00$700.00$575.00$575.00$700.00
26Riprap (mow strip)(4 in) (432-7013)CY25$700.00$540.00$625.00$725.00$675.00$560.00$600.00
27Riprap (stone protection)(15 in) (432-7042)CY737$185.00$205.00$75.00$180.00$100.00$181.50$250.00
28Rail (type C221) (450-7032)LF399.50$165.00$85.00$250.00$130.00$48.50$400.00
29Concrete box culvert (5 FT X 3 FT) (462-7007)LF556$618.00$600.00$500.00$470.00$463.50$600.00
30Concrete box culvert (8 FT X 4 FT) (462-7021)LF255$1,050.00$900.00$900.00$755.00$770.00$814.00$800.00
31Concrete box culvert (7 FT X 4 FT)(extend) (462-7071)LF51$956.00$2,200.00$1,000.00$815.00$770.00$1,100.00
32RC pipe (CL III)(18 in) (464-7003)LF951$80.00$85.00$100.00$80.00$86.00$94.00$85.00
33RC pipe (CL III)(24 in) (464-7005)LF234$135.00$120.00$115.00$100.00$93.00$114.00$120.00
34RC pipe (CL III)(36 in) (464-7009)LF24$192.00$225.00$160.00$215.00$174.00$250.00
35Manh (complete)(PRM)(48IN) (465-7002)EACH1$6,150.00$6,000.00$6,160.00$5,300.00$4,850.00$7,500.00
36Inlet (complete)(pco)(3FT)(left) (465-7014)EACH1$6,150.00$7,000.00$7,250.00$7,100.00$6,830.00$7,500.00
37Inlet (complete)(pco)(3FT)(right) (465-7015)EACH4$6,150.00$7,000.00$7,265.00$7,100.00$6,830.00$7,500.00
38Inlet (complete)(pco)(6FT)(none) (465-7025)EACH1$10,600$11,000$9,500.00$9,500.00$9,110.00$10,000
39Inlet (complete)(pco)(6FT)(left) (465-7026)EACH2$11,200$12,000$10,100$10,000$10,007$10,000
40Inlet (complete)(pco)(6FT)(right) (465-7027)EACH1$11,132$12,000$10,100$10,000$10,007$10,000
41Inlet (complete)(PSL)(SL)(3FTX3FT) (465-7054)EACH1$4,750.00$5,000.00$5,785.00$5,600.00$4,575.00$6,500.00
42Inlet (complete)(PSL)(RH)(6FTX6FT) (465-7068)EACH2$9,620.00$16,000$12,650$12,250$12,200$15,000
43Inlet (complete)(pazd)(RC)(3FTX3FT) (465-7152)EACH3$5,874.00$5,000.00$5,700.00$5,400.00$4,282.00$5,000.00
44Inlet (complete)(pazd)(RC)(4FTX4FT) (465-7153)EACH1$6,776.00$8,000.00$6,900.00$7,500.00$5,600.00$6,000.00
45Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160)EACH1$7,150.00$9,000.00$7,500.00$7,250.00$5,850.00$7,000.00
46Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162)EACH2$8,250.00$10,000$9,800.00$9,000.00$8,200.00$10,000
47Inlet (complete)(armor curb slot) (465-7338)EACH3$3,800.00$6,500.00$4,200.00$3,500.00$4,300.00$2,500.00
48Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH1$26,000$40,000$32,000$32,000$6,300.00$25,000
49Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH3$40,000$38,900$30,000$35,000$35,000$7,800.00$35,000
50Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH3$2,000.00$1,920.00$2,500.00$1,800.00$2,000.00$1,250.00$4,000.00
51Set (type II)(18 in)(RCP)(3:1)(P) (467-7467)EACH1$1,800.00$1,800.00$1,500.00$1,300.00$2,000.00$900.00$4,000.00
52Set(type II)(24 in)(RCP)(3:1)(P) (467-7469)EACH4$2,500.00$2,100.00$2,000.00$1,500.00$2,000.00$1,000.00$5,000.00
53Adjusting manholes (479-7001)EACH1$5,500.00$1,100.00$850.00$2,500.00$2,350.00$500.00$1,000.00
54Adjusting manholes (utility valve) (479-7009)EACH5$800.00$600.00$1,500.00$950.00$1,000.00$400.00$750.00
55Removing structure (set) (496-7004)EACH6$350.00$500.00$400.00$325.00$400.00$1,000.00
56Removing structure (headwall) (496-7006)EACH2$1,350.00$1,200.00$2,500.00$3,000.00$500.00$1,500.00
57Removing structure (pipe) (496-7007)LF748$17.50$15.00$25.00$25.00$11.00$40.00
58Mobilization (500-7001)LS1$305,000$211,500$310,000$348,000$380,000$180,000$70,000
59Barricades, signs and traffic handling (502-7001)MO12$7,375.00$4,000.00$900.00$3,500.00$18,000$2,310.00$5,000.00
60Portable changeable message sign (503-7002)EACH2$10,500$14,000$15,000$9,000.00$11,000$5,000.00$30,000
61TMA (stationary) (505-7001)DAY89$210.00$600.00$120.00$180.00$135.00$400.00$250.00
62TMA (mobile operation) (505-7002)HR72$70.00$120.00$50.00$65.00$65.00$314.00$100.00
63Rock filter dams (install) (type 2) (506-7002)LF375$50.00$69.00$40.00$70.99$28.50$54.00$35.00
64Rock filter dams (remove) (506-7011)LF375$12.00$1.00$10.00$17.75$14.00$32.50$10.00
65Construction exits (install) (type 1) (506-7020)SY112$20.00$49.00$19.00$33.13$17.00$25.00$25.00
66Construction exits (remove) (506-7024)SY112$10.00$1.00$5.00$10.65$9.50$10.00$5.00
67Temporary sediment control fence (install) (506-7039)LF1,620$4.00$9.00$4.00$4.14$2.95$3.90$4.00
68Temporary sediment control fence (remove) (506-7041)LF1,620$1.50$0.50$0.50$1.18$0.75$1.10$1.00
69Biodegradable erosion control logs (install) (12") (506-7044)LF340$6.50$7.00$5.50$7.10$5.25$6.10$10.00
70Biodegradable erosion control logs (remove) (506-7046)LF340$2.00$1.00$1.00$2.37$2.00$1.10$5.00
71One-way traffic control (flagger cont) (510-7001)HR184$100.00$89.00$115.00$75.00$100.00$314.00$100.00
72Concrete curb & gutter (type II) (529-7009)LF3,154$28.00$25.00$29.98$26.00$27.00$25.00
73Concrete curb & gutter (slotted) (529-7021)LF37$42.00$25.00$100.00$50.00$35.00$25.00
74Driveways (concrete) (530-7006)SY1,226$88.00$100.00$88.06$92.50$89.00$115.00
75Concrete sidewalks (5") (531-7002)SY1,552$78.00$75.00$73.55$60.00$86.00$80.00
76Curb ramps (type 7) (531-7010)EACH3$2,350.00$2,300.00$3,000.00$3,500.00$2,850.00$2,500.00
77Curb ramps (type 10) (531-7011)EACH7$2,350.00$2,500.00$3,250.00$3,500.00$2,800.00$2,500.00
78Metal W-beam guard fence (timber post) (540-7001)LF175$28.00$25.75$25.00$35.00$40.00$30.00$35.00
79Downstream anchor terminal section (540-7015)EACH1$1,500.00$1,311.69$1,475.00$2,750.00$2,200.00$1,623.00$2,500.00
80Metal W - beam guard fence (low fill culvert) (540-7018)LF125$80.00$104.63$95.00$80.00$97.00$106.00$100.00
81Remove metal beam guard fence (542-7001)LF375$3.50$6.24$2.00$2.00$2.50$3.25$5.00
82Remove downstream anchor terminal (542-7003)EACH1$300.00$208.00$180.00$275.00$300.00$198.00$500.00
83Guardrail end treatment (install) (544-7001)EACH1$3,200.00$3,602.19$3,600.00$3,750.00$4,500.00$4,015.00$5,000.00
84Guardrail end treatment (remove) (544-7003)EACH3$300.00$420.55$150.00$275.00$375.00$275.00$500.00
85Pipe underdrains (type 6) (6") (556-7006)LF264$36.00$30.00$40.00$25.00$65.00$40.00
86Mailbox install-S (TWW-post) type 4 (560-7008)EACH6$350.00$432.00$300.00$721.71$625.00$660.00$350.00
87Relocate RD IL asm (trans-base) (610-7004)EACH1$4,500.00$6,825.00$4,800.00$6,507.20$5,000.00$4,565.00$3,000.00
88Conduit (PVC) (schedule 40) (2") (618-7030)LF415$25.00$50.40$30.00$35.49$21.00$23.10$45.00
89Conduit (prepare) (618-7090)LF210$7.00$18.90$5.00$2.37$1.00$1.10$10.00
90Electrical conductor (no.8) insulated (620-7008)LF1,245$4.00$3.15$3.00$2.37$1.90$2.10$3.00
91Ground box type A (122311)W/apron (624-7002)EACH2$1,800.00$2,310.00$2,000.00$1,774.69$2,500.00$2,475.00$2,500.00
92Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH20$850.00$787.50$700.00$857.77$750.00$825.00$850.00
93Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,000.00$892.50$800.00$1,254.11$1,100.00$935.00$950.00
94Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH1$750.00$472.50$400.00$325.35$300.00$495.00$500.00
95Remove SM RD SN sup&AM (644-7073)EACH15$150.00$105.00$50.00$118.31$130.00$110.00$125.00
96Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH5$60.00$31.50$25.00$61.52$35.00$33.00$40.00
97Install object marker assembly (OM-3R)(TWT)GND (658-7070)EACH4$400.00$367.50$300.00$508.75$430.00$385.00$450.00
98Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH383$1.50$2.00$2.00$1.15$2.25$3.00$5.00
99Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF38$4.00$2.10$2.00$1.18$2.50$2.20$3.00
100Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF250$4.00$1.05$1.00$1.30$2.50$1.10$2.00
101Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,658$12.00$7.35$6.00$8.28$7.77$7.70$10.00
102Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH6$300.00$183.75$175.00$201.13$205.00$193.00$225.00
103Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH2$300.00$210.00$200.00$207.05$250.00$220.00$250.00
104Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF1,152$0.75$0.58$0.55$0.71$0.34$0.61$1.00
105Reflectorized pavement marking type II (W) 8" (DOT) (666-7177)LF38$0.75$1.05$1.00$0.83$0.52$1.10$2.00
106Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF250$1.00$0.58$0.55$0.83$0.43$0.61$1.00
107Reflectorized pavement marking type II (W) 24" (solid) (666-7184)LF1,658$3.50$3.68$3.00$0.85$3.40$3.85$5.00
108Reflectorized pavement marking type II (W) (arrow) (666-7186)EACH6$90.00$78.75$70.00$33.13$77.00$82.50$100.00
109Reflectorized pavement marking type II (W) (word) (666-7194)EACH2$75.00$78.75$70.00$0.33$77.00$82.50$100.00
110Reflectorized pavement marking type II (Y) 6" (broken) (666-7211)LF699$0.75$0.58$0.55$0.59$0.34$0.61$1.00
111Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF5,104$0.75$0.58$0.55$0.59$0.34$0.61$1.00
112Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF1,152$1.50$0.89$0.85$1.06$0.61$0.94$1.00
113Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF699$1.50$0.89$0.85$1.06$0.61$0.94$1.00
114Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF5,104$1.50$0.89$0.85$0.83$0.61$0.94$1.00
115Reflectorized pavement marker type I-C (672-7002)EACH14$7.00$6.83$6.00$4.73$7.00$7.15$8.00
116Reflectorized pavement marker type II-A-A (672-7004)EACH159$7.00$6.83$6.00$4.73$7.00$7.15$8.00
117Eliminating existing PM & markers (4") (677-7001)LF1,888$1.00$0.53$0.50$1.17$0.70$0.55$1.00
118Eliminating existing PM & markers (12") (677-7006)LF1,139$2.50$2.36$2.25$2.08$0.77$2.50$3.00
119Eliminating existing PM & markers (arrow) (677-7009)EACH2$140.00$78.75$70.00$68.62$52.00$82.50$100.00
120Eliminating existing PM & markers (word) (677-7015)EACH2$160.00$78.75$70.00$68.62$52.00$82.50$100.00
121Pavement surface preparation for marking (6") (678-7002)LF2,835$0.50$0.11$0.10$0.22$0.07$0.15$0.50
122Pavement surface preparation for marking (8") (678-7004)LF268$0.75$0.16$0.15$0.47$0.07$0.20$0.50
123Pavement surface preparation for marking (24") (678-7008)LF1,392$1.00$0.53$0.50$0.59$0.07$0.55$1.00
124Pavement surface preparation for marking (arrow) (678-7009)EACH2$30.00$21.00$20.00$17.75$0.07$22.00$50.00
125Pavement surface preparation for marking (word) (678-7016)EACH2$30.00$21.00$20.00$17.75$0.07$22.00$50.00
126Pavement surface preparation for marking (RPM) (678-7033)EACH99$2.50$2.10$2.00$1.18$0.07$2.20$5.00
127Removal of conduit (690-7001)LF238$3.50$2.50$3.00$11.83$2.00$2.20$10.00
128Remove conductor (690-7150)LF1,455$2.00$1.00$1.00$1.24$0.75$0.85$1.00
129Bonding course (3007-7001)GAL1,646$4.00$3.26$3.50$3.25$3.15$3.50$7.00
130Subsurface util locate (non-paved area) (5061-7001)EACH20$2,000.00$272.18$2,500.00$2,000.00$600.00$350.00$1,000.00
131Ground box (prepare) (6013-7006)EACH2$300.00$315.00$242.34$591.56$400.00$429.00$2,000.00
132Ground box W/ apron (adjust) (6013-7008)EACH1$600.00$700.00$712.25$887.34$550.00$577.00$4,000.00
133PVC pipe - water (C900, 6") (7083-7001)LF458$80.00$119.03$104.19$90.00$120.00$62.50$65.00
134PVC pipe - water (C900, 8") (7083-7002)LF209$100.00$170.78$125.31$100.00$200.00$101.00$100.00
13518" steel encasement (7083-7003)LF87$220.00$305.33$363.90$115.00$215.00$167.00$250.00
136Water service line (2" SDR 9) (7083-7004)LF298$50.00$41.40$86.81$120.00$50.00$12.70$40.00
137Encasement pipe (4" PVC SDR26) (7083-7005)LF70$40.00$56.92$87.34$95.00$48.00$14.10$50.00
138Remove existing 2" WL (7083-7006)LF1,164$30.00$15.52$14.37$60.00$10.00$4.00$30.00
139Remove existing 6" PVC WL (7083-7007)LF23$40.00$15.52$99.13$30.00$50.00$5.00$30.00
140Remove existing 8" PVC WL (7083-7008)LF107$40.00$15.52$15.79$120.00$25.00$5.00$30.00
141Fire hydrant assembly (7083-7009)EACH2$9,000.00$9,392.62$11,262$7,500.00$12,000$11,437$8,500.00
142Remove fire hydrant (7083-7010)EACH2$80.00$1,312.50$806.98$2,000.00$1,000.00$2,350.00$1,500.00
143Adjust structure, fire hydrant (7083-7011)EACH1$2,000.00$2,018.25$3,672.38$1,800.00$4,750.00$2,750.00$500.00
144Reconnect water service (7083-7012)EACH6$1,000.00$3,027.37$2,464.90$1,000.00$4,500.00$2,050.00$2,500.00
145Connect to existing WL (7083-7013)EACH5$600.00$8,642.25$12,497$600.00$5,500.00$3,793.00$5,000.00
146Remove existing 8" PVC wastewater (7083-7014)LF74$5,500.00$25.87$58.04$75.00$20.00$5.00$40.00
147Remove existing 8" steel & PVC wastewater (7083-7015)LF99$40.00$46.57$38.13$100.00$20.00$17.00$40.00
148PVC pipe - wastewater (PVC SDR 26) (6") (7083-7016)LF20$60.00$129.37$111.20$115.00$225.00$68.00$60.00
149PVC pipe - wastewater (PVC SDR 26) (8") (7083-7017)LF176$80.00$139.72$134.32$125.00$110.00$115.00$80.00
150Steel encasement pipe (18") (7083-7018)LF106$220.00$305.32$266.46$115.00$200.00$167.00$250.00
151Standard pre-cast manhole (4-FT diameter) (7083-7019)EACH1$7,000.00$9,056.25$6,021.05$6,000.00$13,500$4,800.00$7,500.00
152Watertight manhole (4-FT diameter) (7083-7020)EACH1$8,000.00$9,573.75$6,932.63$8,500.00$15,000$5,400.00$8,500.00
153Modify manhole for water tightness (7083-7021)EACH1$5,000.00$2,846.25$10,815$1,500.00$9,000.00$5,300.00$500.00
154Concrete trench cap (7083-7022)LF116$30.00$51.75$152.96$115.00$30.00$32.00$30.00
155Remove existing manhole (7083-7023)EACH2$3,000.00$1,811.25$1,523.93$1,500.00$1,850.00$1,900.00$2,500.00
TxDOT contract A00135345: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy