TxDOT contract A00061686 bid tabulation
Bridge Replacement, COUNTY ROAD 412 (CR 412 to AT COTTONWOOD CRK TRIB). Let by Texas DOT on April 7, 2026, Fisher, Abilene District. 6 bids received; low bid $3,158,064 by Skyline Bridge LLC, -31% against the engineer's estimate of $4,574,023.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 52
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Skyline Bridge LLC | $3,158,064 | Low | -31% |
| 2 | Delgado'S Contractors, LLC | $3,627,377 | +15% | -21% |
| 3 | Hodges and Son Construction Company, Inc. | $3,830,110 | +21% | -16% |
| 4 | Tucan Contracting, LLC | $3,887,221 | +23% | -15% |
| 5 | Coppell Construction Co., Inc. | $4,172,547 | +32% | -9.0% |
| 6 | Altus Construction LLC | $4,852,521 | +54% | +6.0% |
Engineer's estimate: $4,574,023.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Skyline Bridge LLC | 2. Delgado'S Contractors, LLC | 3. Hodges and Son Construction Company, Inc. | 4. Tucan Contracting, LLC | 5. Coppell Construction Co., Inc. | 6. Altus Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 22.97 | $10,000 | $1,025.00 | $750.00 | $3,900.00 | $1,650.00 | $2,500.00 | $8,450.24 |
| 2 | Excavation (roadway) (110-7001) | CY | 956 | $17.00 | $16.00 | $25.50 | $15.00 | $22.00 | $18.00 | $72.88 |
| 3 | Excavation (channel) (110-7002) | CY | 2,386 | $30.70 | $14.00 | $25.00 | $15.00 | $22.00 | $20.00 | $34.29 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 2,656 | $65.46 | $30.00 | $28.00 | $20.00 | $27.50 | $24.00 | $52.20 |
| 5 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 5,006 | $2.50 | $0.74 | $1.00 | $1.00 | $0.43 | $0.70 | $2.60 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 2,503 | $2.50 | $0.74 | $1.00 | $1.00 | $0.39 | $0.70 | $5.20 |
| 7 | Broadcast seed (temporary_cool) (164-7006) | SY | 2,503 | $2.50 | $0.74 | $1.00 | $1.00 | $0.40 | $0.70 | $5.20 |
| 8 | Vegetative watering (168-7001) | TGL | 80.70 | $50.00 | $1.00 | $50.00 | $1.00 | $77.00 | $25.00 | $34.42 |
| 9 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 5,757 | $18.99 | $20.00 | $22.50 | $35.00 | $33.00 | $25.00 | $27.32 |
| 10 | Cem stabil BKFL (400-7010) | CY | 394 | $160.00 | $265.00 | $255.00 | $250.00 | $220.00 | $275.00 | $253.95 |
| 11 | Temporary special shoring (403-7001) | SF | 306 | $35.00 | $50.00 | $80.00 | $33.00 | $94.00 | $35.42 | |
| 12 | Drilled shaft (18 in) (416-7002) | LF | 214 | $100.00 | $170.00 | $200.00 | $231.00 | $210.00 | $193.50 | |
| 13 | Drilled shaft (30 in) (416-7005) | LF | 966 | $400.00 | $175.00 | $250.00 | $250.00 | $341.00 | $260.00 | $279.71 |
| 14 | Drilled shaft (36 in) (416-7006) | LF | 123 | $200.00 | $600.00 | $600.00 | $462.00 | $670.00 | $752.61 | |
| 15 | Class C concrete (abutment) (420-7012) | CY | 210 | $1,800.00 | $950.00 | $1,500.00 | $1,300.00 | $1,320.00 | $1,100.00 | $1,553.54 |
| 16 | Reinforced concrete slab (422-7001) | SF | 12,006 | $29.99 | $22.00 | $27.00 | $28.00 | $29.70 | $31.00 | $40.81 |
| 17 | Retaining wall (spread footing) (423-7015) | SF | 570 | $145.00 | $100.00 | $150.00 | $154.00 | $65.00 | $100.29 | |
| 18 | Prestressed concrete girder (TX34) (425-7002) | LF | 338 | $300.00 | $310.00 | $290.00 | $244.90 | $300.00 | $385.47 | |
| 19 | Prestressed concrete girder (TX40) (425-7003) | LF | 400 | $290.00 | $310.00 | $290.00 | $244.90 | $305.00 | $380.51 | |
| 20 | Prestressed concrete box beam (4B20) (425-7026) | LF | 713.96 | $295.95 | $400.00 | $325.00 | $330.00 | $381.35 | $390.00 | $292.08 |
| 21 | Prestressed concrete box beam (5B20) (425-7027) | LF | 356.98 | $295.62 | $300.00 | $325.00 | $330.00 | $381.35 | $400.00 | $345.56 |
| 22 | Prestressed concrete box beam (4B34) (425-7030) | LF | 380 | $455.00 | $325.00 | $500.00 | $381.35 | $505.00 | $279.94 | |
| 23 | Prestressed concrete box beam (5B34) (425-7031) | LF | 190 | $377.25 | $325.00 | $500.00 | $381.35 | $520.00 | $298.02 | |
| 24 | Riprap (concrete)(5 in) (432-7002) | CY | 150 | $30.70 | $500.00 | $695.00 | $700.00 | $715.00 | $610.00 | $466.65 |
| 25 | Riprap (stone protection)(12 in) (432-7041) | CY | 259 | $175.00 | $200.00 | $180.00 | $198.00 | $255.00 | $215.44 | |
| 26 | Riprap (stone protection)(15 in) (432-7042) | CY | 555 | $170.00 | $215.00 | $180.00 | $198.00 | $245.00 | $187.61 | |
| 27 | Riprap (stone protection)(18 in) (432-7043) | CY | 200 | $240.00 | $170.00 | $250.00 | $185.00 | $198.00 | $255.00 | $190.16 |
| 28 | Riprap (stone protection)(36 in) (432-7048) | CY | 755 | $182.00 | $275.00 | $200.00 | $198.00 | $225.00 | $179.13 | |
| 29 | Rail (type T223) (450-7008) | LF | 1,188 | $155.00 | $108.00 | $160.00 | $160.00 | $198.00 | $150.00 | $151.29 |
| 30 | Type A joint (454-7001) | LF | 316 | $239.07 | $75.00 | $50.00 | $60.00 | $77.00 | $200.00 | $57.60 |
| 31 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 6 | $61,847 | $12,360 | $20,500 | $20,000 | $11,000 | $28,000 | $27,595 |
| 32 | Mobilization (500-7001) | LS | 1 | $30,000 | $225,000 | $195,000 | $350,000 | $330,000 | $375,000 | $485,255 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $18,000 | $3,850.00 | $3,250.00 | $3,000.00 | $3,300.00 | $16,000 | $36,394 |
| 34 | Temporary sediment control fence (install) (506-7039) | LF | 3,452 | $7.00 | $3.25 | $8.00 | $1.00 | $3.30 | $4.55 | $4.72 |
| 35 | Temporary sediment control fence (remove) (506-7041) | LF | 3,452 | $2.50 | $1.50 | $1.00 | $1.00 | $1.10 | $1.50 | $1.18 |
| 36 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,318 | $10.00 | $6.00 | $9.00 | $1.00 | $5.50 | $9.00 | $6.49 |
| 37 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,318 | $1.50 | $2.00 | $1.00 | $1.00 | $0.99 | $2.00 | $1.18 |
| 38 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 60 | $75.00 | $50.00 | $110.00 | $44.00 | $60.00 | $258.09 | |
| 39 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 60 | $75.00 | $25.00 | $110.00 | $27.50 | $60.00 | $258.09 | |
| 40 | Metal W-beam guard fence (timber post) (540-7001) | LF | 525 | $31.32 | $26.00 | $29.00 | $25.00 | $33.00 | $27.00 | $26.31 |
| 41 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 22 | $1,181.67 | $1,245.50 | $1,300.00 | $1,200.00 | $1,650.00 | $1,075.00 | $1,289.04 |
| 42 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,450.00 | $1,500.00 | $1,400.00 | $1,540.00 | $1,245.00 | $1,405.08 | |
| 43 | Guardrail end treatment (install) (544-7001) | EACH | 20 | $3,805.12 | $3,500.00 | $3,400.00 | $3,500.00 | $3,850.00 | $3,200.00 | $3,136.64 |
| 44 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $400.00 | $1,500.00 | $1,000.00 | $1,210.00 | $800.00 | $1,771.11 | |
| 45 | Cca (install)(N)(TL2)(work zone) (545-7017) | EACH | 2 | $8,745.00 | $8,500.00 | $9,000.00 | $9,900.00 | $7,900.00 | $6,228.42 | |
| 46 | Wire fence (type A) (552-7001) | LF | 1,907 | $25.57 | $18.50 | $25.00 | $18.00 | $27.50 | $20.00 | $21.63 |
| 47 | Wire fence (type C) (552-7003) | LF | 1,170 | $25.75 | $25.00 | $20.00 | $27.50 | $20.00 | $50.18 | |
| 48 | Wire fence (remove) (552-7011) | LF | 2,214 | $6.20 | $4.20 | $2.00 | $5.00 | $2.20 | $4.00 | $9.66 |
| 49 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 15 | $710.53 | $1,247.50 | $1,000.00 | $900.00 | $660.00 | $790.00 | $260.94 |
| 50 | Remove SM RD SN sup&AM (644-7073) | EACH | 11 | $160.21 | $195.00 | $250.00 | $50.00 | $110.00 | $100.00 | $118.07 |
| 51 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 42 | $14.83 | $46.50 | $35.00 | $45.00 | $38.50 | $32.00 | $27.10 |
| 52 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 70 | $45.55 | $46.50 | $35.00 | $45.00 | $44.00 | $36.00 | $27.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.