TxDOT contract A00131976 bid tabulation
Widen Road - Add Lanes, Various (Las Vegas Trail; Quebec Drive to IH 820). Let by Texas DOT on July 1, 2026, Tarrant, Fort Worth District. 4 bids received; low bid $5,160,282 by Foutsco Paving Company, LLC, -25% against the engineer's estimate of $6,914,803.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 105
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foutsco Paving Company, LLC | $5,160,282 | Low | -25% |
| 2 | Ragle Construction, Inc. | $5,474,781 | +6.0% | -21% |
| 3 | Ed Bell Construction Company | $6,111,372 | +18% | -12% |
| 4 | Jagoe-Public Company | $6,166,871 | +20% | -11% |
Engineer's estimate: $6,914,803.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foutsco Paving Company, LLC | 2. Ragle Construction, Inc. | 3. Ed Bell Construction Company | 4. Jagoe-Public Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 16 | $4,000.00 | $1,000.00 | $33,750 | $18,900 | $4,550.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 831 | $35.00 | $40.00 | $16.00 | $23.00 | $20.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 63 | $50.00 | $30.00 | $14.00 | $76.00 | $26.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 1,302 | $15.00 | $10.00 | $8.50 | $16.00 | $21.00 |
| 5 | Excavation (roadway & channel) (110-7004) | CY | 9,029 | $45.00 | $22.00 | $40.00 | $42.00 | $42.00 |
| 6 | Embankment (final)(DC)(type C2) (132-7010) | CY | 1,493 | $50.00 | $18.00 | $15.00 | $63.00 | $70.00 |
| 7 | Compost manuf topsoil (4") (161-7002) | SY | 8,690 | $15.00 | $9.00 | $6.85 | $7.30 | $10.00 |
| 8 | Block sodding (162-7002) | SY | 6,032 | $25.00 | $4.55 | $7.25 | $5.64 | $5.00 |
| 9 | Roll sodding (162-7008) | SY | 2,658 | $10.00 | $4.55 | $7.50 | $5.86 | $5.00 |
| 10 | Broadcast seed (temporary_warm) (164-7005) | SY | 4,345 | $1.00 | $0.25 | $0.50 | $0.53 | $0.30 |
| 11 | Broadcast seed (temporary_cool) (164-7006) | SY | 4,345 | $1.00 | $0.26 | $0.50 | $0.53 | $0.30 |
| 12 | Vegetative watering (168-7001) | TGL | 305 | $180.00 | $65.00 | $40.00 | $53.25 | $38.00 |
| 13 | Rdside amenity (gate) (194-7009) | EACH | 1 | $5,000.00 | $11,500 | $3,500.00 | $5,325.00 | $2,700.00 |
| 14 | Proof rolling (216-7001) | HR | 16 | $150.00 | $400.00 | $125.00 | $315.00 | $60.00 |
| 15 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 2,815 | $100.00 | $80.00 | $110.00 | $88.00 | $80.00 |
| 16 | Lime (com or QK)(slurry) (260-7005) | TON | 222 | $400.00 | $325.00 | $315.00 | $315.00 | $330.00 |
| 17 | Lime TRT (existing material)(8") (260-7007) | SY | 13,246 | $10.00 | $6.00 | $3.90 | $3.15 | $6.00 |
| 18 | Cement TRT (new base)(8") (275-7011) | SY | 5,000 | $10.00 | $6.00 | $2.90 | $5.25 | $3.00 |
| 19 | Salvage, haul & stockpile reclaimed asphalt PV (2"-6") (305-7035) | SY | 1,920 | $15.00 | $5.24 | $5.50 | $7.19 | $7.00 |
| 20 | Salvage, haul & stockpile reclaimed asphalt PV (5 to 9") (305-7038) | SY | 5,940 | $15.00 | $8.00 | $5.50 | $8.79 | $9.00 |
| 21 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 4,834 | $12.00 | $0.10 | $5.50 | $8.38 | $4.25 |
| 22 | D-GR HMA type-B PG64-22 (341-7001) | TON | 2,020 | $150.00 | $125.00 | $150.00 | $127.32 | $110.00 |
| 23 | Tack coat (341-7082) | GAL | 2,303 | $10.00 | $0.10 | $5.50 | $5.33 | $3.00 |
| 24 | SP mixes SP-C sac-B PG70-28 (344-7025) | TON | 1,257 | $225.00 | $155.00 | $175.00 | $172.64 | $130.00 |
| 25 | Concrete pavement (CRCP) (9") (360-7003) | SY | 492 | $150.00 | $132.36 | $95.00 | $161.00 | $160.00 |
| 26 | Trench excavation protection (402-7001) | LF | 1,878 | $30.00 | $40.00 | $2.00 | $25.00 | $12.00 |
| 27 | Temporary special shoring (403-7001) | SF | 8,474 | $50.00 | $35.00 | $0.10 | $50.00 | $36.00 |
| 28 | Retaining wall (spread footing) (423-7015) | SF | 6,209 | $125.00 | $77.10 | $90.00 | $90.00 | $135.00 |
| 29 | Riprap (concrete)(5 in) (432-7002) | CY | 12 | $2,000.00 | $522.42 | $650.00 | $1,155.00 | $500.00 |
| 30 | Riprap (stone common)(grout)(24 in) (432-7040) | CY | 447 | $200.00 | $232.95 | $175.00 | $630.00 | $400.00 |
| 31 | Rail (type C223) (450-7034) | LF | 422 | $200.00 | $89.60 | $125.00 | $205.00 | $220.00 |
| 32 | Concrete box culvert (7 FT X 6 FT) (462-7018) | LF | 400 | $1,300.00 | $515.70 | $1,200.00 | $915.00 | $1,100.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,577 | $175.00 | $165.00 | $92.00 | $150.00 | $180.00 |
| 34 | RC pipe (CL III)(30 in) (464-7007) | LF | 418 | $200.00 | $210.00 | $125.00 | $175.00 | $290.00 |
| 35 | Inlet (complete)(CO)(10 FT)(FTW) (465-7185) | EACH | 5 | $12,000 | $4,909.40 | $11,350 | $11,000 | $12,000 |
| 36 | Inlet (complete)(CO)(15 FT)(FTW) (465-7186) | EACH | 4 | $15,000 | $6,272.10 | $14,750 | $13,000 | $16,000 |
| 37 | Inlet (complete)( CO)(20 FT)(FTW) (465-7187) | EACH | 4 | $18,000 | $7,637.60 | $18,075 | $15,000 | $16,000 |
| 38 | Inlet (complete)(cob)(20 FT)(FTW) (465-7203) | EACH | 1 | $30,000 | $10,294 | $21,050 | $20,000 | $29,000 |
| 39 | Adjusting manholes (479-7001) | EACH | 4 | $1,450.00 | $800.00 | $1,280.00 | $4,500.00 | $3,600.00 |
| 40 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,200.00 | $1,500.00 | $600.00 | $2,000.00 | $4,800.00 |
| 41 | Removing structure (headwall) (496-7006) | EACH | 2 | $1,400.00 | $1,800.00 | $1,400.00 | $5,000.00 | $7,000.00 |
| 42 | Removing structure (box culvert) (496-7008) | LF | 63 | $100.00 | $87.00 | $70.00 | $300.00 | $600.00 |
| 43 | Mobilization (500-7001) | LS | 1 | $700,000 | $305,000 | $540,000 | $595,000 | $684,000 |
| 44 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $15,000 | $100,000 | $35,825 | $21,000 | $36,000 |
| 45 | Portable changeable message sign (503-7002) | EACH | 4 | $8,500.00 | $5,000.00 | $12,000 | $20,000 | $15,750 |
| 46 | TMA (stationary) (505-7001) | DAY | 94 | $225.00 | $1.00 | $400.00 | $210.00 | $260.00 |
| 47 | Rock filter dams (install) (type 2) (506-7002) | LF | 122 | $60.00 | $40.00 | $44.00 | $61.13 | $46.00 |
| 48 | Rock filter dams (remove) (506-7011) | LF | 122 | $25.00 | $14.00 | $18.00 | $26.63 | $19.00 |
| 49 | Construction exits (install) (type 1) (506-7020) | SY | 342 | $40.00 | $33.50 | $44.00 | $54.21 | $4.25 |
| 50 | Construction exits (remove) (506-7024) | SY | 342 | $15.00 | $9.00 | $13.00 | $23.43 | $14.00 |
| 51 | Temporary sediment control fence (install) (506-7039) | LF | 3,762 | $5.00 | $0.10 | $5.00 | $3.04 | $5.00 |
| 52 | Temporary sediment control fence (remove) (506-7041) | LF | 3,762 | $2.00 | $0.10 | $1.00 | $1.38 | $1.00 |
| 53 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 285 | $10.00 | $4.50 | $6.00 | $4.26 | $6.00 |
| 54 | Biodegradable erosion control logs (remove) (506-7046) | LF | 285 | $3.00 | $1.10 | $1.00 | $2.08 | $1.00 |
| 55 | Constructing detours (508-7001) | SY | 642 | $100.00 | $85.00 | $120.00 | $111.00 | $100.00 |
| 56 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 180 | $50.00 | $70.00 | $150.00 | $40.00 | $70.00 |
| 57 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 40 | $50.00 | $70.00 | $150.00 | $120.00 | $70.00 |
| 58 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 180 | $10.00 | $50.00 | $12.00 | $30.00 | $50.00 |
| 59 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 40 | $10.00 | $50.00 | $20.00 | $90.00 | $60.00 |
| 60 | Concrete curb (mono) (type II) (529-7007) | LF | 286 | $15.00 | $15.93 | $13.00 | $10.50 | $2.00 |
| 61 | Concrete curb & gutter (type II) (529-7009) | LF | 3,829 | $70.00 | $26.25 | $27.00 | $42.00 | $26.00 |
| 62 | Driveways (concrete) (530-7006) | SY | 929 | $135.00 | $93.24 | $96.00 | $147.00 | $120.00 |
| 63 | Concrete sidewalks (4") (531-7001) | SY | 3,001 | $100.00 | $50.84 | $55.00 | $77.00 | $70.00 |
| 64 | Curb ramps (type 1) (531-7005) | EACH | 2 | $4,600.00 | $2,500.00 | $1,750.00 | $2,500.00 | $3,700.00 |
| 65 | Curb ramps (type 3) (531-7007) | EACH | 3 | $4,000.00 | $2,500.00 | $1,350.00 | $2,500.00 | $3,700.00 |
| 66 | Curb ramps (type 22) (531-7014) | EACH | 1 | $7,000.00 | $3,500.00 | $3,710.00 | $4,000.00 | $5,000.00 |
| 67 | Concrete sidewalks (special) (type A) (531-7029) | SY | 57 | $300.00 | $129.63 | $135.00 | $275.00 | $320.00 |
| 68 | Remove metal beam guard fence (542-7001) | LF | 238 | $5.00 | $5.00 | $5.00 | $29.35 | $6.00 |
| 69 | Remove terminal anchor section (542-7002) | EACH | 2 | $200.00 | $300.00 | $300.00 | $1,467.31 | $360.00 |
| 70 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 21 | $1,000.00 | $645.00 | $650.00 | $692.25 | $700.00 |
| 71 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,000.00 | $735.00 | $725.00 | $772.13 | $700.00 |
| 72 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,200.00 | $1,225.00 | $1,130.00 | $1,203.45 | $1,200.00 |
| 73 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,300.00 | $1,299.00 | $1,130.00 | $1,203.45 | $1,300.00 |
| 74 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 4 | $100.00 | $75.00 | $60.00 | $63.90 | $80.00 |
| 75 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 3,087 | $2.00 | $0.50 | $0.45 | $0.80 | $0.40 |
| 76 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 3,358 | $2.00 | $0.50 | $0.45 | $0.80 | $0.40 |
| 77 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 7,105 | $6.00 | $3.75 | $3.55 | $5.06 | $6.00 |
| 78 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 4,076 | $2.00 | $0.88 | $1.35 | $1.54 | $0.90 |
| 79 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 37 | $15.00 | $5.76 | $7.00 | $5.33 | $6.00 |
| 80 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 3,765 | $2.00 | $0.88 | $1.35 | $1.54 | $0.90 |
| 81 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 57 | $3.00 | $2.00 | $2.45 | $1.07 | $1.75 |
| 82 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,098 | $2.00 | $1.00 | $1.45 | $1.07 | $0.90 |
| 83 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 403 | $10.00 | $6.89 | $6.95 | $7.19 | $7.00 |
| 84 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 16 | $160.00 | $155.00 | $181.00 | $149.10 | $140.00 |
| 85 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 2 | $250.00 | $199.00 | $362.00 | $239.63 | $190.00 |
| 86 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 7 | $250.00 | $170.00 | $210.00 | $159.75 | $160.00 |
| 87 | Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087) | EACH | 29 | $85.00 | $38.00 | $25.50 | $58.58 | $60.00 |
| 88 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 383 | $2.00 | $1.00 | $0.85 | $0.85 | $0.70 |
| 89 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,183 | $2.00 | $0.87 | $0.68 | $0.80 | $0.70 |
| 90 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 277 | $2.00 | $1.00 | $0.85 | $0.85 | $0.70 |
| 91 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 5,183 | $2.00 | $0.87 | $0.68 | $0.80 | $0.70 |
| 92 | Reflectorized pavement marker type I-C (672-7002) | EACH | 66 | $5.00 | $5.00 | $3.55 | $15.98 | $5.00 |
| 93 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 7 | $5.00 | $5.00 | $5.00 | $26.63 | $5.00 |
| 94 | Eliminating existing PM & markers (6") (677-7002) | LF | 836 | $2.00 | $0.75 | $0.65 | $2.13 | $0.50 |
| 95 | Eliminating existing PM & markers (24") (677-7008) | LF | 98 | $2.00 | $3.90 | $3.55 | $3.20 | $2.75 |
| 96 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $2.00 | $55.00 | $65.00 | $53.25 | $39.00 |
| 97 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 1 | $2.00 | $75.00 | $125.00 | $63.90 | $50.00 |
| 98 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $2.00 | $55.00 | $65.00 | $58.58 | $47.00 |
| 99 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,360 | $2.00 | $0.25 | $0.06 | $0.32 | $0.02 |
| 100 | Pavement surface preparation for marking (8") (678-7004) | LF | 355 | $2.00 | $0.33 | $0.08 | $0.64 | $0.06 |
| 101 | Pavement surface preparation for marking (24") (678-7008) | LF | 70 | $5.00 | $55.00 | $0.24 | $1.07 | $0.50 |
| 102 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 2 | $2.00 | $15.00 | $15.00 | $21.30 | $12.00 |
| 103 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 1 | $50.00 | $20.00 | $30.00 | $31.95 | $17.00 |
| 104 | Pavement surface preparation for marking (word) (678-7016) | EACH | 1 | $50.00 | $15.00 | $15.00 | $26.63 | $13.00 |
| 105 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 2 | $1,200.00 | $225.00 | $1,750.00 | $1,597.50 | $230.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.