TxDOT contract A00194530 bid tabulation
Bridge Replacement, FM 2610 (FM 2610 to At Menard Creek.). Let by Texas DOT on September 4, 2025, Polk, Lufkin District. 7 bids received; low bid $2,472,737 by THK Construction LLC, -1.3% against the engineer's estimate of $2,506,060.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 65
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $2,472,737 | Low | -1.0% |
| 2 | Hodges and Son Construction Company, Inc. | $2,486,932 | +1.0% | -1.0% |
| 3 | Skyline Bridge LLC | $2,654,652 | +7.0% | +6.0% |
| 4 | Lakey, Inc. | $2,843,814 | +15% | +13% |
| 5 | C. E. Barker, LTD. | $3,074,907 | +24% | +23% |
| 6 | East Texas Bridge, Inc. | $3,094,935 | +25% | +23% |
| 7 | James Construction Group, LLC | $3,834,895 | +55% | +53% |
Engineer's estimate: $2,506,060.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Hodges and Son Construction Company, Inc. | 3. Skyline Bridge LLC | 4. Lakey, Inc. | 5. C. E. Barker, LTD. | 6. East Texas Bridge, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 10.60 | $3,000.00 | $1,500.00 | $4,200.00 | $3,000.00 | $3,650.00 | $29,800 | $9,500.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 2,359 | $18.00 | $18.00 | $20.00 | $18.00 | $23.80 | $34.34 | $25.00 |
| 3 | Embankment (final)(DC)(type C) (132-7006) | CY | 606 | $30.00 | $20.00 | $30.00 | $40.00 | $26.00 | $24.68 | $30.00 |
| 4 | Blading (150-7001) | STA | 7 | $150.00 | $100.00 | $100.00 | $200.00 | $150.00 | $563.35 | $400.00 |
| 5 | Broadcast seed (temporary_warm) (164-7005) | SY | 2,720 | $1.00 | $0.33 | $0.40 | $0.50 | $1.00 | $1.07 | $1.65 |
| 6 | Broadcast seed (temporary_cool) (164-7006) | SY | 2,720 | $1.00 | $0.37 | $0.40 | $0.50 | $1.00 | $1.07 | $1.65 |
| 7 | Bond fiber MTRX seed (permanent)(rural)(clay) (164-7083) | SY | 5,177 | $1.00 | $0.61 | $0.75 | $0.75 | $6.00 | $1.07 | $1.65 |
| 8 | Vegetative watering (168-7001) | TGL | 207.10 | $20.00 | $5.00 | $1.00 | $1.00 | $34.50 | $112.67 | $25.00 |
| 9 | Soil ret BLKT(SL_steep_clay_short) (169-7005) | SY | 1,582 | $5.00 | $1.56 | $2.00 | $2.00 | $37.70 | $5.37 | $3.25 |
| 10 | Sprinkling (dust control) (204-7001) | TGL | 26 | $25.00 | $10.00 | $20.00 | $10.00 | $1.00 | $112.67 | $45.00 |
| 11 | Proof rolling (216-7001) | HR | 2 | $150.00 | $100.00 | $200.00 | $100.00 | $1,000.00 | $563.35 | $200.00 |
| 12 | FL BS (roadway del) (type D GR 3) (247-7210) | TON | 1,176 | $75.00 | $55.00 | $70.00 | $80.00 | $80.00 | $53.65 | $85.00 |
| 13 | Cement (275-7001) | TON | 48 | $300.00 | $350.00 | $325.00 | $300.00 | $262.50 | $321.91 | $350.00 |
| 14 | Cement TRT (existing material & new base)(12") (275-7009) | SY | 2,589 | $5.00 | $9.00 | $8.00 | $26.00 | $2.75 | $17.71 | $8.00 |
| 15 | Asphalt (RC-250) (316-7032) | TON | 2.75 | $3,000.00 | $5,000.00 | $3,900.00 | $4,000.00 | $28,080 | $6,438.24 | $2,500.00 |
| 16 | Asphalt (AC-15P or CRS-2P) (316-7088) | TON | 5.43 | $1,800.00 | $4,500.00 | $3,400.00 | $4,000.00 | $1,110.00 | $6,438.24 | $2,500.00 |
| 17 | Aggregate (type E or L, GR-5) (316-7254) | CY | 20 | $1,100.00 | $1,000.00 | $650.00 | $2,000.00 | $1,500.00 | $321.91 | $350.00 |
| 18 | Aggregate (type E or L, PE or PL GR 4) (sac-A) (316-7274) | CY | 26 | $1,050.00 | $1,000.00 | $550.00 | $2,500.00 | $1,200.00 | $32.19 | $350.00 |
| 19 | SP mixes SP-C PG70-22 (344-7019) | TON | 285 | $190.00 | $275.00 | $300.00 | $400.00 | $150.00 | $236.07 | $275.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 193 | $260.00 | $280.00 | $275.00 | $325.00 | $350.00 | $182.42 | $315.00 |
| 21 | Drilled shaft (18 in) (416-7002) | LF | 200 | $200.00 | $145.80 | $95.00 | $175.00 | $194.50 | $157.74 | $135.00 |
| 22 | Drilled shaft (36 in) (416-7006) | LF | 540 | $380.00 | $258.00 | $205.00 | $260.00 | $382.12 | $412.05 | $275.00 |
| 23 | Drilled shaft (42 in) (416-7007) | LF | 585 | $400.00 | $393.60 | $330.00 | $325.00 | $413.00 | $529.01 | $440.00 |
| 24 | Class C concrete (abutment) (420-7012) | CY | 62.40 | $1,300.00 | $1,100.00 | $1,000.00 | $1,250.00 | $1,362.50 | $960.97 | $1,600.00 |
| 25 | Class C concrete (cap) (420-7022) | CY | 56.40 | $1,500.00 | $1,500.00 | $1,100.00 | $1,750.00 | $1,540.00 | $1,047.80 | $1,600.00 |
| 26 | Class C concrete (column) (420-7038) | CY | 35.90 | $2,000.00 | $1,500.00 | $1,200.00 | $1,900.00 | $1,500.00 | $1,047.80 | $1,800.00 |
| 27 | Reinforced concrete slab (422-7001) | SF | 12,960 | $20.00 | $21.00 | $28.00 | $27.00 | $31.00 | $26.05 | $37.00 |
| 28 | Approach slab (422-7013) | CY | 81.30 | $800.00 | $750.00 | $750.00 | $850.00 | $750.00 | $882.68 | $1,050.00 |
| 29 | Prestressed concrete girder (TX40) (425-7003) | LF | 1,789.62 | $225.00 | $245.81 | $265.00 | $215.00 | $197.00 | $214.27 | $235.00 |
| 30 | Riprap (concrete)(4 in) (432-7001) | CY | 19.30 | $600.00 | $750.00 | $800.00 | $1,000.00 | $700.00 | $654.55 | $1,000.00 |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 45 | $600.00 | $750.00 | $700.00 | $750.05 | $700.00 | $654.55 | $825.00 |
| 32 | Riprap (stone protection)(24 in) (432-7045) | CY | 126 | $150.00 | $170.00 | $225.00 | $250.00 | $235.00 | $249.48 | $255.00 |
| 33 | Rail (type T223) (450-7008) | LF | 792 | $160.00 | $150.00 | $130.00 | $175.00 | $150.00 | $217.36 | $195.00 |
| 34 | Armor joint (sealed) (454-7003) | LF | 111 | $200.00 | $150.00 | $200.00 | $125.00 | $200.00 | $96.57 | $125.00 |
| 35 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $50,000 | $102,000 | $80,000 | $30,000 | $127,725 | $89,599 | $150,000 |
| 36 | Mobilization (500-7001) | LS | 1 | $230,000 | $230,000 | $230,000 | $200,000 | $113,500 | $285,210 | $275,000 |
| 37 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $3,500.00 | $994.56 | $3,000.00 | $2,200.00 | $17,500 | $2,780.54 | $5,000.00 |
| 38 | Portable changeable message sign (503-7002) | EACH | 2 | $20,000 | $20,000 | $18,000 | $18,000 | $15,000 | $21,461 | $25,000 |
| 39 | TMA (stationary) (505-7001) | DAY | 10 | $300.00 | $300.00 | $300.00 | $300.00 | $205.00 | $1,073.04 | $350.00 |
| 40 | TMA (mobile operation) (505-7003) | DAY | 4 | $300.00 | $400.00 | $300.00 | $50.00 | $262.50 | $804.78 | $350.00 |
| 41 | Rock filter dams (install) (type 2) (506-7002) | LF | 45 | $40.00 | $66.96 | $1.00 | $50.00 | $54.30 | $53.65 | $70.00 |
| 42 | Rock filter dams (remove) (506-7011) | LF | 45 | $15.00 | $19.44 | $1.00 | $5.00 | $17.03 | $21.46 | $25.00 |
| 43 | Construction exits (install) (type 1) (506-7020) | SY | 178 | $40.00 | $75.60 | $1.00 | $10.00 | $34.00 | $32.19 | $50.00 |
| 44 | Construction exits (remove) (506-7024) | SY | 178 | $15.00 | $28.08 | $1.00 | $1.00 | $12.66 | $10.73 | $25.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 1,700 | $5.00 | $4.32 | $1.00 | $3.75 | $4.57 | $5.37 | $5.50 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 1,700 | $1.00 | $1.08 | $1.00 | $1.50 | $1.25 | $2.15 | $1.25 |
| 47 | Metal W-beam guard fence (steel post) (540-7002) | LF | 650 | $40.00 | $30.82 | $30.00 | $34.00 | $33.00 | $39.70 | $30.00 |
| 48 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $1,800.00 | $2,079.00 | $2,000.00 | $2,400.00 | $2,370.00 | $2,251.24 | $2,200.00 |
| 49 | Remove metal beam guard fence (542-7001) | LF | 650 | $4.00 | $2.50 | $1.00 | $5.00 | $3.00 | $3.22 | $3.00 |
| 50 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,348.00 | $3,500.00 | $3,700.00 | $3,331.54 | $3,433.73 | $3,500.00 |
| 51 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $250.00 | $250.00 | $500.00 | $500.00 | $300.00 | $536.52 | $300.00 |
| 52 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 2 | $500.00 | $1,500.00 | $2,000.00 | $1,500.00 | $650.00 | $583.65 | $1,250.00 |
| 53 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 18 | $30.00 | $48.60 | $45.00 | $50.00 | $25.00 | $21.46 | $50.00 |
| 54 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 14 | $40.00 | $54.00 | $50.00 | $50.00 | $35.00 | $37.56 | $60.00 |
| 55 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 2,490 | $1.00 | $0.92 | $1.50 | $2.00 | $0.44 | $0.91 | $1.65 |
| 56 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 2,490 | $1.00 | $0.92 | $1.50 | $2.00 | $0.41 | $0.91 | $1.65 |
| 57 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 561 | $2.00 | $4.26 | $3.00 | $3.75 | $2.50 | $2.41 | $3.30 |
| 58 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 125 | $3.00 | $2.00 | $3.00 | $2.00 | $1.22 | $5.37 | $3.00 |
| 59 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 125 | $3.00 | $2.00 | $3.00 | $2.00 | $1.22 | $5.37 | $3.00 |
| 60 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 2,090 | $2.75 | $2.00 | $4.00 | $5.00 | $0.93 | $1.99 | $4.45 |
| 61 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 2,090 | $2.75 | $2.00 | $4.00 | $5.00 | $1.00 | $1.99 | $4.45 |
| 62 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 210 | $5.00 | $13.77 | $15.00 | $20.00 | $4.20 | $13.68 | $16.50 |
| 63 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 27 | $10.00 | $10.80 | $10.00 | $15.00 | $5.50 | $10.73 | $11.00 |
| 64 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,440 | $0.15 | $0.11 | $1.00 | $1.50 | $0.10 | $0.11 | $1.15 |
| 65 | Bonding course (3007-7001) | GAL | 129.50 | $6.00 | $15.00 | $10.00 | $30.00 | $22.75 | $10.73 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.