TxDOT contract A00134791 bid tabulation
Bridge Replacement, COUNTY ROAD 177 (CR 177 at BOGGY CREEK to STR# AA01-32-001). Let by Texas DOT on September 4, 2025, Lavaca, Yoakum District. 10 bids received; low bid $1,508,380 by Texas Steel Industrial Placing, LLC, -3.1% against the engineer's estimate of $1,557,405.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 57
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Texas Steel Industrial Placing, LLC | $1,508,380 | Low | -3.0% |
| 2 | STX Civil | $1,566,338 | +4.0% | +1.0% |
| 3 | E-Z Bel Construction, LLC | $1,574,787 | +4.0% | +1.0% |
| 4 | Hunter Industries, LTD. | $1,626,031 | +8.0% | +4.0% |
| 5 | Trevway, Inc. | $1,644,529 | +9.0% | +6.0% |
| 6 | Presidio Contracting, LLC | $1,668,845 | +11% | +7.0% |
| 7 | Lakey, Inc. | $1,721,092 | +14% | +11% |
| 8 | C. E. Barker, LTD. | $2,152,588 | +43% | +38% |
| 9 | Forde Construction Company, Inc. | $2,222,173 | +47% | +43% |
| 10 | CK Newberry, LLC | $2,526,435 | +67% | +62% |
Engineer's estimate: $1,557,405.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Texas Steel Industrial Placing, LLC | 2. STX Civil | 3. E-Z Bel Construction, LLC | 4. Hunter Industries, LTD. | 5. Trevway, Inc. | 6. Presidio Contracting, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 9.06 | $3,000.00 | $2,500.00 | $3,985.00 | $4,000.00 | $3,807.20 | $5,500.00 | $7,700.00 |
| 2 | Obliterating abandoned road (106-7001) | STA | 2.92 | $7,000.00 | $1,700.00 | $1,963.00 | $1,000.00 | $1,887.47 | $6,100.00 | $3,150.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 597 | $22.00 | $22.00 | $23.00 | $24.00 | $42.00 | $12.00 | $27.35 |
| 4 | Excavation (channel) (110-7002) | CY | 523 | $20.00 | $20.00 | $24.00 | $19.00 | $42.00 | $22.00 | $27.35 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 262 | $25.00 | $30.00 | $40.00 | $19.00 | $42.00 | $22.00 | $14.35 |
| 6 | Blading (150-7002) | HR | 30 | $100.00 | $125.00 | $100.00 | $90.00 | $126.50 | $50.00 | $85.00 |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,382 | $1.00 | $0.70 | $1.00 | $0.85 | $0.90 | $1.00 | $1.35 |
| 8 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 121 | $1.35 | $1.00 | $10.00 | $10.55 | $1.00 | $13.10 | |
| 9 | Broadcast seed (temporary_warm) (164-7005) | SY | 376 | $1.00 | $1.35 | $1.00 | $0.50 | $0.53 | $1.00 | $4.00 |
| 10 | Broadcast seed (temporary_cool) (164-7006) | SY | 376 | $1.00 | $1.35 | $1.00 | $0.50 | $0.53 | $1.00 | $4.00 |
| 11 | Vegetative watering (168-7001) | TGL | 11.63 | $100.00 | $100.00 | $50.00 | $25.00 | $40.93 | $100.00 | $90.00 |
| 12 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 349 | $135.00 | $120.00 | $90.00 | $130.00 | $93.48 | $124.68 | $122.50 |
| 13 | Asphalt (RC-250) (316-7016) | GAL | 291 | $15.00 | $20.00 | $7.00 | $15.50 | $10.10 | $16.42 | $16.30 |
| 14 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 10 | $715.00 | $1,250.00 | $1,430.00 | $1,045.00 | $369.60 | $2,526.32 | $1,100.00 |
| 15 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 11 | $715.00 | $1,200.00 | $1,360.00 | $975.00 | $501.60 | $2,400.00 | $1,100.00 |
| 16 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 494 | $15.00 | $20.00 | $10.00 | $13.10 | $9.00 | $12.63 | $13.80 |
| 17 | D-GR HMA type-B PG70-22 (exempt) (341-7014) | TON | 155 | $240.00 | $178.00 | $137.00 | $208.00 | $265.26 | $230.00 | |
| 18 | D-GR HMA type D PG70-22 (exempt) (341-7069) | TON | 52 | $240.00 | $244.00 | $222.00 | $233.20 | $404.21 | $360.00 | |
| 19 | Tack coat (341-7082) | GAL | 94 | $20.00 | $5.02 | $20.00 | $4.45 | $25.26 | $21.00 | |
| 20 | Cut & restoring pavement (400-7006) | SY | 27 | $200.00 | $200.00 | $260.00 | $139.00 | $120.00 | $440.00 | $187.00 |
| 21 | Cem stabil BKFL (400-7010) | CY | 61 | $165.00 | $200.00 | $153.00 | $120.00 | $95.00 | $300.00 | $340.00 |
| 22 | Drilled shaft (24 in) (416-7004) | LF | 846 | $275.00 | $300.00 | $295.00 | $235.00 | $352.11 | $358.00 | $240.00 |
| 23 | Class C concrete (abutment) (420-7012) | CY | 39.20 | $1,350.00 | $1,100.00 | $1,520.00 | $1,800.00 | $1,700.00 | $1,200.00 | $1,315.00 |
| 24 | Class C concrete (cap) (420-7022) | CY | 26.40 | $1,600.00 | $1,500.00 | $2,365.00 | $2,800.00 | $2,100.00 | $1,144.00 | $2,030.00 |
| 25 | Class C concrete (column) (420-7038) | CY | 11.90 | $2,000.00 | $1,500.00 | $2,375.00 | $2,800.00 | $1,200.00 | $1,253.00 | $2,190.00 |
| 26 | Reinforced concrete slab (slab beam) (422-7007) | SF | 4,810 | $23.00 | $22.00 | $27.00 | $28.00 | $30.00 | $21.00 | $28.30 |
| 27 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 910.05 | $265.00 | $250.00 | $245.00 | $305.00 | $195.00 | $227.29 | $275.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 3 | $1,250.00 | $1,000.00 | $895.00 | $700.00 | $1,500.00 | $1,625.00 | |
| 29 | Riprap (stone protection)(18 in) (432-7043) | CY | 638 | $205.00 | $180.00 | $215.00 | $210.00 | $227.21 | $181.00 | $158.00 |
| 30 | Rail (type T223) (450-7008) | LF | 214 | $140.00 | $150.00 | $240.00 | $325.00 | $200.00 | $120.00 | $133.00 |
| 31 | Rail (type C223) (450-7034) | LF | 201 | $210.00 | $250.00 | $255.00 | $260.00 | $200.00 | $192.00 | |
| 32 | Armor joint (sealed) (454-7003) | LF | 92 | $160.00 | $125.00 | $175.00 | $145.00 | $169.47 | $154.84 | $140.00 |
| 33 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 47 | $500.00 | $550.00 | $365.00 | $550.00 | $583.92 | $780.00 | $612.00 |
| 34 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 2 | $18,000 | $15,000 | $15,000 | $8,000.00 | $13,284 | $15,000 | $10,525 |
| 35 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $30,000 | $30,000 | $16,000 | $32,500 | $7,731.69 | $30,000 | $44,000 |
| 36 | Removing structure (small) (496-7036) | EACH | 1 | $1,000.00 | $2,500.00 | $455.00 | $500.00 | $1,176.63 | $2,000.00 | $1,140.00 |
| 37 | Mobilization (500-7001) | LS | 1 | $140,000 | $155,000 | $123,000 | $50,000 | $156,414 | $168,000 | $166,800 |
| 38 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $2,500.00 | $1,000.00 | $1,500.00 | $1,000.00 | $2,867.21 | $1,200.00 | $3,580.00 |
| 39 | TMA (stationary) (505-7001) | DAY | 5 | $450.00 | $100.00 | $200.00 | $1,056.72 | $300.00 | $430.00 | |
| 40 | Rock filter dams (install) (type 1) (506-7001) | LF | 100 | $50.00 | $50.00 | $55.00 | $45.00 | $47.46 | $10.00 | $42.00 |
| 41 | Rock filter dams (remove) (506-7011) | LF | 100 | $10.00 | $15.00 | $15.00 | $12.00 | $12.66 | $1.00 | $10.00 |
| 42 | Sandbags for erosion control (506-7035) | EACH | 130 | $5.00 | $8.00 | $5.00 | $8.00 | $8.44 | $6.00 | $10.00 |
| 43 | Temporary sediment control fence (install) (506-7039) | LF | 1,745 | $5.00 | $4.50 | $5.00 | $5.15 | $4.22 | $3.00 | $5.25 |
| 44 | Temporary sediment control fence (remove) (506-7041) | LF | 1,745 | $2.00 | $2.00 | $1.00 | $1.00 | $1.05 | $1.00 | $1.00 |
| 45 | Driveways (ACP) (530-7010) | SY | 104 | $75.00 | $52.00 | $80.00 | $49.50 | $75.00 | $105.00 | |
| 46 | Metal W-beam guard fence (timber post) (540-7001) | LF | 150 | $35.00 | $28.00 | $50.00 | $29.00 | $30.01 | $38.00 | $35.70 |
| 47 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,000.00 | $22.00 | $2,650.00 | $2,550.00 | $2,163.94 | $2,165.00 | $1,850.00 |
| 48 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,000.00 | $4,630.00 | $3,265.00 | $3,480.43 | $3,452.00 | $3,465.00 |
| 49 | Crash cushion attenuator (install)(R)(N)(TL2) (545-7009) | EACH | 2 | $25,000 | $21,000 | $23,900 | $21,213 | $20,474 | $20,685 | |
| 50 | Wire fence (type A) (552-7001) | LF | 538 | $25.00 | $20.00 | $25.00 | $65.00 | $63.96 | $44.00 | $26.25 |
| 51 | Wire fence (special) (552-7005) | LF | 50 | $30.00 | $30.00 | $35.00 | $91.00 | $96.68 | $126.00 | $157.50 |
| 52 | Wire fence (water gap) (552-7010) | LF | 100 | $100.00 | $30.00 | $50.00 | $40.00 | $42.64 | $120.00 | $78.75 |
| 53 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 2 | $450.00 | $300.00 | $750.00 | $635.00 | $676.90 | $1,000.00 | $605.00 |
| 54 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 1 | $600.00 | $400.00 | $500.00 | $480.00 | $511.67 | $800.00 | $555.00 |
| 55 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $200.00 | $100.00 | $115.00 | $110.00 | $117.26 | $100.00 | $110.00 |
| 56 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $45.00 | $30.00 | $45.00 | $24.50 | $26.12 | $6.00 | $18.00 |
| 57 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $45.00 | $30.00 | $40.00 | $30.00 | $31.98 | $13.00 | $29.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.