Low bidders on TxDOT contracts carried a median of $108.49 per SF for this item, over the 24 months to 19 NOV 2026, across 26 low bids. Half of all 149 bids fell between $95.00 and $150.00.

Owner
Texas DOT
Item
423-7015
Unit
SF
Data through
19 NOV 2026

TxDOT has bid this work under more than one code: 4236005 on lettings from 09 APR 2020 to 03 AUG 2023 (108 bids); 4236005004 on lettings from 03 AUG 2022 to 03 AUG 2022 (4 bids); 4236005005 on lettings from 05 MAR 2024 to 09 JUL 2024 (38 bids); 423-6005 on lettings from 06 NOV 2024 to 07 JAN 2025 (8 bids); 423-7015 on lettings from 07 FEB 2025 to 02 SEP 2026 (145 bids). They are combined here into one trend.

$108.49Low bidder's median, per SF
$114.00Median of all bids, per SF
26Contracts in the window
$110.00Engineer's estimate, median per SF

By year of letting

Retaining wall (spread footing), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202033$70.0025$78.80
20211010$57.0049$68.60
202255$75.0017$84.00
202344$87.5021$85.00
202499$110.0042$109.00
202588$116.9947$110.98
20261818$104.50102$116.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Austin District4$112.4927$114.00
San Antonio District5$96.2427$120.00
Dallas District3$150.0026$140.00
Fort Worth District3$83.0015$90.00
Retaining wall (spread footing), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (SF)Low bidsLow-bid median
98 to 3786$145.89
444 to 1,2487$96.24
1,581 to 3,6756$124.50
5,370 to 27,3477$90.33
Retaining wall (spread footing), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Retaining wall (spread footing), TxDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 SEP 2026A00210535Paris District270$350.00$230.00$123.004Highway 19 Construction LLCTxDOT
06 AUG 2026A00119935Laredo District444$94.88$107.28$123.004Pulice Construction, Inc.TxDOT
06 AUG 2026A00128671Childress District838$91.50$100.00$250.003J. Lee Milligan, Inc.TxDOT
02 JUL 2026A00216234Austin District1,905$152.00$146.00$105.005E-Z Bel Construction, LLCTxDOT
01 JUL 2026A00193362San Antonio District280$85.00$124.00$120.007J3 Company, LLCTxDOT
01 JUL 2026A00131976Fort Worth District6,209$77.10$90.00$125.004Foutsco Paving Company, LLCTxDOT
03 JUN 2026A00186691San Antonio District447$96.24$107.50n/a6STX CivilTxDOT
02 JUN 2026A00219663Fort Worth District1,248$105.00$105.00$140.007Ibctx, LLCTxDOT
07 MAY 2026A00031457San Antonio District378$141.79$141.79$95.003Webber, LLCTxDOT
07 MAY 2026A00184443Bryan District3,675$135.00$140.00$107.005Big Creek Construction, LTD.TxDOT
08 APR 2026A00200988San Antonio District550$60.00$117.50$110.002Relmco, Inc.TxDOT
07 APR 2026A00061686Abilene District570$145.00$122.65n/a6Skyline Bridge LLCTxDOT
04 MAR 2026A00207039Wichita Falls District2,520$95.00$107.90n/a12Texas Steel Industrial Placing, LLCTxDOT
04 MAR 2026A00215071Amarillo District98$117.00$117.00$110.001STX CivilTxDOT
05 FEB 2026A00135345Austin District1,581$114.00$120.00n/a10Rucoba & Maya Construction, LLCTxDOT
Latest TxDOT contracts carrying Retaining wall (spread footing)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy