TxDOT contract A00207039 bid tabulation
Construct Pedestrian Infrastructure, FM 1306 (FM 51 to Gainesville High School). Let by Texas DOT on March 4, 2026, Cooke, Wichita Falls District. 12 bids received; low bid $2,192,972 by Texas Steel Industrial Placing, LLC, -23% against the engineer's estimate of $2,835,174.
- Owner
- Texas DOT
- Letting
- 04 MAR 2026
- Pay items
- 90
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Texas Steel Industrial Placing, LLC | $2,192,972 | Low | -23% |
| 2 | STX Civil | $2,231,704 | +2.0% | -21% |
| 3 | Xit Paving and Construction Inc. | $2,296,746 | +5.0% | -19% |
| 4 | Ti-Zack Concrete, LLC | $2,365,288 | +8.0% | -17% |
| 5 | Altus Construction LLC | $2,470,595 | +13% | -13% |
| 6 | Professional Traffic Control LLC | $2,518,587 | +15% | -11% |
| 7 | Garret Shields Infrastructure | $2,677,525 | +22% | -6.0% |
| 8 | Tucan Contracting, LLC | $2,791,151 | +27% | -2.0% |
| 9 | Jagoe-Public Company | $2,828,006 | +29% | 0.0% |
| 10 | Ed Bell Construction Company | $3,268,725 | +49% | +15% |
| 11 | Built Right Construction of Oklahoma, LLC | $3,496,935 | +59% | +23% |
| 12 | O. Trevino Construction, LLC | $3,699,480 | +69% | +30% |
Engineer's estimate: $2,835,174.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Texas Steel Industrial Placing, LLC | 2. STX Civil | 3. Xit Paving and Construction Inc. | 4. Ti-Zack Concrete, LLC | 5. Altus Construction LLC | 6. Professional Traffic Control LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 13 | $120.00 | $9.00 | $60.00 | $35.08 | $29.53 | $12.35 | |
| 2 | Removing concrete (driveways) (104-7011) | SY | 503 | $30.00 | $50.00 | $15.50 | $41.00 | $36.26 | $25.84 | $17.54 |
| 3 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 99 | $20.00 | $6.50 | $35.00 | $9.21 | $11.33 | $16.37 | |
| 4 | Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048) | SY | 1,042 | $17.00 | $15.00 | $13.00 | $16.00 | $35.01 | $11.29 | $5.70 |
| 5 | Excavation (roadway) (110-7001) | CY | 1,172 | $20.00 | $25.00 | $28.00 | $60.00 | $19.45 | $28.73 | $28.50 |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,707.60 | $33.00 | $45.00 | $25.00 | $50.00 | $13.35 | $42.23 | $65.86 |
| 7 | Block sodding (162-7002) | SY | 7,074 | $7.00 | $4.75 | $7.00 | $7.00 | $6.60 | $5.49 | $7.86 |
| 8 | Vegetative watering (168-7001) | TGL | 635 | $30.00 | $1.00 | $20.00 | $15.00 | $1.10 | $29.96 | $28.30 |
| 9 | Flexible pavement structure repair(8") (351-7007) | SY | 140 | $90.00 | $160.00 | $85.00 | $180.00 | $137.50 | $402.79 | $83.00 |
| 10 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 32 | $234.92 | $308.00 | $271.00 | $257.40 | $272.01 | $450.00 | |
| 11 | Class A concrete (collar) (420-7008) | EACH | 1 | $1,500.00 | $1,500.00 | $1,300.00 | $1,984.52 | $1,476.33 | $1,596.00 | |
| 12 | Class C concrete (miscellaneous) (420-7067) | CY | 22.60 | $1,100.00 | $550.00 | $800.00 | $950.00 | $798.63 | $415.57 | $1,500.00 |
| 13 | Retaining wall (spread footing) (423-7015) | SF | 2,520 | $95.00 | $72.00 | $76.00 | $104.41 | $98.20 | $105.80 | |
| 14 | Riprap (concrete)(5 in) (432-7002) | CY | 150.50 | $600.00 | $550.00 | $720.00 | $705.00 | $798.63 | $683.18 | $665.50 |
| 15 | Riprap (concrete)(flume) (432-7012) | CY | 19.50 | $1,000.00 | $550.00 | $850.00 | $696.00 | $798.63 | $659.57 | $670.00 |
| 16 | Riprap (concrete)(CL B)(RR8&RR9) (432-7055) | CY | 30 | $550.00 | $800.00 | $696.00 | $798.63 | $517.19 | $650.00 | |
| 17 | Rail (handrail)(type B) (450-7059) | LF | 804 | $200.00 | $99.28 | $130.00 | $110.00 | $110.00 | $87.77 | $135.40 |
| 18 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 27 | $650.00 | $721.00 | $515.00 | $1,068.10 | $583.54 | $530.00 | |
| 19 | RC pipe (CL III)(18 in) (464-7003) | LF | 16 | $120.00 | $200.00 | $147.00 | $172.70 | $148.14 | $92.72 | |
| 20 | Wingwall (SW - 0) (HW=6 FT) (466-7205) | EACH | 2 | $15,000 | $20,000 | $11,500 | $9,772.40 | $14,268 | $17,500 | |
| 21 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 1 | $2,000.00 | $2,300.00 | $3,000.00 | $2,502.50 | $2,541.60 | $1,737.00 | |
| 22 | Grate & frame (471-7003) | EACH | 66 | $1,475.00 | $1,600.00 | $1,500.00 | $1,200.00 | $1,266.25 | $1,484.92 | $2,250.00 |
| 23 | Removing structure (set) (496-7004) | EACH | 1 | $500.00 | $500.00 | $809.00 | $982.30 | $679.55 | $670.00 | |
| 24 | Removing structure (pipe) (496-7007) | LF | 16 | $20.00 | $25.00 | $15.00 | $62.00 | $59.40 | $27.27 | $33.75 |
| 25 | Mobilization (500-7001) | LS | 1 | $99,401 | $219,277 | $174,000 | $150,000 | $173,219 | $245,826 | $100,000 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $3,250.00 | $2,000.00 | $4,000.00 | $1,650.00 | $20,588 | $3,000.00 |
| 27 | Portable changeable message sign (503-7002) | EACH | 3 | $10,000 | $20,000 | $8,500.00 | $5,089.00 | $1.10 | $6,252.68 | $1,000.00 |
| 28 | TMA (stationary) (505-7001) | DAY | 231 | $275.00 | $100.00 | $195.00 | $282.00 | $1.10 | $173.69 | $200.00 |
| 29 | TMA (mobile operation) (505-7003) | DAY | 20 | $350.00 | $1.00 | $200.00 | $1,800.00 | $1.10 | $130.26 | $250.00 |
| 30 | Concrete curb (type II) (529-7002) | LF | 344 | $70.00 | $40.00 | $30.00 | $15.00 | $50.18 | $42.77 | $19.50 |
| 31 | Concrete curb & gutter (type II) (529-7009) | LF | 6,661 | $50.00 | $40.00 | $38.00 | $43.00 | $39.17 | $32.80 | $38.50 |
| 32 | Concrete curb (slotted) (529-7013) | LF | 22 | $60.00 | $50.00 | $51.00 | $47.60 | $65.07 | $38.50 | |
| 33 | Concrete curb & gutter (armor curb) (529-7018) | LF | 84 | $215.00 | $300.00 | $700.00 | $272.00 | $301.46 | $374.22 | $40.30 |
| 34 | Concrete curb (ribbon) (529-7028) | LF | 8 | $50.00 | $150.00 | $55.00 | $98.00 | $40.77 | $78.16 | $72.00 |
| 35 | Driveways (concrete) (530-7006) | SY | 784 | $125.00 | $100.00 | $110.00 | $95.00 | $118.39 | $123.56 | $145.25 |
| 36 | Concrete sidewalks (4") (531-7001) | SY | 4,834 | $119.00 | $70.00 | $75.00 | $73.00 | $117.64 | $64.80 | $119.50 |
| 37 | Curb ramps (type 1) (531-7015) | SY | 52 | $125.00 | $120.00 | $120.00 | $167.48 | $303.57 | $160.00 | |
| 38 | Curb ramps (type 3) (531-7017) | SY | 11 | $300.00 | $125.00 | $120.00 | $191.00 | $167.48 | $123.32 | $170.00 |
| 39 | Curb ramps (type 6) (531-7019) | SY | 39 | $125.00 | $120.00 | $189.00 | $167.48 | $129.40 | $180.00 | |
| 40 | Curb ramps (type 7) (531-7020) | SY | 142 | $275.00 | $125.00 | $120.00 | $149.00 | $167.48 | $216.44 | $196.00 |
| 41 | Curb ramps (type 21) (531-7023) | SY | 32 | $275.00 | $125.00 | $120.00 | $139.00 | $129.80 | $231.87 | $220.00 |
| 42 | Concrete sidewalks (special) (531-7025) | SY | 416 | $170.00 | $215.00 | $230.00 | $170.00 | $272.26 | $208.78 | $296.60 |
| 43 | In RD IL (type SA) 30S-8 (250W EQ) LED (610-7064) | EACH | 4 | $6,546.31 | $8,579.50 | $7,571.00 | $7,200.60 | $7,580.00 | $5,000.00 | |
| 44 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 140 | $19.50 | $19.83 | $26.00 | $23.00 | $21.81 | $22.96 | $12.50 |
| 45 | Conduit (prepare) (618-7090) | LF | 330 | $4.00 | $17.63 | $23.00 | $20.00 | $19.39 | $20.41 | $7.10 |
| 46 | Electrical conductor (no.6) bare (620-7009) | LF | 40 | $3.62 | $4.50 | $4.00 | $3.98 | $4.19 | $1.70 | |
| 47 | Electrical conductor (no.6) insulated (620-7010) | LF | 360 | $4.05 | $5.50 | $5.00 | $4.46 | $4.69 | $2.50 | |
| 48 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $2,000.00 | $2,941.84 | $3,855.50 | $3,402.00 | $3,235.10 | $3,406.37 | $1,320.00 |
| 49 | Remove ground box (624-7013) | EACH | 1 | $264.45 | $346.50 | $306.00 | $290.40 | $306.21 | $354.00 | |
| 50 | Aluminum signs (type A) (636-7001) | SF | 63 | $45.00 | $18.75 | $164.00 | $46.00 | $42.90 | $45.64 | $30.00 |
| 51 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 2 | $950.00 | $586.74 | $989.50 | $868.00 | $495.00 | $805.47 | $900.00 |
| 52 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 14 | $740.00 | $322.60 | $590.00 | $462.00 | $165.00 | $542.77 | $600.00 |
| 53 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $100.00 | $99.00 | $327.50 | $578.00 | $165.00 | $99.87 | $115.00 |
| 54 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 4 | $34.37 | $150.00 | $289.00 | $137.50 | $93.36 | $162.00 | |
| 55 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 564 | $14.00 | $9.50 | $12.50 | $6.00 | $8.75 | $11.00 | $8.50 |
| 56 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 1 | $250.00 | $327.50 | $289.00 | $275.00 | $289.48 | $200.00 | |
| 57 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 8 | $60.00 | $37.50 | $49.00 | $289.00 | $66.00 | $43.42 | $37.50 |
| 58 | Pavement sler 24" (666-7352) | LF | 564 | $2.00 | $1.00 | $1.50 | $6.00 | $3.30 | $1.16 | $2.28 |
| 59 | Pavement sler (arrow) (666-7353) | EACH | 1 | $25.00 | $33.00 | $289.00 | $88.00 | $28.95 | $38.00 | |
| 60 | Pavement sler (yld tri) (666-7365) | EACH | 8 | $25.00 | $5.00 | $6.50 | $289.00 | $33.00 | $5.79 | $20.00 |
| 61 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $65.00 | $85.00 | $578.00 | $137.50 | $75.26 | $65.00 | |
| 62 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $65.00 | $85.00 | $578.00 | $137.50 | $75.26 | $60.00 | |
| 63 | Pavement surface preparation for marking (24") (678-7008) | LF | 564 | $1.00 | $0.55 | $0.50 | $6.00 | $2.75 | $0.64 | $0.55 |
| 64 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 1 | $10.00 | $13.00 | $578.00 | $66.00 | $11.58 | $15.30 | |
| 65 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 8 | $20.00 | $5.00 | $6.50 | $289.00 | $22.00 | $5.79 | $15.00 |
| 66 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $43,000 | $47,586 | $62,365 | $55,039 | $52,345 | $55,100 | $52,650 |
| 67 | Removing traffic signals (680-7004) | EACH | 1 | $8,700.00 | $4,374.08 | $5,732.50 | $5,059.00 | $4,811.40 | $5,064.77 | $6,600.00 |
| 68 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $370.00 | $429.10 | $562.50 | $496.00 | $473.00 | $496.87 | $296.00 |
| 69 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 2 | $370.00 | $436.17 | $571.50 | $504.00 | $473.00 | $505.04 | $298.00 |
| 70 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 10 | $370.00 | $429.11 | $562.50 | $496.00 | $473.00 | $496.87 | $296.00 |
| 71 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 2 | $370.00 | $436.17 | $571.50 | $504.00 | $473.00 | $505.04 | $310.00 |
| 72 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $370.00 | $429.10 | $562.50 | $496.00 | $473.00 | $496.86 | $300.00 |
| 73 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 1 | $370.00 | $437.11 | $573.00 | $506.00 | $473.00 | $506.13 | $300.00 |
| 74 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 2 | $1,150.00 | $935.21 | $1,225.50 | $1,082.00 | $104.50 | $1,082.88 | $808.00 |
| 75 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 7 | $220.00 | $246.52 | $323.00 | $285.00 | $270.60 | $285.45 | $200.00 |
| 76 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 2 | $275.00 | $260.65 | $341.50 | $301.00 | $286.00 | $301.81 | $255.00 |
| 77 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 285 | $3.20 | $3.20 | $4.00 | $4.00 | $3.52 | $3.71 | $1.80 |
| 78 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 215 | $4.50 | $5.01 | $6.50 | $6.00 | $5.51 | $5.80 | $2.62 |
| 79 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 395 | $2.50 | $6.49 | $8.50 | $8.00 | $7.14 | $7.51 | $3.14 |
| 80 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 1 | $8,300.00 | $10,588 | $13,876 | $12,247 | $11,646 | $12,260 | $9,285.00 |
| 81 | Pedestrian pole assembly (687-7001) | EACH | 1 | $2,000.00 | $2,083.83 | $2,731.00 | $2,410.00 | $2,291.30 | $2,412.88 | $2,974.00 |
| 82 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $1,600.00 | $1,350.50 | $1,770.00 | $1,562.00 | $1,485.00 | $1,563.75 | $1,033.00 |
| 83 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $4,670.00 | $4,017.57 | $5,265.50 | $4,646.00 | $4,418.70 | $4,651.96 | $3,810.00 |
| 84 | Install vid image vehicle det sys (VIVDS) (690-7084) | EACH | 1 | $24,500 | $20,964 | $27,475 | $24,247 | $23,059 | $24,274 | $6,358.00 |
| 85 | VIVDS cable (install) (690-7137) | LF | 705 | $0.50 | $3.80 | $5.00 | $5.00 | $4.18 | $4.40 | $1.50 |
| 86 | VIVDS camera (install) (690-7138) | EACH | 3 | $31,500 | $1,458.03 | $1,911.00 | $1,686.00 | $1,603.80 | $1,688.26 | $429.90 |
| 87 | Remove roadway illum assembly (LED) (690-7166) | EACH | 4 | $546.77 | $716.50 | $632.00 | $602.80 | $633.11 | $1,151.40 | |
| 88 | Spot tree trimming / brush removal (752-7002) | LF | 510 | $31.85 | $6.00 | $12.50 | $77.00 | $1.10 | $11.26 | $55.50 |
| 89 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 8 | $300.00 | $300.00 | $14.00 | $420.00 | $60.50 | $1,042.11 | $225.00 |
| 90 | Ground box (prepare) (6013-7006) | EACH | 4 | $1,000.00 | $352.57 | $462.00 | $408.00 | $387.20 | $408.24 | $305.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.